Resolved
RESOLVED – That the report and proposed revision of the Internal Audit Plan for the remainder of 2010/11 be approved.
Audit Committee (now Governance Committee) approved this item on Thursday 20 January 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the report and proposed revision of the Internal Audit Plan for the remainder of 2010/11 be approved.
2 That the report be noted.
CORPORATE PRIORITIES
3 This report relates to the following Strategic Objectives:
Strengthen Chorley’s Develop local solutions to economic position in the climate change central Lancashire sub region Improving equality of Develop the character and feel opportunity and life chance of Chorley as a great place to live Involving people in their Ensure Chorley is a Communities consistently top performing organisation
4 The Accounts and Audit Regulations 2003 require every local authority to “maintain an adequate and effective system of internal audit of its accounting records and of its system of internal control in accordance with proper internal audit practices”. Such practices are laid down as standards in the CIPFA Code of Practice for Internal Audit in Local Government in the United Kingdom 2006. 5 The CIPFA Code of Practice defines Internal Audit as “an assurance function that provides an independent and objective opinion to the organisation on the control environment, by evaluating its effectiveness in achieving the organisation's objectives. It objectively examines, evaluates and reports on the adequacy of the control environment as a contribution to the proper, economic, efficient and effective use of resources”.
6 The Internal Audit Service therefore seeks to provide assurance that the Council is a consistently top performing organisation.
7 This is the second progress report for the current financial year and covers the period between 1st April 2010 and 26th November 2010.
INTERNAL AUDIT PLAN
8 Appendix 1 to this report provides a “snapshot” of the overall progress made in relation to the 2010/11 Internal Audit Plan, indicating which audits have been completed, those that are in progress and those that have yet to start. Appendix 1 also shows the time planned and the time spent as at the end of November on individual audits.
9 At the last meeting we advised members of the following:
All the residual audit work in relation to the 2009/10 Audit Plan has now been completed; That further work was requested in respect of the Asset Management Audit. This work is now nearing completion and a draft report will be produced in January; That the Maintenance Inspections Regime Audit has been postponed to allow the implementation of new maintenance schedules to become embedded.
10 In addition to the above, the review of Planning Processes exceeded the planned time available. The work carried out included a review of the Play and Recreation Fund bidding process in relation to which an Executive Cabinet decision was made in September 2010. Following this decision further information was received which needed to be incorporated into the audit review.
11 Appendix 2 provides a brief summary of the Internal Audit work undertaken to date, the assurance rating and any agreed areas for improvement.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Final Audit Com Jan Report Appendix 1Appendix | 30 KB | Download |
PDF |
Final Audit Com Jan Report Appendix 2Appendix | 73 KB | Download |
PDF |
Final Audit Com Jan Report Appendix 3Appendix | 29 KB | Download |
PDF |
Final Audit Com Jan Report Appendix 4Appendix | 21 KB | Download |
PDF |
Internal Audit Plan for 2010/11: Interim report for period up to 26 November 2010Report | 47 KB | DownloadRead as text |
Follow Audit Committee (now Governance Committee) at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Mar 2012 | Internal Audit Plan 2012 -13RESOLVED – That the report be noted. | Noted | Open |
| 15 Mar 2012 | Anti Fraud Corruption PoliciesRESOLVED – 1. That the report be noted. 2. That the Chair of Audit Committee write to all Members of the Council to e... | Noted | Open |
| 15 Mar 2012 | Audit Committee Update 2011/12RESOLVED – That the report be noted. | Noted | Open |
| 15 Mar 2012 | Strategic risk update reportRESOLVED – That the report be noted. | Noted | Open |
| 19 Jan 2012 | Annual Audit Letter 2010/11RESOLVED – That the Audit Letter for 2010/11, as presented by the Audit Commission, be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.