Chorley Borough Council
Executive Cabinet, Thursday 15 March 2018 at 6.30pm

Coronation Recreation Ground Phase 2 Approval and Phase 1 Update

Approved Executive 1 paper

Executive Cabinet approved this item on Thursday 15 March 2018. Below is the council's own wording, with the papers it was decided on.

Item18.EC.23

Resolved

Approval granted for: 1. The procurement approach for phase two at Coronation Recreation Ground. 2. Delegated Authority to the Executive Leader and Executive Member (Economic Development and Public Service Reform ) for the awarding of the phase two contract. 3. Submission of a funding bid to Fields in Trust for £5k active Spaces Funding for the provision of finance to deliver structured sessions to engage the community to use the new facilities at Harpers Lane Recreational Ground. Approval granted for: 1. The procurement approach for phase two at Coronation Recreation Ground. 2. Delegated Authority to the Executive Leader and Executive Member (Economic Development and Public Service Reform) for the awarding of the phase two contract. 3. Submission of a funding bid to Fields in Trust for £5k active Spaces Funding for the provision of finance to deliver structured sessions to engage the community to use the new facilities at Harpers Lane Recreational Ground. Reasons for recommendation(s) 1. To deliver the commitments to improve Coronation recreation and Harpers Recreation Grounds as included in the Play, Open Spaces and Playing Pitch Strategy. This work is proposed to be carried out in phases to keep the recreation grounds open for use throughout the enhancement. 2. To spend the Section 106 developer contributions and external funding which has been collected for these improvements. 3. To maintain the assets and ensure they remain in good repair and therefore reduce any health and safety risk to the public and encourage inward investment in the Borough. 4. To promote the use of the space by the community and contribute to the health and wellbeing of the community. Alternative options ... view the full minutes text for item 18.EC.23
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Report of Meeting Date Director of Business Development and Growth (Introduced by the Executive Exec Cabinet March 2018 Member for Economic Development and Public Service)

CORONATION RECREATION GROUND PHASE 2 APPROVAL AND UPDATE ON PHASE 1 TENDER.

PURPOSE OF REPORT 1. To seek approval for the tender process for phase two at Coronation Recreation Ground and provide an update on the phase one works at Coronation and Harpers Lane Recreation Grounds.

RECOMMENDATION(S)

2. To approve the proposed procurement approach for phase two at Coronation Recreation Ground.

3. To delegate the contract award for phase 2 to the Executive Member for Economic Development and Public Service Reform.

4. To submit a funding bid to Fields in Trust for £5,000 Active Spaces Funding to provide finance to deliver structured sessions to engage the community to use the new facilities at Harpers Lane Rec.

EXECUTIVE SUMMARY OF REPORT 5. An exec cabinet report was approved on 18 November 2017 to agree the proposed planned works and budget for Coronation Recreation Ground and Harpers Lane Recreation Grounds and to delegate the contract award for phase one to the Executive Member for Economic Development and Public Service Reform.

6. It was agreed that £449,000 be allocated to Coronation Recreation Ground and £207,000 be allocated to Harpers Lane Recreation Ground. The sources of funding for these improvements are existing Council reserves and capital receipts already committed to play and open space, along with Section 106 developer contributions and external funding bids.

7. As the total value for the phase 2 procurement was unknown owing to the tendering of Phase 1, the procurement approach of phase 2 was agreed to be determined by Exec Cabinet once the grant funding was confirmed and the total cost of phase 1 was fixed.

8. Funding bids submitted have been successful, providing £88,000 towards the project at Coronation Recreation Ground.

9. The pre-tender estimate for delivery of phase 1 on both sites was £150,000 which will carry out essential maintenance works that have been agreed through member engagement. The appointed contractor following tender evaluation quoted £162,000 (including contingency) resulting in budgets needing to be realigned.

10. Phase 2 works at Coronation Recreation Ground consist of a play area for ages 2 – 8 to the value of £150,000 and a MUGA, fitness zone and play equipment for 8+ to a contract value of £170,000. It is proposed to tender these as two separate Design and Build Contracts to run concurrently, procurement have been engaged in this decision and endorsed this approach.

Confidential report Yes No Please bold as appropriate

Key Decision? Yes No Please bold as appropriate

Reason 1, a change in service 2, a contract worth £100,000 Please bold as appropriate provision that impacts upon or more the service revenue budget by £100,000 or more 3, a new or unprogrammed 4, Significant impact in capital scheme of £100,000 or environmental, social or more physical terms in two or more wards

REASONS FOR RECOMMENDATION(S) (If the recommendations are accepted) 11. To deliver the commitments to improve Coronation and Harpers Recreation Grounds as included in the Play, Open Space and Playing Pitch Strategy. This work is proposed to be carried out in phases to keep the recreation grounds open for use throughout the enhancement.

12. To spend the Section 106 developer contributions and external funding which has been collected for these improvements.

13. To maintain the assets and ensure they remain in good repair and therefore reduce any health and safety risk to the public and encourage inward investment in the Borough.

14. To promote the use of the space by the community and contribute to the health and wellbeing of the community.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Coronation Recreation Ground Phase 2 Approval and Phase 1 UpdateReport 202 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 28 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, present
PW
Councillor Paul WalmsleyCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
GD
Councillor Graham DunnCommittee Member, present
GH
Gary HallOfficer, in attendance
CS
Chris SinnottOfficer, in attendance
AK
Asim KhanOfficer, in attendance
ML
Mark LesterOfficer, in attendance
RH
Rebecca HuddlestonOfficer, expected
CM
Chris MoisterOfficer, in attendance

All 28 on the meeting page

On this subject at Chorley

Search all
  1. Coronation Recreation Ground Phase 2 Approval and Phase 1 UpdateThis decision
  2. 18/01216/CB3 - Coronation Recreation Ground, Devonshire RoadDecided
  3. 18/00205/CB3 - Coronation Recreation Ground, Devonshire Road, ChorleyDecided
  4. Planning Application 08/00214/CB3 - Coronation Recreation Ground, Devonshire Road, ChorleyApproved
  5. B1:08/00214/CB3 - Coronation Recreation Ground, Devonshire Road, ChorleyApproved
  6. B1:07/00976/FUL - Coronation Recreation Ground, Devonshire Road, ChorleyDeferred

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies