(Unanimously) That the Highways and Transport Committee 1. Note the progress made with the implementation of the Improvement Action Plan to date. 2. Approve that the Director of Transport and Infrastructure continues to progress implementation of the Improvement Action Plan in Appendix 1. 3. Notes that progress with the plan will be monitored and managed through: a. the Place Directorate Management Team; and b. in conjunction with Cheshire East Highways through the Transportation and Infrastructure Partnership Board, with any significant issues reported to the committee. 4. Approve that the Director of Transport and Infrastructure commissions a further peer review before April 2028 to assess progress.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
The Highways and Transport Committee is recommended to:
1. Note the progress made with the implementation of the Improvement Action Plan to date. 2. Approve that the Director of Transport and Infrastructure continues to progress implementation of the Improvement Action Plan in Appendix 1. 3. Notes that progress with the plan will be monitored and managed through: a. the Place Directorate Management Team; and b. in conjunction with Cheshire East Highways through the Transportation and Infrastructure Partnership Board, with any significant issues reported to the committee. 4. Approve that the Director of Transport and Infrastructure commissions a further peer review before April 2028 to assess progress.
Background 6 The report from FHRG is shown in Appendix 1 to the report to the Highways and Transport Committee on 19 July 2024, listed as a background paper.
7 FHRG’s report identified eight priority recommendations and 13 other recommendations. The recommendations are listed in the Appendix to the Improvement Action Plan. The Appendix also identifies how the Council plans to respond to each of the recommendations.
8 The priority recommendations were regarding:
(a) Increasing the skills and capacity of the Council’s Highways client team;
(b) Reviewing the governance and management of the contract;
(c) Refreshing the contract performance framework;
(d) Refreshing the Council’s asset management policy and strategy;
(e) Considering the future contract model and scope of services; (f) Developing more rigorous and open benchmarking within the contract;
(g) Undertaking earlier budget setting; and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Third Financial Review of 2025/26(By Majority) That the Highways and Transport Committee 1. Note the overall Council’s Financial position as described...
Ward Member Budget Scheme UpdateRESOLVED (By Majority) That the Highways and Transport committee Note the progress made to date on the operation of t...
Local Transport Plan - Approval(By Majority) That the Highways and Transport committee 1. Approve the Local Transport Plan (LTP) strategy (Appendix ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.