11. Three sites were originally identified and feasibility studies were undertaken and the sites deemed potentially suitable, subject to more detailed investigation and public consultation.
12. The progress to date on each site is summarised below:-
Rothwell Road, Adlington
This parcel of land owned by Chorley and is situated in a largely residential area and is adjacent to a school. The land was deemed suitable after the initial feasibility study. However United Utilities have a large diameter pipe running under the site which is subject to an easement agreement. Within this easement there are weight restrictions on the site to protect their apparatus. The Council had hoped that these would not prove to onerous and would allow the development to take place and there would be a certain degree of flexibility.
Unfortunately United Utilities imposed a 6 ton weight limit on the site. With the level of groundwork required and the need to service the site a 6 ton weight limit effectively cuts off the site and prohibits any future development. This is down to the fact that the use of earth moving machines or wagons to take away the spoil well exceeds the weight limit. Therefore, this site is no longer a consideration.
Manor Road, Clayton Le Woods
The public consultation has recently been carried out and all feedback has been responded to. A procurement exercise has been carried out to cost the development works and this is being considered.
There is minor legal issue over access to resolve. Manor Road is a private road and land which adjoins a private road usually has legal rights of access. However due to the fact there is no registered owner of part of the road Chorley needs to apply for a right of access to both the proposed allotment site and the recreational area on the other side of the road. This is a precautionary measure and Legal is currently working with Land Registry to resolve it. Once the access rights issue has been resolved work will commence on site. This site will yield 27 plots and has an area for Community Food Growing.
Duke Street, Chorley
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Allotments: Action Plan UpdateReport | 525 KB | DownloadRead as text |
Follow Executive Cabinet at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... | Decided | Open |
| 17 Sep 2026 | Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. | Approved | Open |
| 17 Sep 2026 | Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... | Noted | Open |
| 17 Sep 2026 | Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... | Approved | Open |
| 17 Sep 2026 | Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.