Resolved
RESOLVED That the 2010-2014 be approved.
Performance and Capacity approved this item on Monday 31 January 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the 2010-2014 be approved.
2.1That the Portfolio Holder approve the Local Development Scheme 2010- 2014.
3.0Reasons for Recommendation(s)
3.1To ensure that the Council has an approved three year programme for the preparation of the various documents that will make up the Local Development Framework.
4.1All
5.0Local Ward Members
5.1All
6.0Policy Implications
6.1The Cheshire East Local Development Framework will set out the vision, objectives, spatial strategy and policies for the development of Cheshire East (outside the National Park) to 2030. It will interpret national planning policies within the context of Cheshire East Borough and will aim to ensure that the future development of the Borough is planned in a sustainable manner. It will be developed in co-operation with other adjacent local authorities to ensure that it contributes to the strategy for the future development of the sub-region. 6.2 The Local Development Framework will take into account other strategies and plans produced by the Council and its Local Strategic Partners in order to present a shared vision and strategy to ensure consistency in programme delivery. It will deliver the spatial aspects of the Cheshire East Sustainable Community Strategy, “Ambition for All”. . 7.0 Financial Implications
7.1The costs of preparing the various documents will be met from current and future Spatial Planning budgets. The Local Development Scheme has taken into account the potential reduction of Spatial Planning staffing and revenue budgets from April 2011.
8.1Local authorities are required by Section 19 of the Planning and Compulsory Purchase Act 2004 to prepare documents to form their Local Development Framework in accordance with their Local Development Scheme.
8.2Section 15 of the Planning and Compulsory Purchase Act 2004 sets out the roles of the local planning authority and the Secretary of State in relation to an authority's Local Development Scheme. Every local planning authority must prepare and maintain a local development scheme specifying the documents that will be local development documents, their subject matter and area and the timetable for their preparation and revision. The local planning authority must submit their local development scheme to the Secretary of State who can direct changes to the scheme as he thinks appropriate. PPS12 sets out guidance on the preparation of Local Development Schemes.
8.3Section 15 requires Local Planning Authorities to revise their Local Development Schemes "at such time as they consider appropriate". This Council’s current Scheme was produced in February 2009, several changes to its content and timetable need to be made, a revised Scheme must therefore be approved and published.
9.0Risk Management Implications
9.1The Local Development Schemes sets out the risks associated with the preparation of the Local Development Framework. Two new risks have arisen since the preparation of the first Local Development Scheme:
• Uncertainties about the proposed revisions to the plan making process announced by the Coalition Government • Uncertainties about the possible reduction in Spatial Planning staffing and revenue budgets from April 2011.
10.0Background and Options
10.1The Local Development Scheme sets out a programme and timetable for the preparation of documents for the Cheshire East Local Development Framework. The first Cheshire East Local Development Scheme was approved in February 2009 and included an extensive list of Development Plan Documents.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local Development SchemeMinutes | 82 KB | DownloadRead as text |
Follow Performance and Capacity at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Apr 2012 | Community GrantsRESOLVED That the listed in the Appendix to the report be awarded, declined or deferred as indicated. | Deferred | Open |
| 30 Apr 2012 | Cheshire East Local Development Scheme 2012 -14RESOLVED That the Local Development Scheme 2012- 2014 be approved. | Approved | Open |
| 16 Apr 2012 | Twinning - Request for Grants by Crewe and Nantwich Twinning Association and the Twinning Association of PoyntonRESOLVED That (1) a grant of £2,500 be awarded to the Crewe and Nantwich Twinning Association (CANTA); (2) a grant of... | Decided | Open |
| 20 Feb 2012 | Minerals Issues Discussion PaperThat the Cabinet Member for Performance and Capacity approve the for purposes of consultation on the development of m... | Approved | Open |
| 31 Jan 2011 | Cheshire East Local Development Framework Annual Monitoring Report 2009/10RESOLVED That the Annual Monitoring Report be approved for submission to the Secretary of State to comply with the re... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.