Fourth Quarter Performance Report 2011/12: Council projects
AgreedScrutiny1 paper
Overview and Scrutiny Performance Panel agreed this item on Monday 23 July 2012. Below is the council's own wording, with the papers it was decided on.
It was agreed that there was an issue regarding access to Selectmove and the fact that Chorley residents didn’t appear to be bidding for properties – potentially because they were unaware of the scheme. There was a review of the Selectmove scheme currently underway. The issue of moving to smaller properties was for registered social landlords to tackle, but would be impacted by forthcoming welfare reforms changes. RESOLVED – that the report be noted and information on the impact of welfare reform changes be forwarded to Members as soon as it becomes available.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
8. The Corporate Strategy is the key strategic document for the authority and includes performance indicators and key projects which focus on delivering the Council’s nine strategic objectives. The Corporate Strategy mirrors, and outlines the Council’s contribution to, the Sustainable Community Strategy, delivery of which is taken forward by the Chorley Partnership.
9. This report includes an update on the new key projects and targets set out in the 2011/2012 – 2014/15 Corporate Strategy.
PERFORMANCE OF KEY PROJECTS
10. Following the refresh of the Corporate Strategy in November, there are 17 key projects for 2011/2012 – 2014/15. Overall performance of key projects is excellent. 15 of the 17 projects (88%) are either on track or scheduled to start later in the year.
11. At the end of the fourth quarter, ten projects (59%) were rated green, meaning that they are progressing according to timescale and plan: • Deliver the Lex s106 open spaces scheme • Deliver the allotment project • Provide start up support for local businesses • Deliver phase two of the support for high quality independent businesses • Deliver a Jubilee weekend event • Develop and deliver a bus shelter improvement plan • Develop an action plan to tackle social isolation in the borough • Implementation of the customer services migration plan • Undertake the streetscene modernisation project • Relocate the council’s depot
12. Four projects (23%) had not started by the end of the fourth quarter, as they are scheduled to start later in the year in order to balance out project work with core business and manage staff capacity.
13. One project (6%) has been completed during the last quarter, and the initial outputs of this project are detailed below: Project Title Project Status
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Performance Focus: Customer and DigitalResolved (unanimously): 1. That the Executive Member and officers be thanked for their attendance; 2. That ... view t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.