What was decided
Cabinet approved the Terms of Reference for procuring external specialist advice, built on three core principles covering the current estate, health and wellbeing, and financial sustainability. Report P2, P31, P32, P33
Cabinet approved the start of work to commission a new leisure service and delegated authority to the Director of Planning and Environment, in consultation with the Portfolio Holder, to develop the model, procure advice, and run consultation before returning to Cabinet. Report P3
Cabinet approved the financial commitment in Appendix C and the addition of a Strategic Commissioning Saving to the MTFS, with phasing from 2029 delegated to the Director of Planning and Environment and the Director of Finance. Report P4, P5, P49
Why
The existing leisure contract with Everybody Health and Leisure expires in April 2029 and cannot be extended under the Procurement Act 2023, which came into force in February 2025. Report P6, P21, P28
The Council currently spends £5.477m a year on leisure, including a £911,000 management fee and £4,390,925 in facilities management costs for 2025/26, and is seeking a financially sustainable model. Report P9, P48
Usage across the 14-site estate varies significantly, and the Council wants an evidence-based options appraisal to inform the future delivery model. Report P10, P17, P18, P19
What happens next
The Director of Planning and Environment will develop the commissioning model, procure a specialist consultant, and consult on proposals before a further Cabinet decision on the chosen delivery model. Report P3, P27
The Executive Director of Resources, as Section 151 Officer, will approve and arrange budget virements in line with Finance Procedure Rules. Report P4
An Equality Impact Assessment will be completed as part of the commissioning process, informed by stakeholder engagement. Report P60
The money
- £911,000 Annual operational management fee to EHL for 2025/26 Report P9
- £175,000 Pension contribution for 2025/26, not included in the management fee Report P9
- £4,390,925 Facilities management costs for 2025/26 paid by the Council as corporate landlord Report P9
- £5.477m Total current annual Council expenditure on leisure services, to be eliminated through the new model Report P48, P49
Options considered
- Chosen: Option 1: Commission a new leisure service by procuring an external consultant to explore different options. Provides a credible, evidence-based options appraisal; current contract cannot be extended and a strategic review is needed for value and sustainability. Report P35, P37
- Rejected: Option 2: Complete the leisure commissioning process without external support. Risk of an uninformed decision on a large contract, potentially increasing medium to long term costs to the Council. Report P38
- Rejected: Do nothing and let the current contract lapse without replacement. Would leave leisure centres without an operator while the Council still paid maintenance and utility costs. Report P36
Implications
- Financial: A Strategic Commissioning Saving is to be added to the MTFS from 2029, with the aim of removing the current £5.477m annual leisure subsidy. Report P5, P48, P49
- Legal: The contract cannot be extended beyond April 2029 under the Procurement Act 2023, so a new commissioning exercise is required. Report P21, P28
- Equalities: An Equality Impact Assessment will be produced as part of the commissioning process, informed by stakeholder engagement. Report P60
- Staffing: Internal officer resource will be needed to procure and manage the consultant, present findings to Cabinet, and oversee the new contract. Report P54
- Risk: Without the recommended approach, a financially sustainable leisure service may not be achieved, adding to the Council's financial pressures. Report P55
- Other: The work supports Corporate Plan commitments on unlocking prosperity, improving health and wellbeing, and ensuring an effective council. Report P57, P58, P59
Who and where
- Cheshire East residents and leisure centre users across the borough Report P10, P27
- Everybody Health and Leisure, the current charitable trust operator of 9 centres Report P6, P7
- Users of the 14-site leisure estate, including 4 joint use wet sites, 2 joint use dry sites, 5 standalone wet sites and 3 standalone dry sites Report P10, P13, P14, P15, P16
- Internal Council teams in Adults, Children's and Place services involved in commissioning Report P29
Timeline
- May 2014: Original operating contract with EHL entered into for an initial 10 years Report P6
- 2019: Cabinet decision to extend the contract, taking the end date to May 2029 Report P6
- February 2025: Procurement Act 2023 came into effect, preventing further contract extension Report P21
- April 2029: Current leisure contract expires Report P21, P28
- From 2029 onwards: Strategic Commissioning Saving to be phased into the MTFS Report P5, P49
Plain English for the jargon
- MTFS: Medium Term Financial Strategy, the Council's multi-year budget plan
- EHL: Everybody Health and Leisure, the current charitable trust operating the Council's leisure centres
- Joint use sites: Leisure facilities shared with a secondary school, used during school hours
- LTS: Learn to Swim membership
- SWOT: Strengths, Weaknesses, Opportunities and Threats analysis