RESOLVED 1. That performance be reported to the Board in a tabular format as shown in table 2 of the report on a quarterly basis. 2. That Officers liaise with and provide updates to the Portfolio Holder and Executive Steering Group for Transformation Project. 3. That the clarification to paragraph 4.6 of the report as requested by the Development Control Manager be noted and approved.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
1.1To provide an update on work being carried out jointly between Development Management and Legal Services on improving performance in relation to Planning Obligations and Lawful Development Certificates. Table 1 details the programme of improvement work and current status. Table 2 provides example of proposed format for reporting progress and completion of work.
Background
2.1At the meeting of the Strategic Planning Board on 23 December 2009, the overall Performance Management Framework for the Development Management service, which set out the mechanism for reporting on performance together with specific reports regarding Enforcement and Appeals, was approved by members.
2.2This report deals with the most appropriate feedback to Members on elements of the service with an input from Legal Services in particular in relation to Section 106 Agreements and Unilateral Undertakings, but also with reference to work undertaken on Lawful Development Certificates.
3.0Current Position
3.1Members will be aware of the ongoing projects which form part of the transformation of the Development Management Service and the associated review of working practices and procedures from the legacy authorities.
3.2The Performance Management Framework report of 23 December 2009, referred to work which was being carried out to establish a full data set of outstanding Obligations awaiting completion. That exercise established that at that time there were approximately 78 currently outstanding Section 106 Agreements.
3.3Maintenance of the list is work in progress, and the list will be refined and updated on a regular basis as cases move through the process. Each case has also been allocated a priority, and these figures will also be regularly reviewed and if necessary amended.
3.4In order to improve efficiency in the processing of applications including lawful development certificates and those requiring S106 planning obligations, an Improvement Plan has been commenced and a summary is set out in Table 1. This will contribute towards compliance with target deadlines and establish best practice for future work.
4.0“Finally Disposed of”
4.1As well as monitoring and prioritising current applications, there is an expectation that planning applications in general should be determined in a timely fashion, as no purpose is served by applications remaining “live” on the register when there is no prospect of the development proceeding, or of the planning obligation being entered into to secure those matters which are considered necessary to mitigate the impact of the development or other outstanding issues resolved.
4.2There may be a number of reasons why a development does not proceed, not all of which are in the applicant’s control, nor indeed within the control of the planning authority. However, having matters outstanding on the register for a protracted period of time can also lead to uncertainty.
4.3The General Development Procedure Order 1995, as amended, provides detail about how planning applications are to be processed, and time periods for decisions on both major and non-major applications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.