CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cheshire East Council
Cabinet, Thursday 4 June 2026 at 10.30am

Local Plan - Approval to commence

Approved Executive 3 papers

AI summaryCheshire East Cabinet approves start of new Local Plan, publishing a 30-month timetable and a notice of intention to commence, with adoption targeted for 30 March 2029.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelegation to Executive Director of Place for scoping consultation
MoneyNot stated
What happens nextScoping consultation starts 21 July 2026Gateway 1 self-assessment due 30 October 2026
Who it affectsCommunities across Cheshire East boroughExcludes Peak District National Park area

What was decided

Cabinet approved the Cheshire East Local Plan timetable (appendix 2) for publication and the Notice of Intention to Commence (appendix 1). Report P5

Cabinet delegated approval of final Scoping Consultation content and design, including topic papers, to the Executive Director of Place in consultation with the Portfolio Holder for Planning, Regeneration and Housing. Report P5, P48

The new Local Plan will integrate a Cheshire East Minerals and Waste Local Plan and follow a 30-month process with three gateway assessments, targeting adoption on 30 March 2029. Report P7, P10, P44

Why

The Council has a statutory duty to prepare a Local Plan under the new plan-making system set out by government in November 2025 and the Town and Country Planning (Local Planning) (England) Regulations 2026. Report P1, P50, P55

Regulations enabling the new style of plan were published on 25 March 2026, meaning the Council can now formally commence preparation. Report P6, P9

Previous work, including an Issues Paper consultation in 2022, two Call for Sites exercises in 2024 and 2026, and multiple evidence base studies, has positioned the Council to start. Report P11, P12, P19

What happens next

The Commencement Notice is to be published on 12 June 2026, triggering a minimum four-month preparation period before Gateway 1. Report P27, P30

A Notice of Scoping Consultation is due by 21 July 2026, with representations to be received by 1 September 2026. Report P31, P33

The Council will make its Gateway 1 self-assessment available on 30 October 2026, with full plan adoption targeted for 30 March 2029. Report P34, P44

The money

  • £70k Government funding for a Green Belt Review Report P21
  • £50k Government funding to support implementation of digital planning Report P21
  • £112k Government funding to implement new system plan-making Report P21
  • £230k Government funding for salary bursaries to support recruitment Report P21

Options considered

  • Chosen: Commence new system plan making now. Required by statutory duty and supported by preparatory work already undertaken Report P10, P18, P50
  • Rejected: Do not commence plan making. Would delay adoption, extend uncertainty for communities, decision makers and applicants, and leave development unplanned for Report P53

Implications

  • Legal: The Council must comply with the Town and Country Planning (Local Planning) (England) Regulations 2026 and the Planning and Compulsory Purchase Act 2004 as amended by the Levelling-up and Regeneration Act 2023. The Secretary of State can intervene or appoint independent Local Plan Commissioners if the Council fails to progress. Report P50, P56, P57
  • Financial: Costs are reflected in the Medium-Term Financial Strategy 2026 to 2030, using an existing earmarked reserve that needs topping up at outturn 2025/26 to avoid in-year pressure. Report P59
  • Staffing: Human resources support is required to resource the Strategic Planning team, with salary bursaries of £230k secured for recruitment. Report P21, P61
  • Equalities: Equality Impact Assessments will be carried out at each stage of plan preparation. Report P68
  • Climate: The new Local Plan offers a chance to refresh policies to mitigate climate change, supporting the Council's pledge to be carbon neutral by 2045. Report P70
  • Other: The Plan will include policies to support health and wellbeing, including for young people and cared for children, across the whole borough including rural areas. Report P71, P72
  • Risk: Risk management is built into the project's Prince2-style programme management approach, with resources and risks kept under review and escalated through governance. Report P20, P62

Who and where

  • Communities and residents across Cheshire East (excluding the Peak District National Park area) Report P55, P64
  • Planning applicants, developers and landowners making planning applications in the borough Report P53, P66
  • Members and officers taking planning decisions in other council committees Report P64, P66
  • Stakeholders responding to the Scoping Consultation and later plan consultations Report P48, P49

Timeline

  • 12/06/2026: Council makes notice of intention to commence local plan preparation available Report P30
  • 21/07/2026: Notice of scoping consultation made available Report P31
  • 01/09/2026: Deadline for scoping consultation representations Report P33
  • 30/10/2026: Gateway 1 self-assessment made available by Cabinet or Portfolio Holder Report P34
  • 05/05/2027: Local elections Report P35
  • 05/07/2027: Notice of plan content and evidence consultation made available Report P36
  • 16/08/2027: Deadline for plan content and evidence consultation representations Report P37
  • 31/01/2028: Gateway 2 advice sought from Cabinet or Portfolio Holder Report P38
  • 03/05/2028: Notice of proposed local plan consultation made available Report P39
  • 28/06/2028: Deadline for proposed plan consultation representations Report P40
  • 25/08/2028: Gateway 3 advice sought (prescribed requirements assessment) Report P41, P42
  • 29/09/2028: Proposed Local Plan submitted to Secretary of State for examination Report P43
  • 30/03/2029: Target date for Full Council to consider adopting the Local Plan Report P44

Plain English for the jargon

  • Local Plan: Statutory planning document setting out policies and site allocations used to decide planning applications across a local authority area.
  • Notice of Intention to Commence: Formal notice the Council must publish to start preparing a new style Local Plan under the 2026 Regulations.
  • Scoping Consultation: Early stage consultation on the proposed approach to policy development, evidence base and engagement plan, run before Gateway 1.
  • Gateway assessments: Three formal checkpoints (Gateway 1, 2 and 3) in the new plan-making process that the Local Plan must pass before independent examination.
  • NPPF: National Planning Policy Framework, the government's national planning policy document.
  • MTFS: Medium-Term Financial Strategy, the Council's multi-year budget planning document.
  • Prince2: A structured project management method used to plan, manage and control projects.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED (unanimously): That the Cabinet Approve the Cheshire East Local Plan timetable (appendix 2) for publication. Publish the Notice of Intention to Commence the Cheshire East Local Plan (appendix 1). Delegate approval of the final content and design of the Scoping Consultation documentation, including accompanying topic papers and other information, to the Executive Director of Place in consultation with the Portfolio Holder for Planning, Regeneration and Housing.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Cabinet

Executive summary

2 Cheshire East Council has a statutory duty to prepare the Cheshire East Local Plan and will do so under the government’s new plan making system. Government published details of the new system in November 2025 and has since published Regulations in 2026, enabling new style local plans to be formally commenced. Whilst revised national planning policy and further detailed guidance is expected to be published during 2026, the Council is now able to make a formal start on its new Local Plan.

3 This report will initiate two of the first three stages of the new process by seeking approval to publish the Cheshire East Local Plan Timetable and Notice of Intention to Commence the Cheshire East Local Plan. The third stage, to undertake the Scoping Consultation, is proposed to be initiated through a separate delegation to the Executive Director of Place in consultation with the Portfolio Holder for Planning, Regeneration and Housing.

OFFICIAL RECOMMENDATIONS

The Cabinet is recommended to:

1. Approve the Cheshire East Local Plan timetable (appendix 2) for publication; 2. Publish the Notice of Intention to Commence the Cheshire East Local Plan (appendix 1); and 3. Delegate approval of the final content and design of the Scoping Consultation documentation, including accompanying topic papers and other information, to the Executive Director of Place in consultation with the Portfolio Holder for Planning, Regeneration and Housing.

Background 4 National planning reform was first introduced via a White Paper in 2020 which eventually led to the delivery of the Levelling Up and Regeneration Act (LURA) in 2023, the basis of a new system for local plans. Bringing the new style plan making provisions of the LURA into effect requires secondary legislation (regulations). These were published on 25th March 2026.

5 The Councils Local Plan Strategy (LPS) was adopted in 2017 and reviewed in July 2022 when planning reform was being prepared. At that point a deadline of June 2025 was introduced to submit plans under the existing legal framework. It was decided that there was not sufficient time to complete an ‘old style local plan’, and at the time regulations for the new planning system were expected to be published in 2024. In anticipation of commencement in 2024, it was therefore decided to prepare a ‘new system’ local plan which would integrate a new Cheshire East Minerals and Waste Local Plan.

6 However, delays to the progress of national planning reform ensued with the deadline for ‘old style’ plans eventually extended to December 2026.

7 The roll out of planning reform has gathered pace since December 2025 with the publication of further Planning Practice Guidance, regulations, legislation and importantly a consultation on a revised NPPF which will support the new approach to plan making. This consultation closed on 10th March with a finalised version of the NPPF expected to be published later this year.

8 Together, these elements of planning reform change how local plans will be produced with an expectation that the process will be completed within 30 months and be subject to three ‘gateway’ assessments which must be completed before the final examination of the plan. 9 The Strategic Planning Team has carried out significant preparatory work to enable the Council to meet this 30-month timeframe. This work includes:

(a) Consultation on an ‘Issues Paper’ and multiple topic papers in 2022.

(b) Two Call for Sites exercises in 2024 and 2026.

(c) Establishing a project management approach to the programme, led by the Councils Project Management Office (PMO)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Notice of Intention to Commence Local Plan PreparationAppendix 1 393 KB Download
PDF
Local Plan Timetable June 2026Appendix 2 1.9 MB Download
PDF
Local Plan: Approval to commenceMinutes 235 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Local Plan - Approval to commenceThis decision
  2. Cheshire East Best Start in Life Local Plan 2026-2028Decided
  3. Final Local Transport Delivery PlanNoted
  4. Heritage and Local List Supplementary Planning DocumentApproved
  5. Recommendation from the Highways and Transport Committee: Local Transport Plan - ApprovalApproved
  6. Local Transport Plan - ApprovalApproved

More from Cheshire East Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of Previous MeetingThat the minutes of the meeting held on 2 July 2026 be agreed as an accurate record and signed by the Chair. Agreed Open
3 Sep 2026 2026/27 Budget - Quarter 1 Forecast OutturnRESOLVED (unanimously): That Cabinet 1. Note the factors leading to a forecast balanced position and the contents of ... Noted Open
3 Sep 2026 Strategic Risk Register Update Q4 2025-26 and Q1 2026-27RESOLVED (unanimously): That Cabinet 1. Note the position of the Strategic Risk Register following the Quarter 4 2025... Noted Open
3 Sep 2026 Finance Leadership Improvement Plan Update and ReviewRESOLVED (unanimously): That Cabinet 1. Note the content and progress made against the Financial Leadership Improveme... Noted Open
3 Sep 2026 Performance Management Framework and Q4 Performance 2025/26RESOLVED (unanimously): That Cabinet 1. Approve the Performance Management Framework (PMF) attached at Appendix A. 2.... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies