Internal Audit - Interim report on 2009/10 activities
NotedFinance1 paper
Audit Committee (now Governance Committee) noted this item on Thursday 14 January 2010. Below is the council's own wording, with the papers it was decided on.
RESOLVED – 1. That the report be noted. 2. That approval be given to the deferment of the audit reviews of Contract Standing Orders, Asset Management, the Refuse Collection/Recycling Contract and Equality and Diversity issues to the 2010/11 Audit Plan.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
Report to Audit Committee (now Governance Committee)
Recommendations
2 That the committee approves the deferment of the audits to 2010/2011 for the reasons stated below.
CORPORATE PRIORITIES
3 This report relates to the following Strategic Objectives:
Put Chorley at the heart of Develop local solutions to regional economic climate change development in the central Lancashire sub region Improving equality of Develop the character and feel opportunity and life chance of Chorley as a good place to live Involving People in their Ensure Chorley is a performing ü Communities Organisation
4 The Accounts and Audit Regulations 2003 require every local authority to “maintain an adequate and effective system of internal audit of its accounting records and of its system of internal control in accordance with proper internal audit practices”. Such practices are laid down as standards in the CIPFA Code of Practice for Internal Audit in Local Government in the United Kingdom 2006.
5 The CIPFA Code of Practice defines Internal Audit as “an assurance function that provides an independent and objective opinion to the organisation on the control environment, by evaluating its effectiveness in achieving the organisation's objectives. It objectively examines, evaluates and reports on the adequacy of the control environment as a contribution to the proper, economic, efficient and effective use of resources”.
1 6 The Internal Audit Service therefore seeks to provide assurance that the Council is a performing organisation.
Background
7 This is the second interim progress report for the current financial year and covers the period between 28th August 2009 and 27th November 2009.
INTERNAL AUDIT PLAN
8 Appendix 1 to this report provides a “snapshot” of the overall progress made in relation to the 2009/10 Internal Audit Plan, indicating which audits have been completed, those that are in progress and those that have yet to start. Appendix 1 also shows the time planned and actually spent on individual audits.
9 At this stage the plan is on course to be completed. The majority of audit assignments undertaken to date are on or around budget, with the exception of three which have overrun significantly: National Fraud Initiative (NFI), Estates, Criminal Records Bureau and the residual work from 2008/2009 which was reported to the last meeting. A nominal number of days is allocated to NFI in each Annual Audit Plan. The actual time utilised has increased this year in response to the number of ‘matches’ that we have investigated. The review of Criminal Record Bureau checks was being undertaken by an officer who has moved to Information Services and her work is being completed by another member of our Team. This has resulted in the original number of days allocated being exceeded.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit Committee (now Governance Committee) at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.