Resolved
RESOLVED – that the information received be noted.
Overview and Scrutiny Performance Panel noted this item on Monday 23 July 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that the information received be noted.
5. The ICT, Customer and Transformation team have a number of key projects due to be delivered during 2012/13. It is critical that these are supported by effective project documentation so that members and senior officers can be made aware of what these projects involve, who will be delivering them, key milestones and delivery timeframes. Recognising the importance of and extent of the work involved in delivering this programme of work, capacity has been given to developing this position statement and working with ICT to monitor and support progress going forwards.
6. This will also enable the Transformation Strategy and Service Plans to clearly reflect what is happening on the ground and for staff involved to have a clearer appreciation of what their priorities are, where the inter-dependencies between projects exist and the timeframes for delivery.
POSITION STATEMENT AND PROGRAMME PLAN
7. The position statement provides an overview of each of the project, the key milestones, details of documentation in the plan, dependencies with other projects and finally a RAG (Red, Amber or Green) status to give an indication as to how the projects are progressing against plan.
8. The majority of the projects should already have in place more detailed project documentation which is being used to effectively manage and monitor project progress on a day to day basis. Where this was not in place in May, commitment has been given by the project managers that it would be developed shortly. Within the position statement this is referred to as a TID (Transactional Implementation Document).
9. The position statement was drafted in early May and already much has changed and progressed since then. In order to effectively maintain and monitor the position statement and progress against it, ICT are developing a project management tool in SharePoint which is estimated to be in place by the end of August.
10. The programme plan provides a visual representation of the timeline in which the programme is being delivered during 2012/13.
IMPLICATIONS OF REPORT 11. This report has implications in the following areas and the relevant Directors’ comments are included:
Finance Customer Services Human Resources Equality and Diversity Legal Integrated Impact Assessment required? No significant implications in this ü Policy and Communications area
GARY HALL CHIEF EXECUTIVE
There are no background papers to this report.
Report Author Ext Date Doc ID Rebecca Huddleston 5579 16/07/12 O&S Position Statement Report
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ICT Programme PlanReport | 443 KB | DownloadRead as text |
PDF |
ICT TRANSFORMATION PROJECTS POSITION STATEMENT MAY 2012 O&S.docxReport | 96 KB | Download |
PDF |
ICT Transformation Programme: projects timeline 2012 13.xlsxReport | 40 KB | Download |
Follow Overview and Scrutiny Performance Panel at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | Minutes of meeting Thursday, 5 March 2026 of Overview and Scrutiny Performance PanelResolved (unanimously):- That the minutes of the meeting held on Thursday, 5 March 2026 be agreed as a correct record. | Agreed | Open |
| 25 Jun 2026 | Chorley Quarter Four Performance Monitoring Report 2025/26Resolved (unanimously): 1. That the Executive Members and officers be thanked for their attendance; 2. That the sugge... | Decided | Open |
| 25 Jun 2026 | Performance Focus: Customer and DigitalResolved (unanimously): 1. That the Executive Member and officers be thanked for their attendance; 2. That ... view t... | Decided | Open |
| 25 Jun 2026 | Revenue Budget Outturn 2025/26Resolved (unanimously): 1. That the Executive Member and Director of Finance be thanked for their attendance; and 2. ... | Noted | Open |
| 25 Jun 2026 | Capital and Balance Sheet Outturn 2025-26Resolved (unanimously): That the Executive Member and Director of Finance be thanked for their attendance; and That t... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.