RESOLVED (unanimously) : That the Committee 1 delegate to the Executive Director Place to take all necessary actions to enable the delivery stage of the ‘Cheshire Archives – A Story Shared’ project. 2 delegate authority to the Executive Director Place, in consultation with the Director of Governance and Compliance, to enter into or approve any contracts or agreements (including professional consultants and building contracts etc.) required for the delivery phase. 3 approve the entering into a Memorandum of Understanding (MOU) to address all relevant terms for collaborative delivery of the project with CWAC. 4 approve the participation as required in the acceptance of the offer of grant aid from the Heritage Fund by CWAC by the exercise of the delegated authority to proceed with this project. 5 consideration be given to naming the History Centre in honour of the late Councillor Dorothy Flude, subject to public consultation. The meeting adjourned for a short break during which Councillor Kolker returned to the meeting.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
1.1This report provides an update to the ‘Cheshire’s Archives – A Story Shared’ project and provides the context for the delivery phase of the project, which includes the building of a new History Centre in Crewe. The report sets out the governance and decision processes which are required in order to deliver the build phase of the project in a timely manner to prevent delays to the project timetable.
1.2The service identifies, collects, and cares for archives that are the evidence of Cheshire’s communities, delivering access to our shared collections. The project will develop the service and the necessary replacements for the current building. This will deliver two new buildings (History centres) in Chester and Crewe, which will be fit for purpose, accessible to visitors, provide storage and access to collections and using technology to bring the collections closer to people across both Cheshire West and Cheshire East.
Executive summary
2.1The report sets out the current status of the ‘Cheshire’s Archives – A Story Shared’ project, explaining that the project is now moving into the delivery phase, having been successful in a bid to the National Lottery Heritage Fund. The report further sets out the arrangements in place for Governance of the delivery phase and the necessary delegations and permissions.
OFFICIAL 3. Recommendations
3.1Delegate authority to the Executive Director Place to take all necessary actions to enable the delivery stage of the ‘Cheshire Archives – A Story Shared’ project.
3.2Delegate authority to the Executive Director Place in consultation with the Director of Governance and Compliance to enter into or approve any contracts or agreements (including professional consultants and building contracts etc) required for the delivery phase.
3.3To enter into a Memorandum of Understanding (MOU) to address all relevant terms for collaborative delivery of the project with CWAC.
3.4To participate as required in the acceptance of the offer of grant aid from the Heritage Fund by CWAC by the exercise of the delegated authority to proceed with this project
Reasons for recommendations
4.1In April 2021 Members provided all necessary approvals and delegations required to ensure delivery of the project development phase up to and including the submission of grant applications and endorsement of the approach to project delivery. As the project has been successful in its grant application to National Lottery Heritage Fund (NLHF) and will be entering its delivery phase, further delegations will now be required to enable delivery of the project for which Cheshire West and Chester is the accountable body.
4.2A Memorandum of Understanding (MoU) will outline the joint approach across the two authorities to delivering the project and will build on the existing project Terms of Reference. Its main focus is the approach to procurement and contracting in line with the project’s procurement strategy.
4.3This strategy states that Cheshire West and Chester, as the host authority of the shared service, will lead the procurement process and act as the accountable body for the project with the National Lottery Heritage Fund (NLHF), although as this is a joint project, both authorities will be required by NLHF to sign the grant terms and conditions. This remains in line with the April 2021 Cabinet endorsement of the approach to project delivery and the delegated powers sought in this report to enable the project to proceed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Third Financial Review of 2025/26RESOLVED (Unanimously): That the Committee 1 note the overall Council’s Financial position as described within the Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.