RESOLVED That (1) the Council enter into two formal short term (2 year) licence / lease agreements with two separate landowners (Co-op and [name removed]) to enable the Council to access land to construct and establish mitigation habitat areas necessary to ... view the full minutes text for item 8.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
2.1That the Council enter into two formal short term (2 year) licence / lease agreements with two separate landowners (Coop, see plan1 attached and Witter, see plan 2 attached) to enable the Council to access land to construct and establish mitigation habitat areas necessary to mitigate for loss of Great Crested Newt habitat due to the construction of Crewe Green Link Road (South).
2.2The licence / lease be for 2 years or until such time as it is superseded by a subsequent long term arrangement to protect the areas in perpetuity (either by a lease of 150 years minimum term or a freehold transfer to the Council), after which time the newt relocation will be undertaken.
2.3That the construction of the ponds and habitat be undertaken by the Council’s Highway service provider to the specification as set out in the planning permissions 12/3804N and 12/3805N. 2.4 That the terms and conditions of the lease agreement and the contract for the construction of the habitat areas and any ancillary agreements necessary be delegated to the Assets Manager and Borough Solicitor in consultation with the Head of Highways and Transport.
Reasons for recommendations
3.1The construction and establishment of the Great Crested Newt mitigation habitat areas in advance of the main construction works is essential to the timely delivery of Crewe Green Link Road (South).
3.2It is crucial that construction of planting of ponds is undertaken in March 2013 in order to give these areas sufficient time to establish such that they will be ready to accept translocated newts in early 2014, in advance of the main construction works.
3.3In addition to a programme saving, there is a financial saving in the region of £0.5M in terms of the inflationary cost in delivering the main scheme approximately 6-8 months early.
3.4There is a risk that if these works are not undertaken in advance the delivery of the Crewe Green Link Road (South) scheme would be delayed sufficiently to jeopardise the agreed delivery schedule with the main funder (Department for Transport (DfT))
3.5The scope and value of the works falls within the remit and contract of the highway services contract awarded to Ringway-Jacobs (Cheshire East Highways)
3.6The actual heads of terms and conditions of the proposed short term licence / lease and contract for construction of the habitat areas is still being negotiated with the landowners, but are expected to be agreed by early March 2013.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Prosperity and Economic Regeneration at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
Grant Funding for Energy EfficiencyThat (1) the application submitted to the Department of Energy and Climate Change for Local Authority Funds in respec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.