Resolved
Decision made: That the progress report be noted.
Executive Cabinet noted this item on Thursday 30 March 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision made: That the progress report be noted.
1. The purpose of the report is to update the Executive Cabinet on progress with the Lancashire Local Area Agreement (LAA).
CORPORATE PRIORITIES
2. The LAA represents an agreement between Government, the Local Authority and its partners on an agenda for improvement over a three-year period. It is important that the LAA is consistent with local priorities in order that it doesn’t detract from the pursuit of our Community and Corporate Strategy priorities.
3. The issue raised and recommendations made in this report involve risk considerations in the following categories:
Strategy 4 Information Reputation 4 Regulatory/Legal Financial 4 Operational 4 People Other
4. As indicated in paragraph 2 above it is important that the LAA is consistent with our Community and Corporate Strategy priorities. Following CPA significant effort has been invested in providing greater clarity and focus locally through our Community and Corporate strategies. We do not now want to lose this focus through the imposition of targets through the LAA which are not priorities for Chorley.
5. Within the LAA ‘stretch targets’ will be identified which will attract Performance Reward Grant (PRG). If these targets are not achieved a reduced level of PRG will be payable.
6. As the LAA is an agreement between Government and the local authority a failure to deliver may be harmful to our reputation.
7. Once the LAA has been signed the Council will need to deliver operationally to ensure that targets are achieved.
ADMINREP/REPORT BACKGROUND
8. LAA’s have been introduced with the aim of improving co-ordination between central government, local authorities and other key partners. The introduction of LAA’s is the first step in the implementation of the Government’s ten-year vision for the future of local government.
9. In simple terms the intention is that the Government will continue to set its high level strategic priorities. Together local authorities, Local Strategic Partnerships, other partners and the regional government office will then work together to identify local solutions (outcomes) which will achieve both the Government’s strategic priorities and local priorities. These local solutions are then brought together in an agreement between the local area and the Government hence the title ‘Local Area Agreement’.
The diagram below sets out the broad principles of the LAA.
National Priorities
Funding Local Area Outcomes Agreement
Local Priorities
10. The LAA is built around four priority blocks and covers a three-year period (01/04/06 – 31/03/09). The blocks are:
• Safer and Stronger Communities • Children and young people • Economic Development and Enterprise • Healthier Communities and Older People.
11. As with the preceding Local Public Service Agreement twelve targets have been selected as reward targets. Each of these targets has been ‘stretched’ ie a higher level of performance has been estimated because of the existence of the LAA and pump priming monies. If these targets are achieved the Government will pay Performance Reward Grant. Arrangements regarding the distribution of PRG have not yet been finalised and a further report will be presented to Members in due course.
12. In two tier areas the countywide LSP, in our case the Lancashire Partnership, are required to lead preparation of, and discussions around, the LAA.
13. Work has been ongoing with the LAA for over ten months now and a number of councillors and partners have been involved in the various workshops and conferences.
LAA UPDATE
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Lancashire Local Area Agreement: Progress ReportReport | 116 KB | DownloadRead as text |
Follow Executive Cabinet at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... | Decided | Open |
| 17 Sep 2026 | Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. | Approved | Open |
| 17 Sep 2026 | Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... | Noted | Open |
| 17 Sep 2026 | Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... | Approved | Open |
| 17 Sep 2026 | Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.