B1:08/00214/CB3 - Coronation Recreation Ground, Devonshire Road, Chorley

Approved Planning 2 papers

Development Control Committee approved this item on Tuesday 1 April 2008. Below is the council's own wording, with the papers it was decided on.

Item32b

Resolved

Recommendation for the full Council to grant conditional planning permission It was proposed by Councillor Ken Ball, seconded by Councillor Pat Haughton, and subsequently RESOLVED (15 – 0) to refer the planning application to the next Council meeting on 22 April 2008 with a recommendation that planning permission be granted, subject to the following conditions: 1. The proposed development must be begun not later than three years from the date of this permission. Reason: Required to be imposed by Section 51 of the Planning and Compulsory Purchase Act 2004. 2. A light shield to prevent light spillage into neighbouring properties as shown on Drawing No. CBC 4 submitted with the application, shall be fitted to the footpath column numbers 1,6,7,9,10,13,12 and 11 (columns as numbered on drawing no 8520-D-01 Rev A). Reason: To prevent light spillage into neighbouring properties and in accordance with Policy No EP21A of the Adopted Chorley Borough Local Plan Review. 3. The lighting hereby permitted shall be restricted to being lit at the following times only (columns as numbered on drawing no. 8520-D-01 Rev A): · Perimeter footpath lighting: between 08.00hrs and 22.00hrs (columns 1,2,4,5,6,7,8,9,10,16,14,13,12,11,20,21). · Footpath lighting serving the central footpath: no time restriction (columns 15,17,18,19,3) · Floodlighting to all pitches: no illumination before 09.00 hrs or after 21.00 hrs. Reason: To safeguard the amenities of local residents and in accordance with Policy Nos. EP20 and EP21A of the Adopted Chorley Borough Local Plan Review. 4. Unless otherwise agreed in writing, before the development hereby commences a scheme to prevent the lighting dazzling drivers on the highway shall have been submitted to and agreed in writing with the Local Planning Authority. The approved scheme shall be then implemented in full and retained at all times thereafter, unless otherwise agreed in writing with the Local Planning Authority. Reason: To safeguard the amenities of local residents and in accordance with Policy Nos. EP20 and EP21A of the Adopted Chorley Borough Local Plan Review.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Development Control Committee

Item B. 1 08/00214/CB3 Referred to Full Council for Decision

Case Officer [name removed] Chorley North West

Proposal Lighting scheme for recreation ground to include footpath, lighting and sports flood lighting

Location Coronation Recreation Ground Devonshire Road Chorley

Applicant Chorley Borough Council

This application is required to go to Committee as it has been submitted by the Council. It is also required to go to Full Council. Consultation Expiry: 3rd April 2008 Application Expiry: 24th April 2008

Proposal: The application is a Regulation 3 application for the formation of a lighting scheme to Coronation Recreation Ground, including footpath lighting and sports flood lighting.

Background: Coronation Recreation Ground is a public park, with Ashfield Road and Devonshire Road running down the west and east sides of the site respectively. The houses on Collison Avenue back onto the north side of the site and the houses on Regent Road back onto the south side.

A central path runs through the park east to west. To the north of this are two tennis courts and two bowling greens, with a further path against the rear of the houses on Collison Avenue. There is a children’s playground in the southeast corner of the park with a path from the central entrance to the park sweeping round through some trees against the properties on Regent Road.

It is proposed to erect two forms of lighting, footpath lighting to both the perimeter footpaths and central footpath in a traditional heritage style, and sports floodlighting to the tennis and bowling greens.

Planning History: A similar application was withdrawn last year (07/00976/FUL).

Planning Policy: LT14: Public, Private, Educational and Institutional Playing Fields, Parks and Other Recreational Open Space.

Representations: At the time of writing the report no representations have been received. Any received will be placed on the addendum.

Consultations: Environmental Services Due to the design and location of the lamps and the proposed time restriction there is no objection.

Applicants Case: Local to Coronation Recreation Ground there are no other safe places in which children can play. Without this site children are forced to play in the street. By lighting the site the useful life of the play area, open spaces and sports facilities can be extended each day. As the site is also extremely popular with dog walkers, both early in the morning and late at night, the proposal will, if approved, have a major effect on feelings of safety.

For some time the site has played host to an unsavoury element once dusk falls. Alongside the juvenile nuisance and underage drinking that often goes undetected there have been numerous instances of substance and solvent abuse and drug dealing, so much so that the site was targeted as part of Operation Nimrod earlier in the year. These concerns are the driving force behind the Police being financial contributors to the scheme.

In keeping with the traditional nature of the recreation ground, and in particular its ironwork, all footpath lighting is being designed in a heritage style. These include black iron effect columns and lanterns. Column feet will feature a level of detail to give a traditional feel. To minimise levels of vandalism intricate features such as frogs legs connections and ladder arms have been designed out, which should make climbing or swinging from the columns more difficult.

Through discussions with the local Police Architectural Liaison Officer it has been proposed that the most appropriate timings for lighting would be as follows: • Perimeter footpath lighting will come on when required and be switched off at 10pm; • Footpath lighting serving the central footpath (through the trees) will remain on all night; • Sports floodlighting will switch on at dusk and off at 9pm at the latest.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
B1:08/00214/CB3: Coronation Recreation Ground, Devonshire Road, ChorleyReport 41 KB DownloadRead as text
PDF
PlanB10800214CB3(1).pdfReport 49 KB Download

At this meeting

Whole meeting

Who was there

15 of 24 attended
HH
Harold Heaton (profile used as a Councillor)Chair, present
DD
David Dickinson (profile used as Cllr)Vice-Chair, present
KB
Kenneth BallCommittee Member, present
FC
Former Councillor, Eric BellCommittee Member, present
AC
Councillor Alan CainCommittee Member, present
HC
Councillor Henry CaunceCommittee Member, present
MD
Councillor Michael DaviesCommittee Member, apologies
MD
Mike Devaney (profile used for Cllr)Committee Member, present
DE
Dennis EdgerleyCommittee Member, present
DG
Councillor Danny GeeCommittee Member, present
PM
Patricia Mary HaughtonCommittee Member, present
RL
Councillor Roy LeesCommittee Member, present

All 24 on the meeting page

On this subject at Chorley

Search all
  1. B1:08/00214/CB3 - Coronation Recreation Ground, Devonshire Road, ChorleyThis decision
  2. 18/01216/CB3 - Coronation Recreation Ground, Devonshire RoadDecided
  3. 18/00205/CB3 - Coronation Recreation Ground, Devonshire Road, ChorleyDecided
  4. Coronation Recreation Ground Phase 2 Approval and Phase 1 UpdateApproved
  5. Planning Application 08/00214/CB3 - Coronation Recreation Ground, Devonshire Road, ChorleyApproved
  6. B1:07/00976/FUL - Coronation Recreation Ground, Devonshire Road, ChorleyDeferred

More from Chorley Development Control Committee

All decisions
MeetingDecisionOutcome
16 Jul 2019 Minutes of meeting Tuesday, 18 June 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 18 June 2019 be approved as a correct record... Approved Open
16 Jul 2019 19/00417/FULMAJ - Land Adjoining Cuerden Residential Park, Nell Lane, CuerdenFull planning permission granted, subject to conditions and a Section 106 legal agreement. Agreed Open
16 Jul 2019 19/00325/FUL - Playing Field, Kem Mill Lane, Whittle-le-WoodsFull planning permission granted, subject to conditions. Decided Open
18 Jun 2019 Minutes of meeting Tuesday, 21 May 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 21 May 2019 be approved as a correct record ... Approved Open
18 Jun 2019 18/00108/FULMAJ - Chorley Rugby Union Club, Chancery Road, Astley Village, ChorleyFull planning permission granted, subject to conditions and a supplemental Section 106 Agreement. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies