RESOLVED That (1) a special meeting of the Committee be held before the end of the Council year to consider the budget expenditure on the Lyme Green site, the arrangements for the special meeting to be determined in consultation with the Chairman; (2) the specialist sub-groups appointed by the Committee to consider specific aspects of the Committee’s work be asked to identify items for inclusion on the work plan for consideration at the Committee’s next ordinary meeting; and (3) the issue of risk management be included as a standard item for all future meetings of the Committee.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Annual Audit Letter The Committee received and considered the content of the Audit Commission’s Annual Audit Letter. This outlined the findings of the audit of the Council’s financial statements and an assessment of the Council’s arrangements to achieve value for money in the use of resources. It also identified current and future challenges, and future audit arrangements.
Opinion Plan The Committee noted the content of the Audit Commission’s Audit Plan which identified the work that is planned by the External Auditor to give an opinion on the Council’s Financial Statements for the financial year 2011/12.
Audit Committee The Committee considered a report on the progress of Update the Audit Commission in delivering their responsibilities as external auditors. The report included an update on the externalisation of the Audit Practice and also highlighted key emerging national issues and developments
2011-12 Closure of The Committee noted the progress on the preparations Accounts – Progress for producing the Statement of Accounts for 2011-12. Report
Annual Governance The Committee noted the progress against the Statement 2011/12 2010/11 AGS Action Plan and endorsed the process AGS Action Plan for the production of the 2011/12 Annual Governance Statement.
Freedom of The Committee considered a report which detailed how Information and Data the Council fulfils its obligations under the Data Protection Protection Act 1998, Freedom of Information Act (2000) and the Environmental Information Regulations (2004) and the processes that the Council has in place to comply with these legislative requirements were noted.
Compliance with The Committee noted the report detailing the basis for International Auditing the written response to the Audit Commission Standards regarding management arrangements for identifying and reporting risk of fraud and complying with relevant laws and regulations Appendix A
Committee Notes Date/Agenda Item
Internal Audit Update The Committee considered a report on progress against the Internal Audit Plan 2011/12 and resolved that the report be noted and the approach identified to achieve adequate audit coverage in the remainder of 2011/12 be endorsed.
Risk Management The Committee considered a report summarising the Update Key Corporate Risks and risk management work undertaken since the previous report and resolved that in future the Risk Assessment paragraph in all Committee reports should include the risk matrix score.
Work Plan The Committee noted the Work Plan and resolved that a report on the budget expenditure for the waste site at Lyme Green be added to the Work Plan for the next meeting.
27 March 2012
Grants Report to External Auditors are required to report annually on those charged with the issues, amendments and qualifications arising Governance from certification work of grant claims and returns. This report is important because it gives feedback on how effectively the Authority is managing the grants and subsidies it receives and administers.
Internal Audit Plan for The Head of Internal Audit must prepare a risk-based 2012/13 audit plan designed to implement the audit strategy that is fixed for a period of no longer than one year. The Committee is responsible for approving (but not directing) the plan.
Audit Committee Self The Committee will be asked to agree the self- Assessment assessment – using the CIPFA document “measuring the effectiveness of the Audit Committee”.
Risk Management The Risk Management function will report on whether Update best practice is being followed in the management of risk and how new risks are identified and existing risks are changing.
Business Continuity The Committee will be made aware of how the Update authority manages its own contingency and business recovery plans. Appendix A
Committee Notes Date/Agenda Item
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.