25/4821/FUL - ENVIRONMENTAL SERVICES HUB, CLEDFORD LANE, MIDDLEWICH: Additional car parking, relocated bin store and a new security lodge

Approved Planning 2 papers

AI summaryCheshire East Strategic Planning Board approves Environmental Services Hub expansion in Middlewich with extra parking, new bin store and security lodge, subject to 23 conditions and a £176,000 contribution towards the Middlewich Eastern Bypass.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPer officer recommendation, subject to financial contribution notification
Money£176,000Towards the Middlewich Eastern Bypass (internal transfer)
What happens next3 years to commence developmentThen implement conditions and management plans
Who it affectsNot stated

What was decided

Application 25/4821/FUL was approved in line with the officer's recommendation, with 23 conditions covering construction, operations, environment, ecology and drainage.

Approval is conditional on formal notification of an internal transfer of a £176,000 contribution towards the Middlewich Eastern Bypass.

Delegated authority was given to the Head of Planning, in consultation with the Strategic Planning Board Chair, to make minor wording changes before the decision is issued.

Why

The application was approved as per the officer's recommendation; the supporting papers are largely architectural plans and lighting calculations rather than narrative reasoning. Report P19, P89

What happens next

Development must begin within 3 years and the approved plans, travel plan, car park management strategy, noise management plan and ecological mitigation must be implemented.

The applicant must submit further documents before work starts, including an updated ground contamination model, a final construction environmental management plan, biodiversity net gain and landscape planting schemes, a nesting bird protection scheme, a detailed drainage strategy and a halite risk assessment.

The money

  • £176,000 Financial contribution towards the Middlewich Eastern Bypass, via formal notification of an internal transfer

Options considered

  • Chosen: Approve as per officer's recommendation with 23 conditions

Implications

  • Environment and climate: Conditions require implementation of the ecological assessment mitigation, a biodiversity net gain plan, biodiversity enhancement measures, a nesting bird protection scheme and a landscape planting scheme.
  • Environment and climate: Conditions address air quality mitigation, noise management, soil testing, contamination remediation and a halite risk assessment, plus a detailed drainage strategy with a maximum discharge rate.
  • Other: Conditions tie this permission to the storage height, hours, travel plan, noise levels and noise management plan previously imposed on permission 15/2355W.
  • Other: External lighting has been designed to BREEAM Pol 4 and BREEAM Ene 03 credits for reducing night-time light pollution, with security and car park lighting targets set out in the lighting report. Report P48, P92, P96, P126

Who and where

  • Cheshire East Council, as the applicant and site operator of the Environmental Services Hub Report P19
  • Users of the Cledford Lane depot and surrounding industrial area in Middlewich Report P5, P6, P25
  • Middlewich Eastern Bypass, as recipient of the £176,000 financial contribution

Timeline

  • 13.05.25: Architect's first issue of security lodge plan and elevations drawings for comment Report P199, P203
  • 20.01.26: Latest architect's revision to proposed site plan (kerb position updated to align with topo survey) Report P14, P29
  • 2026-05-27: Strategic Planning Board resolves to approve application 25/4821/FUL with 23 conditions
  • Within 3 years of the decision: Development must commence

Plain English for the jargon

  • BREEAM: Building Research Establishment Environmental Assessment Method, a widely used sustainability rating for buildings.
  • HWRC: Household Waste Recycling Centre, a site where the public can drop off recyclable and bulky household waste.
  • Halite risk assessment: An assessment of risks from underground salt (halite) features, relevant in parts of Cheshire where historic salt extraction can cause ground instability.
  • EV (charging point): An electric vehicle charging bay for cars.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

RESOLVED : That application 25/4821/FUL be APPROVED be as per the officer’s recommendation subject to the formal notification of an internal transfer of the financial contribution of £176,000 towards the Middlewich Eastern Bypass, and subject to the following conditions: 1) Commencement of development (3 years) 2) Approved plans 3) Restriction on storage heights of materials or equipment to match that imposed on permission 15/2355W 4) Implementation of the travel plan approved under 15/2355W. 5) Implementation of the submitted car park management strategy 6) Restrictions on the hours of operation to reflect that contained on permission 15/2355W 7) Implementation of the noise management plan approved under 15/2355W 8) Adherence to maximum noise levels established under permission 15/2355W 9) No burning of materials on site 10) Implementation of the mitigation identified in the air quality assessment 11) Submission of an updated conceptual model, phase II ground investigation and risk assessment, and where necessary a subsequent remediation strategy 12) Where deemed necessary under condition 12, submission of a verification report 13) Testing of all soils brought on site 14) Implementation of measures to deal with unexpected contamination 15) Implementation of the mitigation identified in the Ecological Assessment 16) Submission and implementation of a final updated construction environmental management plan and precautionary working method statements 17) Submission of a scheme to protect nesting birds 18) Submission of a scheme of biodiversity enhancement measures 19) Submission of a biodiversity net gain plan 20) Submission of detailed landscape planting scheme 21) Implementation of tree protection measures 22) Submission of final detailed drainage strategy with maximum discharge rate 23) Halite risk assessment In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Planning has delegated authority to do so in consultation with the Chair of the Strategic Planning Board, provided that the changes do not exceed the substantive nature of the Committee’s Councillors Moss and Jackson left the meeting at the end of this application.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Strategic Planning Board

25/4821/FUL Environmental Services Hub Cledford Lane Middlewich CW10 0JR © Copyright: All rights reserved. This drawing must not be reproduced without permission. Do not scale from this drawing. All dimensions are in millimetres unless otherwise stated. Any discrepancies should be reported to the Architect.

0 10m 20m 40m

N Gate 1 Pump Gate 1A Substation house 1:500 @ A1 8.17m high G01 Gate 2 sprinkler tank Gate 3

2140m² Legend

Site Boundary (Area: 5982m2)

Gate 14 Other Land Owned (Area: 56784m2)

Gate 4

WT1 3991m²

Gate 5

Weighbridge

Weighbridge G21 2529m²

Fire Hydrant

WT2 1812m²

P6 Kerb position between private road & land for development 20.01.26 GC PEH Fuel store

updated to align with TOPO Pumps

Pumps

P5 Other land owned line amended following comments from 27.11.25 GC PEH Planning Consultant P4 Site boundary amended 07.10.25 GC FW P3 General Issue following Initial Budget Estimate 22.07.25 GC PEH P2 Boundary Lines Shown 24.06.25 GC PEH Revision Description Date Drawn Checked Gate 15 Halliday Meecham Architects Limited Plant propogation Bin 111 Piccadilly Manchester M1 2HY Store +44 (0)161 661 5566

4 Devonshire Street London W1W 5DT G37 +44 (0)203 440 5175

Bin 569m² [email removed] www.hallidaymeecham.com Hydro Fuel Store Plant G38 Overflow propogation Client: Cheshire East Council Project: CEC Environmental Hub Secrutiy Lodge 360m² Phase/ Location: Cledford Lane, Middlewich, CW10 0JS Drawing: Site Plan as Existing Scale @ A1 Scale @ A3 Date: Drawn: Checked: Job No. Drawing No. 1:500 1:1000 24-06-25 SD PEH 5821 10002 Site Plan as Existing Drawing Ref. Revision

1 : 500 @ A1 5821-HMA-CE-00-DR-A-10002 P6 © Copyright: All rights reserved. This drawing must not be reproduced without permission. Do not scale from this drawing. All dimensions are in millimetres unless otherwise stated. CEC Depot Any discrepancies should be reported to the Architect. signage max 1.5m2

0 10m 20m 40m

N Gate 2 Pump Gate 3 Substation house F1 - New 2.4m high 15 Gate 1 green (RAL 60005) 1:500 @ A1 8.17m high security fence line G01 sprinkler tank around staff car park

6000 Existing brick New double leaf height

11000 building removed & 2140m² barrier with nudge bar. See drawing: 20110 for EV EV EV EV EV EV 28 infilled with planting. Legend further details All walkways wide

2200 Site Boundary (Area: 5982m2) enough for future EV Proposed new EV EV EV EV 41 charging points. Security Lodge Other Land Owned (Area: 56784m2) Gate 4

6000 Existing tree removed New pedestrian Existing tree removed 54 gate Material Key Existing 67 Existing tree removed fence line F1 - Dulok S1 Securiy Fencing (2.4m High) extended (RAL 60005) Parking spaces

6000 (new fencing Existing tree retained 3m x 5m to match existing - 84 2.4m high Existing tree retained green (RAL 60005) 84No. spots with one way system including 10 EV chargers WT1 F1 - New 2.4m high green (RAL 60005) security 3991m² fence line around staff car park

G21 2529m²

F1 - New 2.4m high green (RAL 60005) security P14 Kerb position between private road & land for development 20.01.26 GC PEH Existing fence line around updated to align with TOPO Containers bin store Relocated P13 Further annotations & material key added 18.12.25 GC PEH P12 New vehicle access gates ommited from plan & annotations 16.12.25 GC PEH Fire Hydrant 10m2 Scrap Bins added regarding new fence line HWRC 45m2 P11 Other land owned line amended following comments from 27.11.25 GC PEH 221No. Eurobins Planning Consultant & NMA works removed 352m2 2No. F1 - New 2.4m P11 Other land owned line amended following comments from 27.11.25 GC PEH high green (RAL Loading 60005) security Planning Consultant & NMA works removed Bays fence line around bin store P10 All barriers removed from Cledford way entrances & gates 13.11.25 GC PEH

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25-4821-FUL Key PlansMinutes 2.7 MB DownloadRead as text
PDF
25/4821/FUL: ENVIRONMENTAL SERVICES HUB, CLEDFORD LANE, MIDDLEWICH: Additional car parking, relocated bin store and a new security lodgeMinutes 425 KB Download

At this meeting

Whole meeting

More from Cheshire East Strategic Planning Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 22 July 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Sep 2026 25/1573/FUL - Full planning application for a residential development including associated access, infrastructure and landscaping. Land off Cumber Lane, WilmslowThat application 25/1573/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 3-year ti... Approved Open
16 Sep 2026 25/2071/FUL - Full planning application for a residential development and the provision of associated access and infrastructure works including roads, drainage infrastructure, car parking, public open space and landscaping. Land at Dean Row Road, WilmslowThat application 25/2071/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 2-year ti... Approved Open
16 Sep 2026 National Scheme of DelegationThat the Strategic Planning Board Noted the changes introduced by the for Planning Functions that will be implemented... Noted Open
22 Jul 2026 Minutes of the Previous MeetingThat the minutes of the meetings held on 27 May 2026 and 9 June 2026 be approved as correct records. Approved Open