25/4532/FUL - LAST ORDERS, 116 - 118 Park Lane, Macclesfield, Cheshire East, SK11 6UA
RefusedPlanning6 papers
AI summaryCheshire East Northern Planning Committee has delegated refusal of a planning application at Last Orders, 116-118 Park Lane, Macclesfield, back to officers, citing an inadequate sequential assessment.
Written from the decision and the officer reportPDF Pro
OutcomeRefusedSequential assessment found insufficient
MoneyNot stated
What happens nextOfficers to issue refusalWith delegated authority to amend wording
Who it affectsLast Orders, 116-118 Park Lane, MacclesfieldApplication 25/4532/FUL
What was decided
The committee delegated the application back to officers to refuse, because the submitted sequential assessment does not provide enough information to confirm there are no suitable and available sites in more sequentially preferable locations. Report P3
The recommendation was updated from the main report to reflect updated NPPF (2026) policies and ongoing consultation. Report P1
Why
The development is considered contrary to policy EG5 of the CELPS, SADPD policies RET1 and RET3, and policy TC3 of the NPPF because the sequential assessment is insufficient. Report P3
The update follows revised national planning policy and continuing consultation. Report P1
What happens next
Officers will issue the refusal using the reason set out by the committee. Report P2, P3
The Head of Planning has delegated authority to amend the wording of the decision in consultation with the Northern Planning Committee Chairman, provided changes do not exceed the substantive nature of the decision.
Options considered
Chosen: Delegate to officers to refuse the application. Sequential assessment does not provide enough information to rule out more sequentially preferable sites Report P2, P3
Implications
Legal: Refusal will be issued under planning policy, citing conflict with CELPS, SADPD and NPPF policies. Report P3
Who and where
The applicant for application 25/4532/FUL at Last Orders, 116-118 Park Lane, Macclesfield Report P3
Timeline
2026-08-19: Northern Planning Committee considered application 25/4532/FUL and decided to delegate refusal to officers.
Plain English for the jargon
Sequential assessment: A test for retail and main town centre uses that requires applicants to demonstrate no suitable sites are available in more central (sequentially preferable) locations first.
CELPS: Cheshire East Local Plan Strategy, the local planning policy document for the borough.
SADPD: Site Allocations and Development Policies Document, part of the Cheshire East development plan.
NPPF: National Planning Policy Framework, the government's national planning policy guidance.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68
Resolved
That the application be delegated back to Officers to REFUSE the application for the following reason; 1. The submitted sequential assessment does not provide enough information to conclude that there are no suitable and available sites in more sequentially preferable locations to the application site. The development is therefore contrary to policies EG5 of the CELPS and SADPD Policies RET1, RET 3 and policy TC3 of the NPPF. In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Planning has delegated authority to do so in consultation with the Chairman of the Northern Planning Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Last orders, 116-118 Park Lane, Macclesfield, SK11 6UA
UPDATE PREPARED
18 August 2026
KEY ISSUES
1. NPPF August 2026
Following the publication of the revised National Planning policy Framework (NPPF) on the 17th of August 2026, national policy has been updated. This replaces references to the previous version of the NPPF contained within the main agenda report and is a material consideration.
Principle of development- Main Town Centre use
In respect of paragraph 10.5 of the main report, the definition of Main Town Centre uses has received a minor update as follows;
Main town centre uses: Retail development (including warehouse clubs and factory outlet centres); leisure, entertainment and more intensive sport and recreation uses (including cinemas, restaurants, drive-through restaurants, bars and pubs, nightclubs, casinos, health and fitness centres, indoor bowling centres and bingo halls); banks; professional services; offices; and arts, culture and tourism development (including theatres, museums, galleries and concert halls, hotels and conference facilities).
Specifically, banks and professional services are now also referred to, however this is considered to have no impact on the assessment of this application.
At paragraph 10.8 and 10.15 of the main report, paragraph 91 and 92 of the NPPF have been removed. Policy TC3: Main town centre uses outside of town centres is now instead considered to be of relevance and specifically states that ;
1. A sequential test should be applied to proposals for main town centre uses for which planning permission is required, where these are neither in an existing centre nor in accordance with an allocation for that purpose in an up-to-date development plan.
OFFICIAL 2. The sequential test means that main town centre uses involving new development should be located within town centres identified in the development plan; then, if this is not feasible, in edge of centre locations; and only if suitable sites are not available (or expected to become available within a reasonable period) should out of centre sites be considered. When considering edge of centre and out of centre locations, preference should be given to accessible sites which are well connected to the town centre by sustainable transport modes.
3. Applicants and local planning authorities should exercise flexibility when considering issues such as format and scale, so that opportunities to utilise suitable town centre or edge of centre sites are fully explored.
4. Where a development proposal fails to satisfy the sequential test, or is likely to have a significant adverse impact on one or more of the considerations in policy TC4, it should be refused.
Amendment has also been made to the definitions of edge of centre and out of centre, contained within in Annex B of the NPPF as follows:
Edge of centre: For retail purposes, a location that is well-connected to, and up to 300 metres from, a primary shopping area (if no primary shopping area has been defined in the development plan, it should be regarded as a location that is well- connected to, and up to 300 metres from, that part of the town centre within which retail uses predominate – measured from its outer edge). For all other main town centre uses, a location within 300 metres of a town centre boundary. For office development, this includes locations outside the town centre but within 500 metres of a public transport interchange. In determining whether a site falls within the definition of edge of centre, account should be taken of local circumstances.
Out of centre: A location which is not in or on the edge of a centre but not necessarily outside the settlement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.