Resolved
Recommendation approved.
Executive Cabinet approved this item on Thursday 12 August 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Recommendation approved.
2. Committee is asked to note the report
EXECUTIVE SUMMARY OF REPORT 3. The report advises that, on average, the Council had surplus cash balances of £5.8m on which it received a return of 0.73% during the first quarter of 2010/11. Investments continue to be made only for short periods and with highly rated institutions. The report also includes the commentary of the Council’s treasury advisor on the economic background.
4. It confirms compliance with the prudential indicators specified in the Treasury Strategy .
REASONS FOR RECOMMENDATION(S) (If the recommendations are accepted) 5. No changes in strategy are required.
ALTERNATIVE OPTIONS CONSIDERED AND REJECTED 6. None
CORPORATE PRIORITIES
7. This report relates to the following Strategic Objectives:
Put Chorley at the heart of regional Develop local solutions to climate economic development in the change. Central Lancashire sub-region Improving equality of opportunity Develop the Character and feel of and life chances Chorley as a good place to live Involving people in their Ensure Chorley Borough Council is X communities a performing organization
Updated Template November 2008 INTRODUCTION
8. CIPFA issued the revised Code of Practice for Treasury Management in November 2009, This was adopted by the Council on 2 March 2010. The revised Code suggests that members should be informed of Treasury Management activities at least twice a year. This report therefore ensures this Council is embracing Best Practice in accordance with CIPFA’s revised Code of Practice.
ECONOMIC BACKGROUND:
9. The major features of the quarter were as follows: • Activity indicators suggest that the recovery picked up a little pace in the first quarter; • High street spending recovered after a weak start to the year; • The labour market showed some tentative signs of improvement; • The UK’s trade position deteriorated, despite the weak pound; • CPI inflation remained above target, however the measure of underlying inflation fell; • The Monetary Policy Committee maintained quantitative easing (QE) and kept Bank Rate on hold at 0.5%; • The equity rally went into reverse over concerns about the shape of the global recovery; • The recovery in the US remains fairly strong, but stays weak in the euro-zone
ECONOMIC ACTIVITY
10. The interest rate forecast of the Council’s treasury advisor is as follows:
Now Dec Mar June Sep Mar June Dec Mar 2010 2011 2011 2011 2012 2012 2012 2013 % % % % % % % % % Base rate 0.50 0.50 0.75 1.00 1.50 2.25 2.50 3.50 3.75 5 yr PWLB 2.48 2.95 3.15 3.50 3.50 3.95 4.30 4.70 4.80 10 yr PWLB 3.83 4.40 4.45 4.50 4.60 4.70 4.75 4.95 5.10 25 yr PWLB 4.46 4.75 4.75 4.85 4.90 5.05 5.15 5.25 5.25 50 yr PWLB 4.49 4.75 4.80 4.90 4.95 5.05 5.20 5.25 5.25
• The forecast is based on moderate economic recovery and MPC inflation forecast being below target in two years’ time • The first Bank Rate increase is expected to be in 2011; and to reach 3.75% by March 2013 • Long term PWLB rates are expected to steadily increase to reach 5.25% by early 2013 due to huge gilt issuance, reversal of QE and investor concerns over inflation • There is considerable uncertainty in all forecasts due to the difficulties of forecasting the timing and amounts of QE reversal, the tough cuts outlined in the Emergency Budget, speed of recovery of banks profitability and balance sheet position, changes in the consumer saving ratio, rebalancing of the UK economy in terms of export and import etc • The balance of risks is weighted to the downside TREASURY ACTIVITY
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Treasury Management Activity, 2010/11Report | 170 KB | DownloadRead as text |
Follow Executive Cabinet at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... | Decided | Open |
| 17 Sep 2026 | Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. | Approved | Open |
| 17 Sep 2026 | Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... | Noted | Open |
| 17 Sep 2026 | Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... | Approved | Open |
| 17 Sep 2026 | Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.