RESOLVED – 1. That the proposed amendments to the capital programmes for 2012/13, 2013/14 and 2014/15, be approved as presented in columns (3), (7) and (10) of Appendix 1 to the report; and 2. That the Council be recommended to approve the rephasing of capital budgets between 2012/13 and 2013/14, as presented in columns (2) and (6) of Appendix 1 of the report.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
Report of Meeting Date Chief Executive (Introduced by the Executive Executive Cabinet 22 November Member for Resources, Policy 2012 and Performance)
CAPITAL PROGRAMME MONITORING 2012/13 – 2014/15
PURPOSE OF REPORT 1. To update the Capital Programmes for financial years 2012/13 to 2014/15 to take account of proposed budget changes and the rephasing of expenditure to 2013/14.
2. To report the budgeted receipt and use of contributions from developers for the period 2012/13 to 2014/15.
RECOMMENDATION(S)
3. That the Council be recommended to approve the proposed amendments to the Capital Programmes for 2012/13, 2013/14 and 2014/15, as presented in columns (3), (7) and (10) of Appendix 1.
4. That the Council be recommended to approve the rephasing of capital budgets between 2012/13 and 2013/14, as presented in columns (2) and (6) of Appendix 1.
EXECUTIVE SUMMARY OF REPORT 5. Council of 25th September 2012 approved the increase in the 2012/13 to 2014/15 Capital Programme from £14,176,270 to £14,322,860. The £146,590 increase was in respect of schemes in 2013/14 to be funded with contributions from developers: affordable housing - £53,700; and play, recreation and public open space projects - £92,890. In addition, £57,440 of the Housing Renewal budget was allocated to Disabled Facilities Grants in 2012/13; and £201,730 of that budget was rephased to 2013/14 and the same amount to 2014/15 to fund DFGs. Rephasing of £90,000 of the affordable housing budget was required because the contribution to finance it had not yet been received.
6. It is now recommended that the programme should be increased by a further £72,030 to £14,394,890. It is recommended that the budget for additional and replacement refuse and recycling bins should be increased by £78,000. The Housing Renewal budget should be increased by £3,170 to “recycle” a repaid grant. Repairs and minor improvements totalling £9,140 should be moved to the revenue budget.
7. The acquisition of 98 - 102 Market Street and adjacent land on Gillibrand Street has been completed under budget. The saving of £23,890 should be transferred to the Planned Improvements to Assets budget towards the cost of developing the site.
8. Agreement has not yet been reached to construct the Chorley East Health Centre, so it is recommended that budget provision should be rephased to 2013/14 because of the reduced possibility of completing the project during 2012/13. The effect on the revenue budget is neutral, because capital financing costs in 2013/14 would have been recovered from the NHS via the rent of the health centre.
9. In order to improve fire doors at Cotswold House, it is recommended that £13,480 should be transferred from the uncommitted Housing Renewal budget. The council’s partner for the long-term empty homes scheme has been unable to secure additional funding, so the budgeted contribution can be added back to the affordable housing budget pending allocation to specific projects.
10. Streetscene projects rephased to 2013/14 total £55,020. The projects would be financed with external contributions already received.
11. Appendix 2 presents the budgeted use of developers’ contributions from 2012/13 to 2014/15. The balance of uncommitted contributions is indicated to total approximately £422,000.
Confidential report Yes No Please bold as appropriate
Key Decision? Yes No Please bold as appropriate
Reason 1, a change in service 2, a contract worth £100,000 Please bold as appropriate provision that impacts upon or more the service revenue budget by £100,000 or more 3, a new or unprogrammed 4, Significant impact in capital scheme of £100,000 environmental, social or or more physical terms in two or more wards
REASONS FOR RECOMMENDATION(S) (If the recommendations are accepted)
12. The 2012/13 to 2014/15 Capital Programme should be increased to include budget provision for refuse and recycling bins that reflects increased costs and meets demand for new and replacement bins.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.