Resolved
That the Joint Committee 1 note the findings, recommendations, and next steps for Phase 2: Transitional Services 2 note the findings, recommendations, and next steps for Phase 3: six smaller shared services.
Shared Services Joint Committee noted this item on Friday 21 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Joint Committee 1 note the findings, recommendations, and next steps for Phase 2: Transitional Services 2 note the findings, recommendations, and next steps for Phase 3: six smaller shared services.
2.1It is recommended that Members:
i) Note the findings, recommendations, and next steps for Phase 2: Transactional Services ii) Note the findings, recommendations, and next steps for Phase 3: six smaller shared Services
3.1The Shared Service Joint Committee terms of reference sets out that Joint Committee is responsible for overseeing changes related to the shared services.
3.2A Review of the arrangements between the two councils is being undertaken. This report brings members of the committee up to date on developments.
4.1Cheshire East Council and Cheshire West and Chester Councils agreed to commission a strategic review of all the existing eight formal shared services. It was agreed that an external perspective and expertise would be valuable, and a specification was drawn up, a procurement exercise undertaken, and C.Co, the consultancy arm of CIPFA, were appointed to conduct the reviews. This work has largely been completed and is in the process of being reviewed.
OFFICIAL-SENSITIVE OFFICIAL 5. Approach to the Shared Services Review
5.1The purpose of the review exercise is to:
- provide assurance on the operation of the shared service in terms of both meeting the objectives of each council and delivering value for money. - to identify opportunities for efficiencies and financial savings; and, - to identify how could the services work better and/or what will make them work better?
5.2The review of all the shared services has been undertaken in three phases, this report provides a summary:
Phase 1: ICT Shared Services – in depth review Phase 2: Transactional Services – in depth review Phase 3: Wider Shared Services (remaining six shared services) – light touch review
6. Summary Progress of Phase 1: ICT Shared Services (in depth review)
6.1The key findings of this review were reported to this committee on 24 September 2021. Further work on technical and financial assurance and due diligence was agreed. The more detailed exercise is required to fully understand the impacts, the delivery plan, the costs, and the benefits of moving to the recommended ICT model before a decision is taken.
6.2The resource impact across ICT services as a whole is regularly monitored through project governance to ensure this is manageable and to reduce any additional costs or impacts.
6.3This activity is underway and is anticipated to complete by April 2022.
7. Summary Progress of Phase 2: Transactional Services (in depth review)
7.1The review of Transactional Shared Service has considered the strategic alignment between the Councils, efficiency and effectiveness of the service, through baselining costs, benchmarking against other councils and gaining a deeper understanding of performance from a customer perspective. It has then considered the best delivery model for the future and has recommended opportunities for further improvement.
7.2Transactional Services is hosted by Cheshire West and Chester Council and operates as a shared service model with a 50:50 split of all costs and potential liabilities such as underspends and overspends. The review identified that overall, this funding equates to a broad 50:50 split of all costs associated.
7.3The review has acknowledged the significant challenges that Transactional Services have faced over the last few years, particularly in relation to the implementation of UNIT 4 ERP and COVID response.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Shared Service Review Update ReportMinutes | 104 KB | DownloadRead as text |
Follow Shared Services Joint Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jun 2025 | Appointment of ChairThat Councillor Jill Rhodes be appointed as chair for the 2025/26 municipal year. | Decided | Open |
| 27 Jun 2025 | Appointment of Vice ChairThat Councillor Carol Gahan be appointed as vice-chair for the 2025/26 municipal year. | Decided | Open |
| 27 Jun 2025 | Minutes of Previous MeetingThat the minutes of the meeting held on 25 April 2025 be approved as a correct record. | Approved | Open |
| 27 Jun 2025 | Shared Services Business Plans 2024-25 - End of Year ReportThat the Joint Committee note the Shared Services performance for 2024/25. | Noted | Open |
| 27 Jun 2025 | The Future Model for ICT: Programme Gemini UpdateThat the Joint Committee notes the progress made and current status of the Phase 1 Gemini Programme and recommends to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.