Resolved
RESOLVED - that the project highlight report be noted.
Housing Transfer Committee noted this item on Tuesday 10 October 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - that the project highlight report be noted.
Chorley Council Housing Stock Transfer Highlight Report
PROJECT DOCUMENTATION
HIGHLIGHT REPORT
Chorley Council Housing Stock Transfer
Version: 12
Date: 02/10/06
This Project utilises Chorley Borough Councils Project Management Methodology
Author: Helen Schofield
Project Manager: Helen Schofield
Programme Board: Housing Transfer Negotiating Group
Page 1 Chorley Council Housing Stock Transfer Highlight Report
Date of Report 02/10/06
Period Covered
From September 2005 to October 2006
Overall Project Status Fair
A positive ballot result was achieved on August 8th with 69.6% of tenants voting, and 63.1% of those who voted, voted ‘Yes’. The result was accepted and approval given to proceed by the Executive Cabinet on August 24th.
Budget Status Fair
The post ballot budget has now been agreed by the Council and the Section 25 letter sent.
Spent this period Spent to date Balance 18,201 18,201 1,457,449 This includes interest on the loan and non-recoverable VAT and is the total of both budgets.
Schedule Status Fair
The project plan is currently on track, with names now assigned to each item/task.
On track
Products Completed Fair
• Pre ballot and ballot stage complete • Stage 2 ended 8th August • Positive ballot result achieved • • Stock condition survey completed by FPD Savills • Implications of stock condition successfully incorporated in draft business plan • • Environmental survey commissioned – to include asbestos • Survey ready in draft form • Classification of HRA nearing completion • Draft report on future arrangement for Homelessness Service issued • Homelessness report has been reviewed and now completed – been reviewed by Councils consultants, awaiting comments from the Director Of Finance • • Repository now on netstore for all documents • Disengagement issues identified and meeting held on 21st April – updates have now been collated and a more detailed approach will be taken at the Disengagement Sub Group • Post ballot consultants for Council have now been appointed – Lead are Enterprise BWNL and Legal are Trowers and Hamlins. Tribal and Wright Hassall have been retained as the lead and legal advisors respectively to CCH
Page 2 Chorley Council Housing Stock Transfer Highlight Report
• 1st post ballot report went to the Exec Cabinet on 24th August • A Housing Transfer Committee has been set up to meet on the same day as the HTNG meetings. • Negotiating structures have been drawn up and staffing arrangements set up • Extra sub groups have been established – Asset, Disengagement and Finance and are due to meet monthly • CCH has also established extra groups – Project Management Board, CCH/Adactus liaison group, engagement group and finance group • The Corporate Team has gained an ICT Project Manager, a Corporate Transfer Accountant and the part time Project Assistant’s role has become a full time Project Officer.
• The Section 25 letter has now been sent • VAT Advisor interviews being held 2.10.06 • Draft environmental survey has been received and is with Trowers & Hamlins for comment
Sub Group Reports Fair
Asset Sub Group – Paul Morris (Lead Officer), Roger Handscombe, Helen Schofield, Mike Wingeatt, Sharon Simmonds The Group has met twice and the schedule for assets to transfer is almost complete, this should all be agreed by 7th October. The accommodation offer has been proposed to CCH and their comments are awaited. An inventory of all assets should also be complete by the 7th October. A questionnaire has been sent out to all housing staff and any long serving non housing staff to obtain information which may help identify any risks associated with the warranty process. Responses are due to be collated at the end of October.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Stock Transfer: Project Highlight ReportReport | 266 KB | DownloadRead as text |
Follow Housing Transfer Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2007 | Exclusion of Press and PublicRESOLVED – that the press and public be excluded from the meeting during the consideration of the following items of ... | Decided | Open |
| 22 Mar 2007 | Adjournment of MeetingRESOLVED – That the meeting be adjourned to resume at 2.00pm on Friday, 23 March 2007 to consider (i) an update on th... | Agreed | Open |
| 22 Mar 2007 | Transfer Completion ArrangementsRESOLVED – (1) That, subject to Resolution (2) below, approval be given to the transfer of the Council’s housing stoc... | Approved | Open |
| 21 Feb 2007 | Housing Stock Transfer - Projects Highlight reportRESOLVED – That the report be noted. | Noted | Open |
| 21 Feb 2007 | Exclusion of Press and PublicRESOLVED – That the press and public be excluded from the meeting for the following items of business on the ground t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.