09/2806W-Mere Farm Quarry, Chelford Road, Nether Alderley, Macclesfield, Cheshire, Interim Extension to Sand Workings at Mere Farm Quarry for Hanson Quarry Products Europe Ltd
ApprovedPlanning1 paper
Strategic Planning Board approved this item on Wednesday 20 April 2011. Below is the council's own wording, with the papers it was decided on.
RESOLVED – That the application be APPROVED subject to entering into a deed of variation to update the existing Section 106 agreement and entering into further agreement to secure an additional 10 year aftercare scheme beyond the five years required by condition and the following conditions: 1. The replication where relevant of the existing 68 conditions attached to the current permission for the quarry that deal with: Duration of working Hours of working Traffic Method of working Plant and machinery Noise Dust Drainage Pollution control Archaeology Site maintenance Soil stripping and storage Restoration Aftercare Plus additional conditions: 2. No working within 30 metres of badger setts 3. Additional badger survey in advance of working 4. Protection of breeding birds 5. Provision of barn owl boxes 6. Submission of detailed landscaping plan 7. Submission of a habitat and management plan 8. Submission of a proposed scheme for enhanced public access in the vicinity of the extension 9. Submission of details of a Liaison Committee to be agreed by LPA, which shall operate prior to the commencement of development until the Quarry is fully restored, unless otherwise agreed Note: Following consideration of this item, Councillors A Arnold and C Thorley left the meeting and did not return.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Planning Reference No: 09/2806W Application Address: Mere Farm Quarry, Chelford Road, Nether Alderley. Proposal: Extension to sand workings Applicant: Hanson Quarry Products Europe Ltd, Hanson House, 14 Castle Hill, Maidenhead, Berkshire, SL6 4JJ Application Type: Major mineral application Grid Reference: 382310 375011 Ward: Bucklow Alderley Expiry Dated: 13 Dec 2009 Constraints: Manchester Airport Safeguarding, Wind Turbine consultation area, Green Belt
SUMMARY RECOMMENDATION: Approve subject to conditions and amended Section 106 legal agreement
MAIN ISSUES: Validity of application Need for sand extraction Impact on hydrology Loss of agricultural land Protected species Ecological enhancement and restoration
1. REASON FOR REFERRAL
This application was deferred from Strategic Planning Board on 5th January 2011 for the following reasons:
(a) For more detailed information regarding proposed mitigation and restoration measures, plus public access to the area after the quarry ceases working; and
(b) Further consideration to the establishment and operation of a Liaison Committee on the site
2. DESCRIPTION OF SITE AND CONTEXT
The site is located approximately a kilometre east of Chelford, to the north of the A537 and east of the A535, and 8km west of Macclesfield. Access to the quarry is by a dedicated tarmac road with deceleration and acceleration lanes directly off the A537. This access road connects with the processing plant, stockpile area, site offices and car park. The proposed site is a 6 ha extension to the north west of the existing quarry. This land is currently improved pastureland surrounded by hedges and fencing with occasional mature trees. The land has been classified as grade 2 and 3a agricultural land which is considered best and most versatile.
Immediately to the south of the extension lies the active excavation of the existing quarry with previously quarried areas to the south east now consisting of a large lake. The processing plant, settling lagoons, stockpiles and offices lie approximately a kilometre east of the proposed extension. Beyond a 60 metre wide strip of agricultural land to the west of the site lies the A535.
The closest properties on the A535 are approximately 350m to the south west, whilst Roadside Farm lies 300m to the north with the land falling to Pedley Brook a further 450m north. To the north east of the site and north of the quarry are a number of isolated properties all gaining access off Bollington Lane, with most set within existing woodland. The nearest of these properties to the site is Sandlewood Farm which lies approximately 250m to the east. Public footpath Chelford No 2 has been diverted to the north of the existing excavation and currently runs through the proposed site in an east west direction.
Existing screen mounding and tree planting ensures that the majority of active workings or site infrastructure are not visible from either the west (A535) or the south (A537) and existing woodland to the north and east also aid to screen activity.
The quarry has generally been worked from east to west exploiting a sand body that has varied in thickness between 10 and 25m and consists of two deposits separated by a clay band varying from 2 to 4 metres thick. Soils and clay overburden tends to vary in depth between 0.4 to 1.5m. Historic extraction rates for the sand vary between 250,000 and 280,000 tonnes a year, although this rate has dropped in recent years due to the downturn in the economy. The maximum production is equivalent to 42 HGV’s a day.
From 1988, the local water table has been reduced by continued pumping to enable sand to be removed down to 60m AOD although recent depths are between 63 and 65m AOD, equal to a working depth of less than 20m. Ground levels outside the quarry vary from 90m AOD to the east of the quarry to 78m to the west.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
09/2806W-Mere Farm Quarry, Chelford Road, Nether Alderley, Macclesfield, Cheshire, Interim Extension to Sand Workings at Mere Farm Quarry for Hanson Quarry Products Europe LtdMinutes
14309/2806W-Mere Farm Quarry, Chelford Road, Nether Alderley, Macclesfield, Cheshire, Interim Extension to Sand Workings at Mere Farm Quarry for Hanson Quarry Products Europe LtdThis decision
09/2806W-Mere Farm Quarry, Chelford Road, Nether Alderley, Macclesfield, Cheshire, Interim Extension to Sand Workings at Mere Farm Quarry for Hanson Quarry Products Europe LtdThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.