CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cheshire East Council
Shared Services Joint Committee, Monday 16 April 2018 at 12.00pm

Finance & HR System Replacement Programme

Noted Committee 1 paper

Shared Services Joint Committee noted this item on Monday 16 April 2018. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

That the Committee 1 note the status of the programme, as detailed in section 5 of the report, including the conditional signoff of the “build complete” milestone and the approach to resolving outstanding issues and releasing the remainder of the milestone payment; 2 endorse and agree that the Council and Agilisys teams (the Programme) formally review the Project Plan together, as detailed in section 9 of the report, which highlights an emerging and indicative two month extension to the programme, to access and replan activity, risks, deliverables and benefits of the programme, reporting back to the Committee on the proposals in May 2018; 3 note the broad range of business engagement activities which have been undertaken since the last update to the Committee, as described in section of the report, and the outcome of the first of a series of “change readiness assessments”; 4 note and endorse the benefit realisation processes, described in section of the report, which is underway to assess and confirm the business savings which were set out in the July 2017 Cabinet reports; 5 note the key elements of the training strategy, set out in section 8 of the report, which has been developed jointly in support of the programme; 6 note the financial pressures on the programme, as noted in section 10 of the report, and endorse the proposal to bring a full update to the next meeting of the Committee; and 7 note the positive feedback arising from the Internal Audit report following completion of the design phase of this ... view the full minutes text for item 34.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Shared Services Joint Committee

CHESHIRE EAST COUNCIL CHESHIRE WEST & CHESTER COUNCIL SHARED SERVICES JOINT COMMITTEE

Date of Meeting: 16 April 2018

Report of: Dominic Oakeshott, Best4Business Programme Director, Cheshire Shared Services

Subject/Title: Finance & HR System Replacement (“Best4Business”) Programme

1.0Report Summary

1.1The purpose of this report is to update Members on the progress being made in implementing a replacement HR and Finance system for the Councils and their partners.

2.0Decisions Requested

Members are asked to:

 Note that status of the programme as detailed in section 5, including the conditional signoff of the “build complete” milestone and the approach to resolving outstanding issues and releasing the remainder of the milestone payment;  Endorse and agree that the Council and Agilisys teams (the Programme) formally review the Project Plan together, as detailed in section 9 which highlights an emerging and indicative two month extension to the programme, to assess and replan activity, risks, deliverables and benefits of the programme, reporting back to this committee on the proposals in May 2018;  Note the broad range of business engagement activities which have been undertaken since the last update to the Committee as described in section 6, and the outcome of the first of a series of “change readiness assessments”;  Note and endorse the benefit realisation processes described in section 7 which is underway to assess and confirm the business savings which were set out in the July 2017 Cabinet reports;  Note the key elements of the training strategy set out in section 8 which has been developed jointly in support of the programme;  Note the financial pressures on the programme as noted in section 10 and endorse the proposal to bring a full update to the next meeting of this Committee; and  Note the positive feedback arising from the Internal Audit report following completion of the design phase of this programme, as set out in section 11. 3.0 Reasons for Recommendations

3.1To enable Members to review and comment on progress made in implementing the future Finance and HR systems and processes for the Councils and their partners.

4.0Report Background

4.1At the May 2016 meeting of this Committee, Members approved a programme of work to procure a new system or solution to replace the existing Finance and HR system. Both Councils’ Cabinet meetings approved a recommendation in July 2017 to award a contract to Agilisys for the implementation of the Unit 4 Business World system. This report provides an update to the Committee regarding progress toward completion of this activity.

5.0Programme status

5.1The majority of system build activity by Agilisys is now complete. The Programme Board signed off the major programme milestone, “build complete”, on 29th March. This was three weeks later than the planned signoff date of 7th March, which reflected the significant pressures and challenges being experienced and managed by the programme team as part of the build phase of the programme. The delayed signoff was provided on a conditional basis, recognising that certain core processes were not yet in a position to be demonstrated to the Councils to confirm that our requirements had been fully met, as set out in the agreed solution design. A proportion of the value of the build complete milestone has been retained, and will be paid to Agilisys upon demonstration of these outstanding elements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Finance & HR System Replacement ProgrammeMinutes 155 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Finance & HR System Replacement ProgrammeThis decision
  2. Finance & HR System Replacement ProgrammeNoted

More from Cheshire East Shared Services Joint Committee

All decisions
MeetingDecisionOutcome
27 Jun 2025 Appointment of ChairThat Councillor Jill Rhodes be appointed as chair for the 2025/26 municipal year. Decided Open
27 Jun 2025 Appointment of Vice ChairThat Councillor Carol Gahan be appointed as vice-chair for the 2025/26 municipal year. Decided Open
27 Jun 2025 Minutes of Previous MeetingThat the minutes of the meeting held on 25 April 2025 be approved as a correct record. Approved Open
27 Jun 2025 Shared Services Business Plans 2024-25 - End of Year ReportThat the Joint Committee note the Shared Services performance for 2024/25. Noted Open
27 Jun 2025 The Future Model for ICT: Programme Gemini UpdateThat the Joint Committee notes the progress made and current status of the Phase 1 Gemini Programme and recommends to... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies