RESOLVED (by majority): That the Highways and Transport Committee 1. Note the progress made on the operation of the Ward Member Budget Scheme during its first year of operation during 2023-24 and the ongoing work being undertaken with local ward members to identify works and deliver on these across the network. 2. Note the proposed steps being taken as set out within the report to improve the overall scheme delivery. 3. Approve, for the 2024-25 financial year, the annual allocation per elected member of £4,512. 4. Agree that all Members are provided with a quarterly electronic update on the scheme by the Highways service. The meeting adjourned for a short break at 11.46 and reconvened at 11.55am. Councillor P Coan left the meeting and did not return.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
The Highways and Transport Committee is recommended to:
1. Note the progress made on the operation of the Ward Member Budget Scheme during its first year of operation during 2023-24 and the ongoing work being undertaken with local ward members to identify works and deliver on these across the network.
2. Note the proposed steps being taken as set out within the report to improve the overall scheme delivery.
3. Approve, for the 2024-25 financial year, the annual allocation per elected member of £4,512*. 4. Agree that all Members are provided with a quarterly electronic update on the scheme by the Highways service.
*Noting the decision of Council on 27 February 2024 to reduce Council investment within the capital programme, as set out in paragraph 29 of this report.
Background
4. The Ward Member Budget scheme was introduced on a trial basis in April 2021 to replace the old Area Highway Groups. The trial ran for two years (2021-2 and 2022-3), with each member allocated a capital budget of £4,200 per annum to use on a specified list of highway activities provided by the Service.
5. The Highways and Transport Committee received an update on the ward budget scheme at its meeting in January 2022, followed by a final report in September 2022 with recommendations on how to deliver and manage the scheme in future years.
6. The Committee approved:
A capital budget of £6,500 per Member, per annum (55% increase);
The scheme to operate over a four-year period from April 2023 to March 2028 - a total of £26k to each Member plus £20k per annum of administrative costs (£553k per annum and £2.212m over the four years);
The previous application process to no longer be used;
Individual ward work programmes to be developed based on local intelligence gathered, and engagement with Members; and
The proposed new approach will enable much greater interaction between Highways Officers and Members, supporting a key theme coming out of the Member Satisfaction Survey at the time.
7. The revised approach aimed to achieve a number of benefits:
To continue to provide a locally determined element within Highways capital works, that contributes to achieving the council’s asset management objectives. Members would retain the flexibility to prioritise work at the start of each financial year and whether to spend their allocation equally over the four years, combine multiple years or join with fellow Member ward budgets to deliver larger value works.
Seeking to avoid applications being voided on the basis that they are either not compliant with policy or are already being delivered within the committed Highways work programme. Existing data within systems like Fix My Street would be used to inform work programmes.
The process would allow a known quantum of work to be programmed from the start of each year, rather than trying to fit in ad-hoc as and when Member applications are received and validated. This would make delivery of the Member budgets more cost-efficient and generate increased value for money.
Provide greater certainty around budget spend each year. The move to a request-based process aimed to remove reliance on receiving valid Member applications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Third Financial Review of 2025/26(By Majority) That the Highways and Transport Committee 1. Note the overall Council’s Financial position as described...
Ward Member Budget Scheme UpdateRESOLVED (By Majority) That the Highways and Transport committee Note the progress made to date on the operation of t...
Local Transport Plan - Approval(By Majority) That the Highways and Transport committee 1. Approve the Local Transport Plan (LTP) strategy (Appendix ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies