Cheshire East Council
Prosperity and Economic Regeneration, Tuesday 5 March 2013 at 10.00am

Under Bridge Agreement with Network Rail, and Network Rail Professional Fees Estimate in relation to the Crewe Green Link Road (South)

Agreed Committee 4 papers

Prosperity and Economic Regeneration agreed this item on Tuesday 5 March 2013. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED That (1) the Council enter into a formal Underbridge Agreement with Network Rail on the terms and conditions set out in Appendix 1 to the report; (2) the estimate of Network Rail’s professional fees associated with the development of the scheme, including those incurred before the DfT Final Funding Approval stage, be accepted and formal approval of such be provided to Network Rail; and (3) any further amendments or modifications of the terms of the agreement or scale of the estimated costs to be incurred prior to final exchange of legal contract be delegated to the Head of Highways and Transport in consultation with the Council’s Monitoring Officer and Chief Financial Officer, and the Portfolio Holder for Prosperity and Economic Regeneration .
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Prosperity and Economic Regeneration

Dated

NETWORK RAIL INFRASTRUCTURE LIMITED

- and –

CHESHIRE EAST BOROUGHCOUNCIL

TWO PARTY UNDERBRIDGE AGREEMENT relating to a new structure under the railway on KCS1 at 7m990yds CONTENTS

1. DEFINITIONS AND INTERPRETATION ........................................................................................... 1

2. DUTIES AND OBLIGATIONS OF THE COUNCIL ............................................................................ 5

3. DUTIES AND RIGHTS OF NETWORK RAIL .................................................................................. 17

4. SUSPENSION .................................................................................................................................. 20

5. INDEMNITY AND LIMIT OF LIABILITY ........................................................................................... 21

6. MISCELLANEOUS ........................................................................................................................... 22

Schedule 1 - Particulars .............................................................................................................................. 27

Schedule 2 - Payment................................................................................................................................. 28

Schedule 3 - Network Rail's Services ......................................................................................................... 32

Schedule 4 - Notice Details......................................................................................................................... 33

Schedule 5 - Plan of Land in the Ownership of Network Rail ..................................................................... 35

Schedule 6 – Escalation Procedure............................................................................................................ 36 THIS AGREEMENT is made the day of 2013

BETWEEN

(1) NETWORK RAIL INFRASTRUCTURE LIMITED ("Network Rail") registered in England and Wales as Company No. 2904587 and having its registered office at Kings Place, 40 Melton Street, London NW1 2EE

and

(2) CHESHIRE EAST BOROUGH COUNCIL ("the Council") of Council Offices Westfields Middlewich Road Sandbach Cheshire CW11 1HZ ]

WHEREAS

(1) The Council wishes to design and construct a new Road which crosses under the Railway Infrastructure on KCS1 at 7m990yds.

(2) The Council wishes to design and construct the New Structure to be known as 21C to carry the Road under the Railway Infrastructure. It is intended that the Council will adopt the Road.

(3) Network Rail is prepared to permit the Council to design and construct the New Structure and Network Rail is prepared to own and maintain the New Structure at the cost of the Council, subject to the terms and conditions of this Agreement, which reflects the statutory obligations and framework within which Network Rail is obliged to operate the Railway.

(4) Network Rail is prepared to dedicate its land which carries the Road to the Council for the purpose of a public highway for or in connection with the New Structure upon terms to be subject to a separate legal agreement and payment of compensation.

NOW IT IS AGREED by and between the parties hereto as follows:

1. DEFINITIONS AND INTERPRETATION

1.1In this Agreement, unless the context otherwise requires:

1.1.1 “Accepted Design” means the design for the Works accepted by Network Rail in accordance with Clause 2.2.2.13

1.1.2 “Approved Drawings” means any drawing approved by Network Rail in connection with the Works (in particular drawings submitted under clauses 2.2.2.6 and 2.2.2.13;

1.1.3 “Certificates for Design and Checking of Structures” means certificates in such format as Network Rail shall require in respect of those parts of the Rail Related Works;

1.1.4 “Certificates for Design and Checking of Temporary Works” means certificates in such format as Network Rail shall require in respect of Temporary Works;

1.1.5 “CDM Regulations” means the Construction (Design and Management) Regulations 2007;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Under Bridge Agreement: Appendix 1Minutes 250 KB DownloadRead as text
PDF
Under Bridge Agreement: Appendix 2Minutes 21 KB Download
PDF
Under Bridge Agreement: Appendix 3Minutes 20 KB Download
PDF
Under Bridge Agreement with Network Rail, and Network Rail Professional Fees Estimate in relation to the Crewe Green Link Road (South)Minutes 67 KB Download

At this meeting

Whole meeting
7Under Bridge Agreement with Network Rail, and Network Rail Professional Fees Estimate in relation to the Crewe Green Link Road (South)This decision
8Crewe Green Link Road (South) - Great Crested Newt Mitigation Habitat Lease Agreement, and Construction and EstablishmentAgreed

More from Cheshire East Prosperity and Economic Regeneration

All decisions
MeetingDecisionOutcome
15 Apr 2013 Home Energy Conservation Act Further ReportThat the approval be given to the publication of the Home Energy Conservation Act Further Report. Approved Open
15 Apr 2013 Congleton Transport Infrastructure Study Revised ObjectivesThat approval be given to the following revised scheme objectives for the Congleton transport infrastructure study: 1... Approved Open
5 Mar 2013 Crewe Green Link Road (South) - Great Crested Newt Mitigation Habitat Lease Agreement, and Construction and EstablishmentRESOLVED That (1) the Council enter into two formal short term (2 year) licence / lease agreements with two separate ... Agreed Open
7 Jan 2013 Grant Funding for Energy EfficiencyThat (1) the application submitted to the Department of Energy and Climate Change for Local Authority Funds in respec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies