Resolved
RESOLVED That the minutes be approved as a correct record and signed by the Chairman.
Environment Overview and Scrutiny Committee approved this item on Thursday 5 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the minutes be approved as a correct record and signed by the Chairman.
CHESHIRE EAST COUNCIL Minutes of a meeting of the New Delivery Vehicles and Environment Overview and Scrutiny Committee held on Thursday, 8th January, 2015 at Committee Suite 1,2 & 3, Westfields, Middlewich Road, Sandbach CW11 1HZ
PRESENT
Councillor W Livesley (Chairman) Councillor K Edwards (Vice-Chairman)
Councillors G Barton, H Davenport, R Fletcher, M Hardy, A Martin and B Murphy
C Allman – Programme Manager I Bunn – Principal Building Control and Planning Systems Manager L Butcher – Executive Director of Strategic Commissioning A Dunstone – Contract and QA Manager R Kemp – Commissioning Manager – Waste and Environment D Laycock – Project Manager
39 APOLOGIES FOR ABSENCE
There were no apologies for absence
40 DECLARATIONS OF INTEREST
There were no declarations of interest.
41 WHIPPING DECLARATIONS
There were no whipping declarations.
42 PUBLIC SPEAKING
There were no members of the public present wishing to speak
43 MINUTES OF THE MEETING HELD ON 4 DECEMBER 2014
Consideration was given to the minutes of the last meeting.
RESOLVED
That the minutes be approved as a correct record and signed by the Chairman. 44 DEVELOPING THE ENVIRONMENTAL SERVICES HUB
Consideration was given to a presentation on developing the Environmental Services hub. The presentation outlined:
• The approach • Key principals • The need for change • Key work streams • Proposed services to be delivered • Progress to date • Benefits for Environmental Services • Benefits from partnering with Bentley • Key issues
It was intended for the hub to be based in Middlewich, land had been purchased, however planning permission was still required. The site provided excellent links to the rest of Cheshire East, the hub would be a waste transfer site and the headquarters for ANSA.
It importance of working closely with Bentley was noted as the migration was two phased, the timeframe was ambitious and planning permission had still to be sought by both Bentley and the Council.
The authority was committed to providing one Environmental Services Hub for the Borough as it was not practicable to provide two for a borough the size of Cheshire East, Members requested to receive evidence to prove that one hub would be cost effective.
With regard to the lessons learnt, it was agreed that there needed to be full communication with Members and the public. It was noted that an engagement strategy was currently being developed.
RESOLVED
That Members receive a cost/benefit analysis of providing one hub for the whole of the Cheshire East.
45 PLANNING SUPPORT COMPANY
Further to the meeting held on 4 December 2014, the Committee received additional information on the Building Control and Planning Support high level process.
Councillor M Hardy had met with finance officers to discuss the evidence relating to mitigating loss and a cumulative surplus of £90K over 5 years. He felt that the financial need to form a company was proven and the suggested profit over 5 years was conservative, however the management fee should be reviewed annually. Members agreed that the support services costs appeared to be high, however noted, savings would be made through the transition period and that to compete with the private sector the company would need to be commercial.
Members agreed that the constitution needed to be revised to allow the Council to be more agile.
RESOLVED
1. That the update be received 2. That the final proposals be supported to the Committee prior to Cabinet.
46 ASSESSMENT OF WASTE COLLECTION COMPLIANCE WITH NEW LEGISLATION (TEEP)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the Last MeetingMinutes | 36 KB | DownloadRead as text |
Follow Environment Overview and Scrutiny Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2016 | Minutes of Previous meetingRESOLVED That the minutes of the meeting held on 28 January 2016 be approved as a correct record and signed by the Ch... | Approved | Open |
| 24 Mar 2016 | Flood Risk ManagementRESOLVED (a) That the presentation be received; (b) That the Chairman be requested to write to the Highways and Infra... | Decided | Open |
| 24 Mar 2016 | Parks StrategyRESOLVED – That the draft parks strategy be noted. | Noted | Open |
| 24 Mar 2016 | Forward PlanRESOLVED That the forward plan be received | Decided | Open |
| 24 Mar 2016 | Work ProgrammeRESOLVED – That items relating to TSSL and Bus Service Routes be considered at the informal meeting to be held on 23 ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.