RESOLVED - (1) That the Executive Cabinet be requested to clarify any action it proposes to take to mitigate the potential risks to the delivery of the Capital Programme should the expected capital receipts not be realised as anticipated. (2) That the Director of Finance be requested to indicate in future Capital Programme monitoring reports likely variances in addition to target and performance statistics. (3) That a review of the strategic relevance of the Capital Programme and its reflection of the Council’s corporate and community strategies be included in the list of potential new overview and scrutiny topics for further examination.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To update members on the progress of the 2006/07 Capital Programme, and to seek member support and approval for a number of recommendations from the Capital Programme Board.
CORPORATE PRIORITIES
2. The schemes within the Capital Programme contribute to the achievement of all the Councils corporate priorities.
RISK ISSUES
3. The issue raised and recommendations made in this report involve risk considerations in the following categories:
Strategy Information Reputation Regulatory/Legal Financial Operational People Other
4. The Capital Programme sets out the council strategic investment plans and if these are not delivered it will not fully achieve its strategic objectives, running the risk of damaging the Councils reputation.
5. The Capital Programme also carries a significant financial risk. This is in terms of ensuring value for money, maximising resources available, and managing the performance to ensure the least possible impact on the revenue account.
6. The estimated financing of the programme in 2006/07 takes into account capital receipts from the sales of assets that have not yet been received. Should they not be received some schemes within the programme may need to be frozen or the level of external borrowing increased.
Background
7. This report follows the same format as the Capital Monitoring reports in 2005/06, which details the performance of the capital programme followed by recommendations from the Capital Programme Board.
8. On the 29th June 2006 Executive Cabinet approved the 2006/07 capital programme budget of £12,160,320.
ADMINREP/REPORT HOW ARE WE PERFORMING?
9. The Capital Programme Board has been established now for 15 months, and has made good progress ensuring a more controlled and successful delivery of the programme.
10. Chorley Council’s approach to project management is a well thought of method within the North West. In May we hosted a North West eGovernment Group event, which involved a presentation on how we approach project management here in Chorley. Recently the North West Centre of Excellence also chose our project management toolkit, to promote as being best practice for managing projects.
(A) Key Performance Indicators
11. High level monitoring of the Capital Programme is carried out through 4 Performance Indicators, which have been described in previous Executive Cabinet reports. Table 1 lists these and shows targets and current performance.
Performance Indicator Target Performance 2006/07 August 2006 % %
1. The % of the Capital Programme budget actually spent. 90 49
2. The % of projects using the toolkit. 70 59
3. The % of successful projects. 90 0
4. The % of capital schemes intended to be completed 85 0 during the year actually completed.
Table 1 - Capital Programme 2006/07 - Key Performance Indicators
12. The performance of the first two targets is already very promising and ahead of schedule.
13. The percentage of the budget actually spent is ahead of target, but this is mainly due to a recent £4.5 million payment in respect of the Eaves Green Link Road.
14. The percentage of projects using the toolkit is already ahead of the 2005/06 year-end result of 34%.
15. The Project Support Officer is working with project managers to increase the number of schemes using the project management toolkit, starting with the largest projects in terms of cost, timescale, and risk, as these schemes will benefit the most from being managed and controlled more effectively.
16. The percentage of successful projects can only be measured on schemes that both use the toolkit, and that have been completed. As no schemes have yet been completed this year, there is currently no data for these measures. This is not uncommon for this time of year.
(C) Capital Monitoring 2006/07
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Chorley Leisure Scrutiny UpdateResolved (unanimously – 1. That the Executive Member for Early Intervention and the officers be thanked for their att...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.