Resolved
That the Internal Audit Update Report be received and noted.
Audit and Governance Committee noted this item on Thursday 26 May 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Internal Audit Update Report be received and noted.
Internal Audit Update Report April 2021– February 2022 (2021/2022 Internal Audit Plan)
OFFICIAL 1. Introduction
1.1In accordance with the Public Sector Internal Audit Standards, the Internal Audit Update Report April 2021- February 2022 contains “emerging issues in respect of the whole range of areas to be covered in the annual report.”
1.2Internal Audit is required to form an annual opinion on the overall adequacy and effectiveness of the organisation’s control environment, which includes consideration of any significant risk or governance issues, and control failures which have been identified.
2. Summary of Audit Work to Date
2.1During this period, audit work was undertaken on the whole of the control environment comprising risk management, key control and governance processes. This work comprised a mix of risk based auditing, regularity, investigations and the provision of advice to officers. Annex 1 explains the variety of audit work undertaken to support the annual audit opinion.
Assurance Work
2.2A summary of the final reports issued to the end of February 2022, by the audit assurance opinion given is included in Table 1. Reports issued to this point are in line with expectations and approaching pre-covid levels of output.
2.3Details of work in progress, covering draft reports issued for agreement with managers, fieldwork in progress and terms of reference stages, is covered in Table 5. It is anticipated that sufficient work in terms of quantity and coverage will be undertaken to deliver the annual opinion for 2021/22, with the number of final reports issued expected to be approaching the total number issued in 2019/20.
2.4Figures relating to 2019/20 have been included in the table below to assist with comparison; no assurance work had been completed in the first half of 2020/21 as a result of the Covid-19 response.
Table 1: Reports to date by assurance level
Assurance Level 2021/22 (to 2020/21 Full Year 2019/20 28/02/2022) Full Year Good 2 6 6 Satisfactory 3 4 4 Limited 4 3 11 No Assurance 0 0 2 Total 9 13 23
OFFICIAL Page 2 of 14 Table 2: Summary of Final Assurance Reports 2021/22 to 28 February 2022
Audit Report Reason Audit Management Summary of Findings for Assurance Response – (Limited /No Review Opinion Assurance Reports Only)
Council Tax Identified Good No actions raised Billing via Reconciliation Planning 2022/23 Process NDR Billing Identified Good No actions raised Reconciliation via 2022/23 Planning Process Deprivation of Identified Satisfactory All actions Liberty via Audit agreed Safeguards Plan B4B Go Live 2 Identified Reasonable* The audit report Sign Off via Audit (CWaC IA provided (joint work with Plan opinion) assurance to CWAC and Programme issued using Board in relation their assurance to the Go Live levels) decision B4B Go Live 2 Identified No formal Issues raised in Progress against the Sign Off – via Audit assurance the audit report issues raised in this Cutover Plan opinion were included report were monitored decision provided within caveats to and reported upon in be attached to the Go Live report the decision to detailed above. enter cutover prior to the formal Go Live decision C&WLEP Local Identified Satisfactory Final Assurance to Director Assurance via of Finance & Customer Framework Planning Services (s151 Officer) (assurance to Process and C&WLEP s151 Officer) management that the framework and procedures are robust and in accordance with national guidance.
Schools Identified Limited All actions The report Consolidated via Audit agreed summarises common Report 2020/21 Plan issues arising from our school audit programme. Areas
OFFICIAL Page 3 of 14 Audit Report Reason Audit Management Summary of Findings for Assurance Response – (Limited /No Review Opinion Assurance Reports Only)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
IA Update Report April 21: February 22- Appendix A FINALMinutes | 14 pages | DownloadRead as text |
PDF |
Internal Audit Plan 2021/22: Progress ReportMinutes | 414 KB | Download |
Follow Audit and Governance Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Minutes of Previous MeetingThat the minutes of the previous meeting be approved as a correct record . | Approved | Open |
| 27 Jul 2026 | Audit and Governance Committee Action LogThat the action log and updates received be noted. | Noted | Open |
| 27 Jul 2026 | Draft Annual Governance Statement 2025-26That the Audit and Governance Committee received and reviewed the draft AGS 2025/26, noting that the final proposed A... | Approved | Open |
| 27 Jul 2026 | Internal Audit Opinion 2025-26RESOLVED That the Audit and Governance Committee 1. Noted and considered the contents of the Internal Audit Annual Op... | Noted | Open |
| 27 Jul 2026 | Final Outturn and Draft Statement of Accounts 2025/26That the Audit and Governance Committee 1. Noted the summarised position of the accounts for year ended 31st March 20... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.