Proposed Supplemental Planning Obligation

Agreed Planning 1 paper

Development Control Committee agreed this item on Tuesday 23 April 2013. Below is the council's own wording, with the papers it was decided on.

Item13.DC.31

Resolved

RESOLVED (unanimously) – That the Council would not enforce against the non-compliance of conditions 15, 16, 22 and 24 of the planning permission reference 00/00492/FUL and instead enter into an supplemental Section 106 agreement that effectively removed the obligation on the developer to lay out an equipped play area and instead pay a commuted sum of £25,000 to the Play and Recreation Fund that would be allocated across the borough and in addition a commuted sum of £11,892 as a maintenance contribution for the POS defined as recreation land in the original agreement.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Development Control Committee

Background

9. Planning permission was granted in March 2002 for the erection of 70no. dwellings and associated infrastructure on land adjacent to Hurst Brook, Chapel Lane, Coppull, Chorley (Ref: 00/00492/FUL)

10. Permission was granted subject to a number of conditions and also separate obligations contained within a Section 106 Agreement.

11. Of particular relevance here are conditions 15, 16, 22 and 24 that required the submission and approval of a landscaping scheme and its implementation; the submission and approval of a landscaping scheme for the provision of public open space and play areas; and the submission and approval of the phasing provision and equipping of the public open space and play areas.

12. However there is no record held on file that any of these conditions of the planning permission were formally discharged before the development commenced.

13. It is accepted however that the landscaping of the site and the area of public open space indicated on the approved plans has been laid out to the satisfaction of the Council although no play equipment has been provided. According to the Council's Building Control records the development was completed in November 2005 and therefore the time period to require any of the landscaping to be replaced has lapsed in any event.

14. In addition, the terms of the original S106 obligation required the developer to lay out, landscape and provide play equipment on the play area for use as an equipped play area, and lay out and landscape an area of casual open space and amenity space.

15. The Council were obliged to adopt, and thereafter maintain the recreational land comprising the play area, casual open space and amenity open space and accept a transfer of that land from the landowner following the payment of commuted sums.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Supplemental Planning ObligationReport 698 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 21 attended
PW
Councillor Paul WalmsleyChair, present
DR
Councillor Dave RogersonVice-Chair, present
HC
Councillor Henry CaunceCommittee Member, present
JC
Councillor Jean CronshawCommittee Member, present
JD
Councillor John DaltonCommittee Member, present
DD
Councillor David DickinsonCommittee Member, present
DE
Councillor Dennis EdgerleyCommittee Member, present
CF
Councillor Christopher FranceCommittee Member, present
DG
Councillor Danny GeeCommittee Member, present
HH
Councillor Harold HeatonCommittee Member, present
SH
Councillor Steve HolgateCommittee Member, present
RL
Councillor Roy LeesCommittee Member, present

All 21 on the meeting page

More from Chorley Development Control Committee

All decisions
MeetingDecisionOutcome
16 Jul 2019 Minutes of meeting Tuesday, 18 June 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 18 June 2019 be approved as a correct record... Approved Open
16 Jul 2019 19/00417/FULMAJ - Land Adjoining Cuerden Residential Park, Nell Lane, CuerdenFull planning permission granted, subject to conditions and a Section 106 legal agreement. Agreed Open
16 Jul 2019 19/00325/FUL - Playing Field, Kem Mill Lane, Whittle-le-WoodsFull planning permission granted, subject to conditions. Decided Open
18 Jun 2019 Minutes of meeting Tuesday, 21 May 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 21 May 2019 be approved as a correct record ... Approved Open
18 Jun 2019 18/00108/FULMAJ - Chorley Rugby Union Club, Chancery Road, Astley Village, ChorleyFull planning permission granted, subject to conditions and a supplemental Section 106 Agreement. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies