Strategic Planning Board, Wednesday 30 January 2019 at 10.30am

Crewe Station Hub Area Action Plan - Development Strategy

Noted Planning 3 papers

Strategic Planning Board noted this item on Wednesday 30 January 2019. Below is the council's own wording, with the papers it was decided on.

Item89

Resolved

RESOLVED 1.That the consultation responses set out at Appendix 1 and the draft Development Strategy Document at Appendix 2 be noted. 2.That the Housing, Planning and Regeneration Portfolio Holder be recommended to approve the Development Strategy attached at Appendix 2 for consultation and that any minor typographical amendments be delegated to officers to agree.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Strategic Planning Board

Cheshire East Local Plan

Crewe Station Hub Area Action Plan: Development Strategy February 2019 1 Introduction 2 2 Key Assumptions 8 3 Emerging Issues 11 4 Area Description 15 5 Vision 17 6 Plan Objectives 18 7 General Development Policies 21 8 Developing the Options 27 9 Boundary Options 33 10 Identifying Potential sub-areas 37 11 Seeking Your Feedback and Next Steps 42

Contents

CHESHIRE EAST LOCAL PLAN Crewe Station Hub Area Action Plan Issues Paper November 2018 1 1 Introduction 1.1 The arrival of HS2 to Crewe presents an unparalleled opportunity to realise Crewe’s full potential as a regional and national hub. The step-change in connectivity enabled by HS2 could bring transformational growth around a future Hub Station that can have significant economic and social benefits for the community of Crewe and beyond.

1.2HS2 phase 2A is set to open as far as Crewe by 2027, with phase 2B programmed for 2033. The Council continues to campaign for a fully enhanced HS2 Hub Station (enabling north and south connections) to be provided in the town, in order to maximise the opportunities for inter-regional connectivity, regeneration and economic growth. The arrival of HS2 to Crewe will require significant re-modelling of Crewe Station to create additional passenger capacity and facilities that in turn will create the need for complimentary and supporting development in the environs of the station.

1.3The connectivity opportunity at Crewe Rail Station exists regardless of the Council’s HS2 related growth ambitions and its desire to secure an enhanced HS2 hub station, however the levels of growth that can be achieved through significantly improved connectivity is potentially of a scale that is truly transformative for Crewe.

1.4The purpose of this document is therefore to explore initial ideas and options on what transformative change could mean for Crewe and to progress multiple work-streams already undertaken by Cheshire East Council, the Local Economic Partnership and the Constellation Partnership. The growth aspirations set out in the Crewe Masterplan of 2017 and the Constellation Partnerships HS2 Growth Strategy 2018 set an important context that this document, and form the basis of the ideas set out here.

1.5Based on both the feedback received in consultation and on an enhanced understanding of the evidence currently being prepared a series of key issues, the Council expects to further develop the ideas in this document. It is anticipated that by testing and evolving the Councils ideas against both public feedback and more detailed evidence will lead to a publication of a refined Crewe Hub Station Area Action Plan prior to submission.

Constellation Partnership HS2 Growth Strategy 2018 1.6 The Constellation Partnership (formerly known as the Northern Gateway Development Zone) consists of 7 major local authorities (including Cheshire East Council, and Cheshire West and Cheshire) and 2 Local Enterprise Partnerships.

1.7On the 1st November 2018, The Constellation Partnership released its HS2 Growth (1) Strategy which outlines the important case for investment in the region. The Strategy features key information around the economic potential of HS2 and the ongoing and evolving Growth Strategy work that will help enable at least 120,000 new jobs, and 100,000 new homes, with a £6 billion per year of GVA by 2040 across the Partnership region. The document also sets out that Crewe has potential to deliver in the region of 7,000 new homes Introduction

and 37,000 new jobs. This additional growth is dependent on the Partnership’s ambition to create 5-7 HS2 trains per hour each way from the Crewe Hub, and 2 HS2 trains per hour each way from Stoke-on-Trent and Stafford.

1 Constellation Partnership documents, available at: http://constellationpartnership.co.uk/

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CSHAAP Dev Strat Jan19Minutes 25 MB DownloadRead as text
PDF
CSHAAP ISSUES PAPER CONSULTATION RESPONSES: KEY POINTSMinutes 154 KB Withheld: personal details
PDF
Crewe Station Hub Area Action Plan: Development StrategyMinutes 107 KB Download

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Crewe Station Hub Area Action Plan - Development StrategyThis decision
  2. 23/4181N - LAND AT CEMETERY ROAD, WESTON, CREWE, CW2 5LQ: The use of land for the stationing of additional caravans for residential purposes, the erection of a second dayroom and formation of additional hardstandingApproved
  3. Levelling Up Fund Bids for Nantwich Road, Crewe StationNoted
  4. Crewe Hub Station UpdateNoted
  5. 18/6389C-Erection of a new foodstore (Use Class A1), access, substation and associated car parking and landscaping. Re-submission of application 18/3123N, Land South East of Crewe Road Roundabout, University Way, Crewe for Mr George Brown, Aldi Stores LimitedApproved
  6. 09/3251N-Demolition of Existing Garage and Petrol Station and Erection of 11no Dwellings, Grenson Motor Co Ltd, Middlewich Road, Minshull Vernon, Crewe, Cheshire for Mr J Middleton, Grenson Motor Co LtdApproved

More from Cheshire East Strategic Planning Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 22 July 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Sep 2026 25/1573/FUL - Full planning application for a residential development including associated access, infrastructure and landscaping. Land off Cumber Lane, WilmslowThat application 25/1573/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 3-year ti... Approved Open
16 Sep 2026 25/2071/FUL - Full planning application for a residential development and the provision of associated access and infrastructure works including roads, drainage infrastructure, car parking, public open space and landscaping. Land at Dean Row Road, WilmslowThat application 25/2071/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 2-year ti... Approved Open
16 Sep 2026 National Scheme of DelegationThat the Strategic Planning Board Noted the changes introduced by the for Planning Functions that will be implemented... Noted Open
22 Jul 2026 Minutes of the Previous MeetingThat the minutes of the meetings held on 27 May 2026 and 9 June 2026 be approved as correct records. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies