Decision made: That the report be noted and that the pets corner element of the project be retained and progressed. Reason for decision: The retention of the pets corner in the project accords with the public’s expressed wishes and efficient monitoring of the scheme will ensure its delivery on time and within budget. Alternative option(s) considered and rejected: None.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
5. Following notification of the successful Heritage Lottery fund award in 2005, work began on site in February 2006. The Astley Park Project is a high profile project which has a valuable role to play in maintaining and enhancing the quality of life of local people. The regeneration of the park along with a proactive management regime has the potential to offer a hugely enhanced asset to the people of Chorley and visitors.
6. The project has been implemented to a number of individual contracts and the purpose of this report is to update Members on the various aspects of these contracts and the overall project.
Updated Template July 2006 WOODLAND AND TREE CLEARANCE CONTRACT
7. This contract has been completed and all outstanding snagging issues have been resolved.
LAKE CONTRACT
8. The de-silting works have been completed and the dam wall made good. The grading of the silt and the restoration works are planned to be completed by May 2007, as programmed. Overflow works are now being carried out for the woodland water feature. Members who have visited the park recently will notice that the resurfacing of the road across the dam and the installation of the new railings is now complete, as part of the contingency works previously reported.
DEMOLITION CONTRACT
9. The demolition work has been completed along with the health and safety plan.
10. During the demolition work a stone void was revealed within the walled garden. The stone void has been examined by Derbyshire Caving Club and a report of the findings has been provided. The void has been identified as an underground cistern for holding water, possibly for run-off water for watering the gardens. The tank has stone sides with the top constructed of stone slabs. All appear to be in excellent condition. The voids were being maintained, the roof will be reinstated and a manhole incorporated for future access. The extent of the void is to be plotted onto the layout plan and adjustments made from the use of the space to allow for the manoeuvring of vehicles.
LANDSCAPE CONTRACT
11. The landscape tender came in over budget, however, after some amendments the contract figure has been reduced to a more manageable figure of £8,000 above initial budget. The project consultants are confident that further savings can be made within the project to balance this overspend. Alternatively, the £8,000 could be used from within the contingency budget built into the overall project. However, this is not the favoured option at present, so early in the project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.