Northern Planning Committee, Wednesday 19 August 2026 at 10.30am

25/2053/FUL - Land Of The Former Knowle House, Sagars Road, Handforth, SK9 3EA

Approved Planning 6 papers

AI summaryCheshire East Northern Planning Committee approves application 25/2053/FUL at the former Knowle House site in Handforth, subject to a Section 106 agreement and 32 planning conditions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedApplication at former Knowle House, Sagars Road, Handforth
Money£904 per bed spaceS106 contribution towards local primary care network (GP practice)
What happens nextS106 agreement to be securedPlus discharge of 32 conditions; head of planning authorised to amend wording
Who it affectsHandforth residents and local GP practiceSite at Sagars Road, Handforth SK9 3EA

What was decided

The committee approved application 25/2053/FUL subject to a Section 106 agreement and 32 conditions set out in the decision.

The S106 agreement must secure £904 per bed space towards the local primary care network (GP practice).

Why

The officer recommendation in the report was to approve the application, subject to the same S106 contribution and conditions. Report P1

The committee accepted that recommendation as the basis for its decision. Report P1

What happens next

A Section 106 agreement must be completed to secure the £904 per bed space contribution towards the local GP practice before the decision is issued.

The developer must submit further details to discharge the 32 conditions before and during construction, covering materials, ecology, drainage, contamination, highways and energy.

The Head of Planning is authorised to amend the wording of the decision (conditions, informatives, obligations, reasons) if needed before it is issued.

The money

  • £904 per bed space S106 contribution towards the local primary care network (GP practice)

Options considered

  • Chosen: Approve subject to S106 and conditions (as recommended). Followed the officer recommendation in the report Report P1

Implications

  • Financial: Developer must pay £904 per bed space to the local primary care network via a Section 106 agreement.
  • Legal: Approval is contingent on completion of a Section 106 legal agreement before the decision is issued.
  • Other: Conditions require biodiversity net gain, birdstrike avoidance measures, badger and nesting bird surveys, hedgehog avoidance methods, and a construction environmental management plan.
  • Other: 10% of energy must come from decentralised and renewable or low carbon sources, with details to be submitted.
  • Risk: Contaminated land conditions require Phase I and Phase II reports, a remediation strategy if needed, a verification report, and testing of any imported soil.

Who and where

  • The applicant (unnamed in the papers)
  • Residents of Handforth, particularly those near Sagars Road
  • The local primary care network (GP practice) receiving the S106 contribution
  • On-site ecology, including birds, badgers and hedgehogs, subject to survey and protection conditions

Timeline

  • 2026-08-19: Northern Planning Committee considered and approved application 25/2053/FUL
  • Within 3 years of the decision: Time limit for implementation of the approved development

Plain English for the jargon

  • Section 106 Agreement: A legal agreement between a developer and the local council, used to make a development acceptable in planning terms, often securing financial contributions or local facilities.
  • S106: Short form of Section 106 Agreement, under the Town and Country Planning Act 1990.
  • BNG: Biodiversity Net Gain, a planning policy requirement that developments leave biodiversity in a better state than before.
  • CEMP: Construction Environmental Management Plan, setting out how a construction site will manage environmental impacts.
  • AIA: Arboricultural Impact Assessment, assessing the effect of a development on trees.
  • Bed space: A single sleeping place within a residential or institutional development, used here to calculate the GP contribution.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item66

Resolved

That for the reasons set out in the report the application be APPROVED subject to a Section 106 Agreement to secure the following: • £904 per bed space towards local primary care network (GP practice); And the following conditions as detailed below; 1. 3-year time limit for implementation 2. Development in accord with approved plans 3. Materials to be submitted 4. Windows to ends on east/north east elevation, serving the stairs (A.00.368 Stair 01 and A.00.484 Stair 03)and adjacent circulation spaces on this end gable to be permanently obscurely glazed and non-opening below a height of 1.7m above the floor level of the rooms/spaces they serve. 5. Window and external doors to be set within an external reveal of 100mm from the outer face of the building. 6. External lighting to be horizontally capped 7. Accordance with submitted noise mitigation measures 8. Glint and glare assessment for solar panels to be submitted 9. 10% of energy to be secured from decentralised and renewable or low carbon sources – details to be submitted 10. Measures for birdstrike risk avoidance to be submitted 11. Landscaping details to show how any BNG enhancements to be met – in relation to birdstrike avoidance 12. Landscaping details and implementation including boundaries. Hard landscaping to include permeable surfacing 13. Biodiversity enhancements – strategy to be submitted 14. Standard BNG condition 15. Habitat creation method statement and management and monitoring plan to be submitted 16. Nesting Bird survey to be submitted 17. External lighting - with light cowls. Details to be submitted 18. Updated badger survey to be submitted 19. In accordance with submitted Hedgehog Reasonable Avoidance Methods 20. Development in accordance with CEMP 21. Tree protection and method statement ( non standard ) – scheme to be submitted 22. In accordance with AIA (82-506, R1-4) dated 3rd May 2026 unless otherwise first approved in writing with LPA 23. Details of levels to be submitted – in relation to trees 24. Contaminated land – submission required of Phase I, Phase II, Remediation Strategy if required 25. Contaminated Land – Verification Report to be submitted 26. Contaminated Land – imported soil to be tested for contamination 27. Actions in the event contamination not previously identified found 28. Development to be carried out in accordance with Travel Plan 29. Parking (including cycle parking) provided in accordance with submitted details prior to first occupation 30. Drainage to be in accordance with revised drainage plan 31. Construction Management Plan to be submitted 32. Highways Condition Survey to be submitted In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head ... view the full minutes text for item 66.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Northern Planning Committee

NORTHERN PLANNING COMMITTEE - 19 August 2026

UPDATE TO AGENDA

APPLICATION NO.

25/2053/FUL

LOCATION

Land Of The Former Knowle House, Sagars Road, Handforth, SK9 3EA

UPDATE PREPARED

18 August 2026

KEY ISSUES

1. NPPF update 2. Representation update 3. Planning obligation update

1. National Planning Policy Framework (NPPF) update

1.1The NPPF has been updated, published on 17th August with immediate effect. Prior to this there had been consultation on amendments but the publication date was not released until the day it came into force, after the preparation of the committee report.

1.2The new NPPF includes Plan-making policies and Decision Making Policies. Relevant decision making policies are as follows: S5: Principle of development outside settlements CC2: Mitigation of climate change CC3: Adaptation to climate change HO7: Meeting the need for homes HO8: Providing affordable homes HO9: Specialist forms of accommodation L2: Making effective use of land GB6: Control of development in the Green Belt GB7: Development which is not inappropriate in the Green Belt GB8: Golden Rules DP3: Key principles for well-designed places DP4: The design process TR3: Locating development in sustainable locations TR4: Street design, access and parking HC3: Community facilities and public service infrastructure serving new development F4: Assessing flood risk for decision-making F8: Sustainable drainage systems and watercourses

UNCLASSIFIED N2: Improving the natural environment N3: Trees in new development N6: Areas of particular importance for biodiversity and geodiversity

1.3Under policy S5 of the updated NPPF, only certain forms of development should be approved outside settlements, unless adverse effects outweigh benefits. These forms of development include redevelopment of previously developed land, including a material change of use to residential or mixed use including residential.

1.4Under the updated NPPF, GB7, the proposal would still be assessed as grey belt. The relevant Green Belt purposes test remains as where development does not strongly contribute to any of purposes (a), (b), or (d). The unmet need test remains unchanged under GB2, in this case there being a lack of a five year supply of deliverable housing sites.

1.5In assessing locational sustainability, TR3: Locating development in sustainable locations, requires assessment using the Department for Transport’s Connectivity Tool (www.connectivity-tool.dft.gov.uk/app). This tool indicates a sustainability score of 59%-62% for the site. Nationally this is below average for public transport access and below average overall (excluding driving). Taking into consideration that this is a national comparison, against all areas including inner city locations, it is comparably well connected for a rural edge location.

1.6The Green Belt conclusion is that the benefit of the proposals outweigh harm to the Green Belt, and any other harm.

1.7The proposal, as amended, is considered acceptable under DP3: Key principles for well-designed places. Conditions are recommended to ensure quality of the development , in accordance with DP4.

1.8HOU7: relates to meeting needs for homes including different groups as set out under HOU1, which includes older people, including those who require care homes. An assessment of need has been provided.

1.9Policies N2 and N6 relate to improvement of the natural environment and areas of particular importance for biodiversity and geodiversity. Subject to conditions, there would not be significant adverse effects on the integrity of the site adjacent local wildlife site. Environmental qualities of the land and adjacent land have been assessed. Conditions include for ecological enhancements.

1.10A site specific flood risk assessment was submitted, which complies with F4, for sites over one hectare in area.

1.11Overall it is not considered that the amendments to the NPPF result in any material change to the assessment of the proposal and the recommendation.

2. Representation Update

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(5) Update Report: 252053FULMinutes 149 KB DownloadRead as text
PDF
(5) Update Report: 252053FULMinutes 149 KB Download
PDF
(5a) 2053 Key PlansMinutes 17 MB Download
PDF
(5a) 2053 Key PlansMinutes 17 MB Download
PDF
25/2053/FUL: Land Of The Former Knowle House, Sagars Road, Handforth, SK9 3EAMinutes 531 KB Download
PDF
25/2053/FUL: Land Of The Former Knowle House, Sagars Road, Handforth, SK9 3EAMinutes 531 KB Download

At this meeting

Whole meeting

Who was there

26 of 26 attended
SB
Councillor Sarah Bennett-WakeCommittee Member, present
MB
Councillor Mary BrooksCommittee Member, present
CB
Councillor Craig BrowneCommittee Member, present
TD
Councillor Tony DeanCommittee Member, present
DE
Councillor David EdwardesChair, present
KE
Councillor Ken EdwardsCommittee Member, apologies, sent representative
TJ
Councillor Thelma JacksonCommittee Member, present
HM
Councillor Hannah MossCommittee Member, present
MS
Councillor Mike SewartCommittee Member, present
LS
Councillor Lesley SmethamCommittee Member, present
JS
Councillor Julie SmithCommittee Member, present
FW
Councillor Fiona WilsonVice-Chair, present

All 26 on the meeting page

On this subject at Cheshire East

Search all
  1. 25/2053/FUL - Land Of The Former Knowle House, Sagars Road, Handforth, SK9 3EAThis decision
  2. 25/1573/FUL - Full planning application for a residential development including associated access, infrastructure and landscaping. Land off Cumber Lane, WilmslowApproved
  3. 25/2071/FUL - Full planning application for a residential development and the provision of associated access and infrastructure works including roads, drainage infrastructure, car parking, public open space and landscaping. Land at Dean Row Road, WilmslowApproved
  4. 26/0640/FUL - LAND ADJACENT TO ALFRED KING CLOSE SHAVINGTON, CREWE, CW2 5UW: Demolition of existing storage buildings, erection of 9 no. dwellings, 1 no. vehicular access point, associated parking and landscapingApproved
  5. 25/3691/FUL - LAND OFF PADGBURY LANE, CONGLETON: Full planning application for residential development for 18 dwellings (Use Class C3), including access, landscaping, parking, servicing and ancillary infrastructureApproved
  6. 25/4415/FUL - BIRCHWOOD HOUSE, 12 BIRCH LANE, HOUGH CW2 5ZG: Demolition of existing buildings and structures; and erection of 8 no. new dwellings, associated landscaping, access and infrastructure worksApproved

More from Cheshire East Northern Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 24 June 2026 be approved as a correct record. Approved Open
19 Aug 2026 26/0581/FUL - The Cave, 91 - 95 Mill Street, Macclesfield, SK11 6NNThat the application be REFUSED as detailed in the Officer recommendation for the following reasons; 1. The proposals... Refused Open
19 Aug 2026 25/4532/FUL - LAST ORDERS, 116 - 118 Park Lane, Macclesfield, Cheshire East, SK11 6UAThat the application be delegated back to Officers to REFUSE the application for the following reason; 1. The submitt... Refused Open
19 Aug 2026 Tree Preservation Order 2026 - Alderley Edge - Brocklands, Brook LaneThat the Tree Preservation Order at Brocklands , Brook Lane, Alderley Edge be confirmed with no modifications. The Or... Decided Open