Highways and Transport Committee, Thursday 22 January 2026 at 10.30am

Decision to Let a Construction Contract for the Middlewich Eastern Bypass

Noted Committee 4 papers

AI summaryCheshire East's Highways and Transport Committee unanimously approved entering Stage 2 of the Middlewich Eastern Bypass construction contract at a £53.8M target cost, within a £107.6M revised budget. The road is expected to open in Spring 2028.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedEntering Stage 2 of construction contract
Money£53.8M target costWithin £107.6M revised MTFS budget
What happens nextAdvance works from 9 February 2026Construction contract starts 17 April 2026
Who it affectsMiddlewich, road users, Mid CheshireEnables Strategic Location LPS 44 development

What was decided

The committee approved entering Stage 2 of the construction contract under the SCAPE framework, delegating authority to the Executive Director of Place in consultation with the Chair and Vice Chair. Report P8

The Head of Infrastructure was appointed as Project Manager, and authorised to instruct the contractor to bring forward works in Appendix A into Stage 1 before formal award. Report P8

The initial Cledford Lane value engineering design was authorised for inclusion in the project programme, with further Cledford Lane elements delegated to the Executive Director of Place. Report P8

Why

The target cost of £53.8M is within the revised MTFS budget of £107.6M approved by full Council in December 2025, and value engineering keeps the scheme within the budget envelope. Report P3, P9, P26

Not proceeding would expose the council to significant financial risk due to high levels of sunk costs already incurred in design, development and land purchase. Report P27

The scheme will relieve congestion in Middlewich town centre, improve journey times in mid Cheshire, and enable the full development of Strategic Location LPS 44 (Midpoint 18). Report P1, P2

What happens next

Land agreements to be triggered by 20 February 2026, with advance works under Stage 1 running from 9 February to 31 March 2026. Report P16, P18

Land agreements to complete by 23 March 2026, with the Stage 2 construction contract commencing on 17 April 2026 and the scheme opening to traffic in Spring 2028. Report P17, P19, P21

The Executive Director of Place will explore additional funding options through the Combined Authority to strengthen the scheme contingency budget. Report P8, P43

The money

  • £53.8M Target cost for construction phase of the scheme Report P3, P10
  • £107.6M Revised MTFS budget for the scheme confirmed by full Council in December 2025 Report P9
  • £107.67m Capital Programme budget (CAP-00375) endorsed by full Council Report P39
  • £3M Additional funding proposed to be ringfenced in a centrally held Capital Reserve as part of 2026/27 MTFS Report P44

Options considered

  • Rejected: Do nothing or do not move to Stage 2. CPOs would expire, sunk costs would be incurred, and there would be further financial consequences Report P30
  • Rejected: Do not appoint Head of Infrastructure as Project Manager. A nominated experienced individual is a contractual requirement of the NEC contract Report P30
  • Rejected: Do not bring forward advance works into Stage 1. Target cost assumes early works; without them there would be major delay and increased total costs Report P30
  • Rejected: Do not phase delivery of Cledford Lane improvements. Legal advice recommended phasing; further risk allowance needed before risk trend is understood Report P30
  • Rejected: Do not explore further funding options. Officer advice is that additional contingency is prudent; Combined Authority will distribute new funding Report P30

Implications

  • Financial: Target cost of £53.8M is within the £107.6M revised budget, but the target cost is higher than envisaged when the budget was set, leaving limited contingency. Report P40
  • Financial: The Scape Contract inflation clause X1 means inflation during construction is a client cost; an allowance is included in the estimate. Report P38
  • Legal: A Compulsory Purchase Order must be implemented, including for full Cledford Lane delivery and linked land property agreements, before the formal Stage 2 contract. Report P8, P33
  • Risk: The risk allowance, including value engineering opportunities, is at the lower end of acceptable; further external funding is recommended to strengthen it. Report P48
  • Risk: Land must be drawn down before the Stage 2 contract is entered into to allow advance works in early February, with significant associated costs. Report P51
  • Legal: Minor scheme design changes, such as road width, will require regularisation via a minor amendment to the planning permission before implementation. Report P35
  • Equalities: Equality, Diversity and Inclusion implications are unchanged from those reported to Highways and Transport Committee on 21 September 2023. Report P57
  • Staffing: No direct human resources impacts; the scheme includes an allowance for future resource costs for managing it. Report P45

Who and where

  • Residents and road users in Middlewich and mid Cheshire Report P1
  • The developer of Strategic Location LPS 44 (Midpoint 18) Report P1
  • Network Rail, Canal and River Trust, Environment Agency, and other third parties Report P50
  • Cheshire West and Chester Council, as the scheme is partly within that area Report P2
  • Users of the Cledford Lane depot Report P12

Timeline

  • 20 February 2026: Trigger land agreements to allow early access and implement CPO powers Report P16
  • 9th Feb, 31st March: Advance Works under Stage 1 Contract Report P18
  • 23 March 2026: Completion date for land agreements Report P17
  • 17 April 26: Construction Contract (Stage 2) commences / unconditional Report P19
  • 24 May 2026: Access date to land required via CPO Report P20
  • Spring 2028: Scheme open to traffic Report P21

Plain English for the jargon

  • SCAPE framework: A procurement framework used for the construction contract; the project is delivered under an NEC Construction Contract in two stages.
  • Stage 1 / Stage 2: Stage 1 covers pre-construction activities; Stage 2 is the main construction phase.
  • CPO: Compulsory Purchase Order, used to acquire the land needed for the scheme.
  • MTFS: Medium Term Financial Strategy, the council's budget planning document.
  • Value engineering: Design or specification changes made to manage costs, such as reducing road width and phasing Cledford Lane delivery.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item38

Resolved

(Unanimously) That the Highways and Transport Committee 1. Delegate authority to the Executive Director of Place in consultation with the Chair and Vice Chair of the committee or appropriate Cabinet Member(s) to: (a) enter Stage 2 of the construction contract under the SCAPE framework (b) attend to any matters ancillary to entering Stage 2 as noted above (c) agree any variations to the Construction Contract in consultation with the Chair and Vice Chair of this committee or appropriate Cabinet Member(s) 2. Agree that the Head of Infrastructure to be appointed as the Project Manager under the Contract. 3. Authorise the Head of Infrastructure to instruct the Contractor to bring forward the works set out in Appendix A into Stage 1 of the Contract to allow delivery prior to a formal award of contract. 4. Authorise the initial Cledford Lane Value engineering design is incorporated into the project programme for initial delivery – as shown in Appendix B of the report. 5. Delegate to the Executive Director of Place in consultation, with the Chair and Vice Chair of the committee or appropriate Cabinet Member(s) the timing and contractual arrangements for the further Cledford Lane elements of ... view the full minutes text for item 38.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Highways and Transport Committee

Executive summary

7 The Middlewich Eastern Bypass scheme will improve the highway network in Middlewich by relieving congestion and road safety concerns in Middlewich town centre, improving journey times in mid Cheshire and enabling the full development of Strategic Location LPS 44 (Midpoint 18)

OFFICIAL in the adopted Local Plan Strategy. The Scheme, which is partly in Cheshire West and Chester, will support the economic growth of the Cheshire and Warrington sub-region.

8 A Target Cost for the construction phase of the scheme has been agreed with the Contractor at £53.8M. This includes the full scope of the Cledford Lane element and takes advantage of a shorter programme taking account of new information on ground conditions and starting as early in the Spring as possible.

9 The Target cost programme and cost assumes that certain time sensitive elements are undertaken in February and March in advance of the formal construction contract being entered into.

10 The updated total cost estimate, inclusive of risk, property and sunk costs is contained in restricted Appendix C. Whilst this remains within the MTFS budget envelope, to maximise the available risk allowance at the start of the project a decision to proceed with the full scope of the Cledford Lane element of the scheme will be deferred until later in the construction phase. The potential savings associated with this value engineering option is set out in restricted Appendix C.

11 Approval from this committee to authorise entering Stage 2 of the Construction Contract will require that the Council draw down the land for the scheme to the value shown in restricted Appendix C.

Recommendations

The Highways and Transport Committee is recommended to:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Works to bring forward into Stage 1 of the ContractAppendix A 70 KB Download
PDF
Cledford Lane Value Engineering OptionAppendix B 499 KB Download
PDF
Risk SummaryAppendix E 126 KB Download
PDF
Decision to Let a Construction Contract for the Middlewich Eastern BypassMinutes 135 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Decision to Let a Construction Contract for the Middlewich Eastern BypassThis decision
  2. Congleton transport Infrastructure - Selection of Preferred Transport Solution (Key Decision Ref CE 13/14-13)Noted
  3. Key Decision CE12/13-11 Congleton Transport Infrastructure - Assessment of a New Link RoadApproved
  4. Call In of Cabinet Decision - CE09/10-10 Car Parking Control and Charging in the area of the Former Borough of CongletonDecided

More from Cheshire East Highways and Transport Committee

All decisions
MeetingDecisionOutcome
2 Apr 2026 Minutes of Previous MeetingThat the minutes of the meeting held on 22 January 2026 be approved as a correct record. Approved Open
2 Apr 2026 Third Financial Review of 2025/26(By Majority) That the Highways and Transport Committee 1. Note the overall Council’s Financial position as described... Noted Open
2 Apr 2026 Ward Member Budget Scheme UpdateRESOLVED (By Majority) That the Highways and Transport committee Note the progress made to date on the operation of t... Agreed Open
2 Apr 2026 Local Transport Plan - Approval(By Majority) That the Highways and Transport committee 1. Approve the Local Transport Plan (LTP) strategy (Appendix ... Approved Open
2 Apr 2026 Local Transport Delivery Plan - Consolidated Funding(By Majority) That the Highways and Transport committee 1.Authorise the Executive Director of Resources and the Secti... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies