09/4074N-Proposed Manufacturing Building on the Former B Block Site, Including Ancillary Infrastructure Comprising Site Access Road, Security Gatehouse, Car Parking and an Internal Firing Range, BAE Systems, Land Systems Munitions, Radway G

Approved Planning 1 paper

Strategic Planning Board approved this item on Wednesday 10 February 2010. Below is the council's own wording, with the papers it was decided on.

Item173

Resolved

RESOLVED That the application be approved subject to the following conditions:- 1.Time Limits: Reserved Matters 2.Development in accordance with approved plans 3.Travel Plan to be submitted and implemented 4.Development to be undertaken in accordance with submitted site management scheme 5.Management scheme to be submitted for the wild grass land area 6.Unless agreed in writing with the Local Planning Authority, no felling of the trees to the north of the rile range as defined in the Design & Access Statement 7.Noise attenuation scheme for the proposals relating to the indoor firing range 8. Construction management plan – to include routing for construction traffic In addition it was agreed that that an informative be added to the decision notice to include the following wording:- The applicants are advised that goods vehicles arriving to and leaving the BAE facility subject to this application, should be directed to the main highway network principally the A5078 south of the site entrance. The A5077 Butterton Lane leading to Crewe should only be used in exceptional circumstances due to the narrow width of the road and its unsuitability for frequent use by goods vehicles.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Strategic Planning Board

Application No: 09/4074N Location: BAE Systems, Land Systems Munitions, Radway Green, Alsager, Near Crewe, CW2 5PJ Proposal: Proposed Manufacturing Building On The Former B Block Site, Including Ancillary Infrastructure Comprising Site Access Road, Security Gatehouse, Car Parking And An Internal Firing Range. Applicant: [name removed], Bae Systems Properties Ltd Application Type: Reserved Matters Ward: Doddington, Crewe & Nantwich and Alsager, Congleton Registration Date: Earliest Determination Date: Expiry Date: Date report Prepared 27 January 2010 Constraints: Site allocated in Congleton Local Plan First Review as Royal Ordnance Factory

SUMMARY RECOMMENDATION: Approve Subject to Conditions

MAIN ISSUES: Impact on the character and appearance of the area. Scale and mass of the building. Development on contaminated land.

REASON FOR REPORT The application is included on the agenda of the Strategic Planning Committee as the scheme exceeds 1,000 m2 floor area and is therefore a major development.

DESCRIPTION OF SITE AND CONTEXT The site lies to the south of Alsager and forms part of the larger BAE complex at Radway Green. The site is identified in the Congleton Borough Local Plan under Policy E9 'Royal Ordnance Factory'.

The application site is located within an established manufacturing and assembly facility. In addition, there is an existing industrial estate located immediately west of the site.

The Royal Ordnance Factory at Radway Green was developed in 1939. The factory was established to produce small arms ammunition (SAA) and cartridges for HM Forces. Industrial production started at the site in 1940, although the site facilities were not fully completed until 1942.

The site originally comprised a number of buildings with production being based within four centrally located large open plan buildings, A, B, C and D blocks. In addition to the main production buildings, a number of firing ranges were constructed on the southern side of the site, along with infrastructure, including gas works, a boiler house, administrative units and waste treatment facilities. To the east of the site, a number of bulk storage magazines were also constructed to store explosive material and finished munitions. To the north of the site, a substantial rail marshalling yard infrastructure yard was built to support site operations.

A line of Goat Willow lies to the south of the B block building and beyond the open air firing range lies open countryside.

At the Strategic Planning Board Meeting on 19 August 2009, outline approval was granted for the redevelopment of the manufacturing building subject to conditions (ref. 09/1285C). This current applications seeks approval for the matters that were reserved as part of the earlier scheme with the exception of the details for the replacement firing range. This element of the scheme will be subject to a separate application at a later date.

DETAILS OF PROPOSAL As indicated, the application is for the approval of a number of reserved matters and seeks permission for the development of a manufacturing building, associated site access road, a security gatehouse, car parking, landscaping and ancillary infrastructure.

As set out in the outline application, the general vehicular access is gained from Number 1 Road North, which runs directly from Radway Green Road (B5078). The B5078 connects directly with Junction 16 of the M6, which is located approximately 1.5km south of the site.

RELEVANT HISTORY Application P08/0131 was granted consent by Crewe & Nantwich Borough Council for the redevelopment of part of the adjoining employment site in 2008. This scheme was for the construction of 41 new small units for B1, B1(c), B2 and B8 uses.

Prior to the submission of the outline application, the applicants submitted a request for a screening and scoping opinion under Regulation 10 (2) and 10 (5) of the Town and County Planning (Environmental Impact Assessment) (England and Wales) Regulations 1999.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09/4074N-Proposed Manufacturing Building on the Former B Block Site, Including Ancillary Infrastructure Comprising Site Access Road, Security Gatehouse, Car Parking and an Internal Firing Range, BAE Systems, Land Systems Munitions, Radway Green, Alsager, Near Crewe for Mr K Mellis, Bae Systems PropeMinutes 175 KB DownloadRead as text

At this meeting

Whole meeting

More from Cheshire East Strategic Planning Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 22 July 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Sep 2026 25/1573/FUL - Full planning application for a residential development including associated access, infrastructure and landscaping. Land off Cumber Lane, WilmslowThat application 25/1573/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 3-year ti... Approved Open
16 Sep 2026 25/2071/FUL - Full planning application for a residential development and the provision of associated access and infrastructure works including roads, drainage infrastructure, car parking, public open space and landscaping. Land at Dean Row Road, WilmslowThat application 25/2071/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 2-year ti... Approved Open
16 Sep 2026 National Scheme of DelegationThat the Strategic Planning Board Noted the changes introduced by the for Planning Functions that will be implemented... Noted Open
22 Jul 2026 Minutes of the Previous MeetingThat the minutes of the meetings held on 27 May 2026 and 9 June 2026 be approved as correct records. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies