13/4749W W T L International Ltd, Tunstall Road, Bosley, Cheshire, SK11 0PE: Installation of a 4.8MW combined heat and power plant together with the extension of an existing industrial building and the erection of external plant and machine

Approved Planning 1 paper

Strategic Planning Board approved this item on Wednesday 30 April 2014. Below is the council's own wording, with the papers it was decided on.

Item215

Resolved

RESOLVED That for the reasons set out in the report the application be approved subject to the following conditions:- 1. Standard conditions 2. Sheeting of all vehicles transporting material 3. No processing of waste wood 4. All handling/storage of wood and ash within enclosed building 5. Ash stored in enclosed hopper 6. Details of acoustic barrier 7. Acoustic barrier to be installed prior to operation of the facility 8. Noise levels 9. lighting scheme 10. Control on number of vehicle movements 11. Restricted times for HGV movements 12. Piling method statement 13. Restricted hours for use of piling 14. Construction environmental management plan 15. Restricted hours of construction activities 16. Stack design details 17. Foul and surface water drainage scheme 18. Control of fuel types 19. Scheme for control of dust 20. Flood emergency plan 21. Scheme for additional screen planting to be submitted and approved in discussion with the Parish Council In the event of any changes being needed to the wording of the Board’s decision (such as to delete, vary or add conditions/ informatives /planning obligations or reasons for approval/refusal) prior to the decision being issued, the Interim Planning and Place Shaping Manager has delegated authority to do so in consultation with the Chairman of the Strategic Planning Board, provided that the changes do not exceed the substantive nature of the Board’s decision. (Prior to consideration of the following application, Councillor Mrs Rachel Bailey left the meeting and did not return).
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Strategic Planning Board

Application No: 13/4749W

Location: W T L INTERNATIONAL LTD, TUNSTALL ROAD, BOSLEY, CHESHIRE, SK11 0PE

Proposal: Installation of a 4.8MW combined heat and power plant together with the extension of an existing industrial building and the erection of external plant and machinery including the erection of a 30m exhaust stack

Applicant: BEL (NI) Ltd.

Expiry Date: 10-Feb-2014

SUMMARY RECOMMENDATION

Approve subject to conditions

MAIN ISSUES • Sustainable waste management • Renewable energy • Alternative sites • Countryside beyond Green Belt • Noise and disruption • Air quality • Highways • Landscape and visual • Ecology • Water resources and flood risk

REASON FOR REPORT

The application has been referred to Strategic Planning Board as the proposal involves a major waste application.

DESCRIPTION OF SITE AND CONTEXT

The application site lies within an existing wood recycling facility in Bosley which is operated by Wood Treatment Limited. The site is located off Tunstall Road which connects to the A523. The site is approximately 800m south west of Bosley and approximately 6km east of Congleton and 8km south of Macclesfield.

The wood recycling facility lies on a linear strip of land which is located in a valley directly adjacent to the River Dane. It is characterised by a mixture of traditional red-bricked and modern steel framed industrial buildings with items of externally located processing plant and machinery and part of the facility is split by Tunstall Road. The site benefits from a substantial belt of natural screening provided by woodland aligning the River Dane to the west.

The surrounding land is used for agriculture and there are two farms located to the east of the site, and a smaller industrial complex to the north. Due to the topography, nearby residential properties lie at elevation with the closest being Lower Key Green farmhouse which lies approximately 80m to the east of the site. A further residential property lies approximately 100m to the north; whilst a terrace of ten dwellings lies adjacent to Tunstall Road approximately 150m to the north.

The application site covers an area of approximately 0.46ha within the wood recycling complex and is located at the southern end of the site. It comprises of the existing industrial buildings, along with part of the internal access road connecting with Tunstall Road.

The application site is located within the boundary of the Peak Park Fringe Area of Special County Value (ASCV). It also lies within 90m of the River Dane and a small portion of the access road is located within flood zone 2 and 3 on the Environment Agency flood zone maps.

RELEVANT HISTORY The site has been subject to a number of planning permissions for industrial related development which include:

• Application 11384PB - erection of steel structural building. Approved August 1977; • Application 21148P – new storage building. Approved Jan 1980; • Application 52572P - Construction of a warehouse building. Approved – April 1988; • Application 64871P - Erection of a steel framed building designed to BS449 for use as a trailer maintenance building. Approved – November 1990; • Application 75642P - production building for grinding sieving and bagging of products. Approved November 1993; • Application 79676P - replacement industrial process building plus updating of existing building. Approved January 1995;

DETAILS OF THE PROPOSAL

This is an application on behalf of Wood Treatment Limited (WTL) for the development of a 4.8MW biomass Combined Heat and Power (CHP) plant. The CHP plant would use waste wood as a fuel for the boiler/steam turbine which would generate electricity and hot water for use by the existing re-processing facility on site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
13/4749W W T L International Ltd, Tunstall Road, Bosley, Cheshire, SK11 0PE: Installation of a 4.8MW combined heat and power plant together with the extension of an existing industrial building and the erection of external plant and machinery including the erection of a 30m exhaust stack for BEL (NIMinutes 405 KB DownloadRead as text

At this meeting

Whole meeting
212Minutes of the Previous Two MeetingsApproved 213Public SpeakingNoted 21413/2389C Land South of, Old Mill Road, Sandbach: Outline Planning Application for up to 200 Residential Dwellings, Open Space and New Access off the A534/A533 Roundabout at Land South of Old Mill Road for Muller Property GroupRefused
21513/4749W W T L International Ltd, Tunstall Road, Bosley, Cheshire, SK11 0PE: Installation of a 4.8MW combined heat and power plant together with the extension of an existing industrial building and the erection of external plant and machineThis decision
21614/0683W Danes Moss Landfill Site, Congleton Road, Gawsworth, Macclesfield, Cheshire, SK11 9QP: To Develop And Operate A Temporary Waste Transfer Pad;Approved 21713/4216C Land West of Padgbury Lane, Padgbury Lane, Congleton, CW12 4LR: Outline Planning for the Development of land to the West of Padgbury Lane, Congleton, for up to 150 dwellings, community facilities and associated infrastructure for Northern Property Investment Company LtdRefused 21813/4219C Land West of Padgbury Lane, Padgbury Lane, Congleton, CW12 4LR: Outline Planning for the Development of Land to the West of Padgbury Lane, Congleton, for up to 120 dwellings, up to 180 sq.Refused 21913/5085N Land To The East Of Broughton Road, Crewe: The erection of 124 dwelling houses, including 44 affordable units, with associated highways and open amenity space, landscaping and ecological protection zone for WCE Properties LtdRefused 220Cheshire East Local Development Scheme 2014 -16Approved

More from Cheshire East Strategic Planning Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 22 July 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Sep 2026 25/1573/FUL - Full planning application for a residential development including associated access, infrastructure and landscaping. Land off Cumber Lane, WilmslowThat application 25/1573/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 3-year ti... Approved Open
16 Sep 2026 25/2071/FUL - Full planning application for a residential development and the provision of associated access and infrastructure works including roads, drainage infrastructure, car parking, public open space and landscaping. Land at Dean Row Road, WilmslowThat application 25/2071/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 2-year ti... Approved Open
16 Sep 2026 National Scheme of DelegationThat the Strategic Planning Board Noted the changes introduced by the for Planning Functions that will be implemented... Noted Open
22 Jul 2026 Minutes of the Previous MeetingThat the minutes of the meetings held on 27 May 2026 and 9 June 2026 be approved as correct records. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies