RESOLVED (unanimously): That the Committee 1 notes the conclusion of technical feasibility assessments related to the Earle Street Link (feasibility) project and that it does not proceed in acquiring land for the purposes of future delivery of an Earle Street Link; and 2 approves the submission of a Project Adjustment Request to the Department of Levelling Up, Housing & Communities seeking approval to reallocate approximately £1m funding within the approved Future High Street Fund programme for Crewe, from the Earle Street Link (feasibility) project to the Southern Gateway project.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
2.1In December 2020, the Government allocated £14.1m to support a programme of ten town centre regeneration projects in Crewe. This report relates to two of those projects:
2.2Earle Street Link (feasibility): Over the past two years, the Council has been engaged with Network Rail to consider the technical constraints of enhancing pedestrian/cycle connectivity across the West Coast Mainline. Having considered these options in detail, it is concluded that there is no scope to
OFFICIAL deliver effective enhanced pedestrian/cycle connectivity across the West Coast Mainline at Earle Street, and the balance of the budget is not required.
2.3Southern Gateway: Positive progress has been made with third party property interests in acquiring the land necessary to create this new pedestrian and cycle link. However, significant construction cost inflation has been experienced and additional funding is required to deliver the scheme as planned.
2.4It is proposed that a Project Adjustment Request is submitted to DLUHC seeking approval to reallocate the balance of approximately £1m grant funding from the Earle Street Link (feasibility) project to the Southern Gateway project.
3. Recommendations That the Committee:
3.1Notes the conclusion of technical feasibility assessments related to the Earle Street Link (feasibility) project and that it does not proceed in acquiring land for the purposes of future delivery of an Earle Street Link; and
3.2Approves the submission of a Project Adjustment Request to the Department of Levelling Up, Housing & Communities seeking approval to reallocate approximately £1m funding within the approved Future High Streets Fund programme for Crewe, from the Earle Street Link (feasibility) project to the Southern Gateway project.
4. Reasons for Recommendations 4.1. In relation to the two projects identified: Earle Street Link (feasibility) 4.2. Over the past two years, the Council has been engaged with Network Rail to consider the technical constraints of enhancing pedestrian/cycle connectivity across the West Coast Mainline. These have considered both a new structure and an adaptation to the existing structure. 4.3. A new structure would need to adhere to clearance heights by Network Rail. Whilst technically feasible, its height would require: a) steps on both sides that would be less attractive to pedestrians that the current provision; b) a ramp on both sides that would be less attractive to those with mobility/access issues than the current provision; and c) third party property that would be expected to involve a protracted acquisition process
4.4Adaptation to the existing Earle Street bridge structure would require the Council to take on full responsibility for its future maintenance costs and, given
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Third Financial Review of 2025/26RESOLVED (Unanimously): That the Committee 1 note the overall Council’s Financial position as described within the Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.