That the Audit and Governance Committee (1) Approve the ; (2) Noted that the plan details priority work during quarters 1 and 2 along with additional areas for consideration during quarters 3 and 4. Progress against the plan, and the priorities for the last 6 months will be reported back as part of the regular updates to the committee.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
1.1The purpose of this report is for the Committee to receive and approve the Summary Internal Audit Plan for 2023/24 (Appendix A).
Executive summary
2.1The preparation and delivery of the annual Internal Audit Plan, the annual opinion on the organisation’s arrangements for governance, risk and internal control, and the assurances these provide to the Annual Governance Statement (AGS) are key indicators and contributors for the Council’s corporate objectives as an open and enabling organisation.
2.2The Council’s Internal Audit Charter, which has been developed to ensure compliance with the Public Sector Internal Audit Standards (PSIAS), requires the preparation of a risk based internal audit plan which takes into account the need to produce an annual internal audit opinion. The opinion is a key source of assurance for the AGS which is approved by the Audit and Governance Committee and signed by the Council’s Chief Executive and Leader.
OFFICIAL 3. Recommendations 3.1. That the Committee: 3.1.1. Approve the Internal Audit Plan 2023/24.
3.1.2. Note that the plan details priority work during quarters 1 and 2 along with additional areas for consideration during quarters 3 and 4. Progress against the plan, and the priorities for the last 6 months will be reported back as part of the regular updates to the Committee. 4. Reasons for Recommendations
4.1The Council’s Internal Audit Charter, developed in accordance with the PSIAS requires the production of an annual internal audit plan. This plan sets out the anticipated range and volume of work which is required to deliver the annual internal audit opinion on the organisation’s arrangements for governance, risk and internal control.
4.2The authority to approve the annual internal audit plan is within the Audit and Governance Committee’s Terms of Reference. 5. Other Options Considered
5.1There is no “do nothing” option. Failure to approve an internal audit plan would mean significant non-compliance with the PSIAS. Approval of the proposed audit plan ensures that the work of Internal Audit during 2023/24 is focused upon and contributes to the annual opinion. 6. Background
6.1All principal local authorities subject to the Accounts and Audit Regulations 2015 must make provision for internal audit in accordance with the Public Sector Internal Audit Standards. The Standards state that the provision of assurance services is the primary role for internal audit in the UK public sector. This role requires the Head of Audit and Risk (as “Chief Audit Executive”) to provide an annual internal audit opinion based on an objective assessment of the framework of governance, risk management and control.
6.2The planning process and risk assessment is detailed in Appendix A. Through this additional and thorough consultation we look to ensure that internal audit resources continue to focus on areas where assurance provides the most value, particularly during periods of change.
6.3For planning purposes, the 2023/24 plan will be based on the current team structure with adjustments made where necessary to reflect any changes in resource during the year.
6.4Proposed audit activities identified through the development and consultation process are matched against the internal audit resources available and
OFFICIAL prioritised accordingly; the proposed risk-based summary internal audit plan for 2023/24 is included in Appendix A.
6.5In accordance with PSIAS, the plan is fixed for a period of no longer than one year. It details the assignments to be carried out, their respective priorities, (by differentiating between core assurance work and other work), and the estimated resources required. The Corporate Leadership Team has been consulted on the plan prior to presentation to the Audit and Governance Committee.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.