To approve the revised capital programme, attached at Appendix A, which includes an amendment to the programme for this quarter of £40,541m, as detailed at point 12 of this report. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report). 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 31st July 2024.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
5. To ensure the Council’s Capital Programme is monitored effectively.
Other options considered and rejected
6. None, it is a requirement to report quarterly on the Capital and Balance Sheet budget monitoring.
Corporate priorities
7. The report relates to the following corporate priorities:
Housing where residents live well A green and sustainable Borough An enterprising economy with vibrant Healthy, safe, and engaged communities local centres in urban and rural areas
Background to the report
8. The Capital Budget for 2024/25 was set at £19,448m by Council in February 2024. This was decreased following approval of the 2024/25 outturn to £15.253m.
9. Following the changes detailed in this report, the total programme now stands at £16,152m the details of which are shown in Appendix B.
Section A: Capital Programme
Key issues
10. The total cost of the Council’s capital investment programme for 2024/25 has increased since the 2023/24 outturn report approved by Cabinet, from £15,253m to £16.152m as at 31st July 2024. The change reflects variations approved since the last report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.
11. The breakdown of the net increase in the programme of £0,899m is detailed in Appendix B. The net variation includes those variations approved since the previous monitoring report and variations in respect of the reprofiling of budgets within the existing programme net increase.
12. Budget variations approved since the last monitoring report have resulted in a total increase of £40,541m to the capital programme. The table below details the changes.
Table 1: Approved budget changes since the last monitoring report 13. A re-profiling of budgets from 2024/25 to future years has been undertaken. The total movement of budgets from 2024/25 amounts to £2,955m. The movements are shown in Appendix B and explanations are contained in the major variations section that follows.
14. Table 2: Slippage and reprofiling across years
Slippage and reprofiling of Scheme Name budget (to)/from future years £'000 An Enterprising Economy With Vibrant Local Centres In Urban and Local Areas Chapel St and Surrounding Public Realm (1,297) Town Hall and White Hart Works (200) Levelling up :Relocation of Bengal Street (1,000) Green And Sustainable Borough Chorley Health Centre (250) Healthy, Safe and Engaged Communites Astley/Astley Cottage (208)
Total (2,955)
As at 31st July 2024 the actual capital expenditure across the programme was £1,124,104
Major variations in the 2024/25 Capital Programme since the previous report
An Enterprising Economy with Vibrant Local Centres in Urban and Local Areas
15. Public Realm Town centre- virement of a budget of £871k which forms part of the Levelling Up match funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.