Decision made: That progress on the project be noted and that the recommendation to approach Heritage Lottery Fund for additional funds for the Building contract, site furniture and the erection of an additional wall to the rear of Astley Hall be approved. Reasons for decision: The expansion of the budget provision will enable the execution of the Building Contract without jeopardizing the design and quality of the renovation project. Similarly, the inclusion of park furniture and the construction of the additional wall will complement and enhance the scheme. Alternative option(s) considered and rejected: None.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
5. Following notification of the successful Heritage Lottery Fund (HLF) award in 2005, work began on site in February 2006. The Astley Park Project is a high profile project which has a valuable role to play in maintaining and enhancing the quality of life of local people. The regeneration of the park along with a proactive management regime has the potential to offer a hugely enhanced asset to the people of Chorley and visitors.
6. The project has been implemented to a number of individual contracts and the purpose of this report is to update Members on the various aspects of these contracts and the overall project. WOODLAND AND TREE CLEARANCE CONTRACT
7. This contract has been completed and all outstanding snagging issues have been resolved.
LAKE CONTRACT
8. The de-silting works have been completed and the dam wall made good. It was hoped that the first grade of the silt would take place by the end of April followed a few weeks later by final spreading and seeding. However the silt is not drying out as quickly as was hoped and therefore we are looking into the possibility of spreading the wet silt to assist the drying out process prior to final grading and seeding.
DEMOLITION CONTRACT
9. The demolition work has been completed along with the health and safety plan.
LANDSCAPE CONTRACT
10. Good progress is being made with the landscape contract, the contractors have made the most of the recent good weather. The renovation of the Ha-ha is complete, work to the front lawns including drainage is also complete. The driveway to the Hall frontage has been tarmaced ready for the resin bound gravel wearing course which will be laid later in the contract. The flags have been removed from the lake side and again the tarmac base course has been laid ready for the resin bound gravel wearing course . These flags are to be reused in the surfacing of the proposed courtyard to the rear of the coach house. The bound gravel path following the western boundary through the woodland north of the lake is complete. Work is ongoing in the walled garden, a new wall is being constructed to the east to enclose the garden on 3 sides and renovation to the existing walls is taking place. The next element of the work to start will be path works within the woodland along the river corridor.
11. The planning application for lighting along Chorley approach has been submitted. Further information has been sought relating to the impact the lighting would have on the bat activity within the area and a design and access statement has been provided. The application is likely to go to the June planning committee.
BUILDING CONTRACT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.