CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Chorley Borough Council
Executive Cabinet, Thursday 27 August 2015 at 6.00pm

Revenue and Capital Budget Monitoring 2015/16 Report 1 (End of June 2015)

Approved Executive 5 papers

Executive Cabinet approved this item on Thursday 27 August 2015. Below is the council's own wording, with the papers it was decided on.

Item15.EC.141

Resolved

Approval granted that the full year forecast position for the 2015/16 revenue budget and capital investment programme be noted. 2. Approval granted that the forecast position on the Council's reserves be noted. 3. Request Council approve the set aside of £100,000 from in-year revenue underspends to fund one-off capital payments to secure recurrent revenue savings on ICT contracts. 4. Request Council approve the use of £39,000 held in reserves for the former NEETs programme to invest in the Town Centre Grants Programme and a further sum of £61,000 be funded from in-year savings. 5. Request Council approve the use of £36,000 from in-year revenue underspends for capital investment in Christmas lighting for the town centre and Market Walk. 6. Request Council approve the Single Front Office Apprenticeships at an estimated cost of £56,000 for two years, and that the unspent budget at 2015/16 year-end be carried forward in an earmarked reserve. 7. Request Council approve the proposed additions and re-profiling of the Capital Programme to better reflect delivery in 2015/16. This requires £166,000 revenue financing of the CCTV Programme to be brought forward from 2016/17 and 2017/18, which would be financed from a reserve earmarked for capital financing. In addition it is recommended that the budget for revenue financing of CCTV should be increased by £85,000, to be met from the forecast underspend. 1. Approval granted that the full year forecast position for the 2015/16 revenue budget and capital investment programme be noted. 2. Approval granted that the forecast position on the Council's reserves be noted. 3. Request Council approve the set aside of £100,000 from in-year revenue underspends to fund one-off capital payments to secure recurrent revenue savings on ICT contracts. 4. Request Council approve the use of £39,000 held in reserves for the former NEETs programme to invest in the Town Centre Grants Programme and a further sum of £61,000 be funded from in-year savings. 5. Request Council approve the use of £36,000 from in-year revenue underspends for capital investment in Christmas lighting for the town centre and Market Walk. 6. Request Council approve the Single Front Office Apprenticeships at an estimated cost of £56,000 for two years, and that the unspent budget at 2015/16 year-end be carried forward in an earmarked reserve. 7. Request Council approve the proposed additions and re-profiling of the Capital Programme to better reflect delivery in 2015/16. This requires £166,000 revenue financing of the CCTV Programme to be brought forward from 2016/17 and 2017/18, which would be financed from a reserve earmarked for capital financing. In addition it is recommended that the budget for revenue financing of CCTV should be increased by £85,000, to be met from the forecast underspend. Reasons for recommendation(s) To ensure the Council’s budgetary targets are achieved. Alternative option(s) considered and rejected None.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Purpose of report

1. This report sets out the provisional revenue and capital outturn figures for the Council as compared against the budgets and efficiency savings targets set for the financial year 2015/16.

RECOMMENDATION(S)

2. Note the full year forecast position for the 2015/16 revenue budget and capital investment programme.

3. Note the forecast position on the Council's reserves.

4. Request Council approve the set aside of £100,000 from in-year revenue underspends to fund one-off capital payments to secure recurrent revenue savings on ICT contracts.

5. Request Council approve the use of £39,000 held in reserves for the former NEETs programme to invest in the Town Centre Grants Programme and a further sum of £61,000 be funded from in-year savings.

6. Request Council approve the use of £36,000 from in-year revenue underspends for capital investment in Christmas lighting for the town centre and Market Walk.

7. Request Council approve the Single Front Office Apprenticeships at an estimated cost of £56,000 for two years, and that the unspent budget at 2015/16 year-end be carried forward in an earmarked reserve.

8. Request Council approve the proposed additions and re-profiling of the Capital Programme to better reflect delivery in 2015/16. This requires £166,000 revenue financing of the CCTV Programme to be brought forward from 2016/17 and 2017/18, which would be financed from a reserve earmarked for capital financing. In addition it is recommended that the budget for revenue financing of CCTV should be increased by £85,000, to be met from the forecast underspend.

EXECUTIVE SUMMARY OF REPORT

9. The projected revenue outturn currently shows a forecast underspend of £444,000 against budget (including savings made in Market Walk financing costs). The report proposes that Council should approve the use of most of the forecast overspend for the funding of service improvements (Recommendations 4 to 9 above), so that £106,000 would be added to General Balances if all proposals are approved.

10. The latest forecast excludes any variation to projected expenditure on investment items added to the budget in 2015/16. These projects are forecast to fully expend in 2015/16 and should there be any balances remaining at year end they will be transferred into specific reserves and matched to expenditure in future years.

11. In the 2015/16 budget the expected net income from Market Walk after deducting financing costs is £0.905m. The latest projection shows that the forecast outturn is £1.055m, most of the improvement being in respect of reduced financing costs.

12. Overall, Net Financing Transactions (interest payable plus MRP, less interest receivable) are expected to be £165k less than budget, mainly because additional PWLB borrowing was not incurred at the end of 2014/15. This borrowing, to replace use of internal cash, might be required before year-end if a longer-term increase in interest rates is imminent.

13. The forecast of capital expenditure in 2015/16 is £10.210m, before rephasing and increasing the CCTV budget.

14. The Council expected to make overall target savings of £150k in 2015/16 from management of the establishment. Savings of £100k have already been achieved for the year, with the remaining balance expected to be achieved over the coming months.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
General Fund Summary v2.pdfAppendix 1 28 KB Download
PDF
Investment Projects.pdfAppendix 2 16 KB Download
PDF
Reserves & Provisions.pdfAppendix 3 32 KB Download
PDF
Capital Programme.pdfAppendix 4 46 KB Download
PDF
Revenue and Capital Budget Monitoring 2015/16 Report 1 (End of June 2015)Report 172 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 22 attended
HH
Hayley HughesOfficer, expected
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, apologies
GD
Councillor Graham DunnCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
PW
Councillor Paul WalmsleyCommittee Member, present
GH
Gary HallOfficer, expected
JC
Jamie CarsonOfficer, in attendance
CM
Chris MoisterOfficer, expected
AJ
Alex JacksonOfficer, in attendance
CR
Carol RussellOfficer, in attendance

All 22 on the meeting page

On this subject at Chorley

Search all
  1. Revenue and Capital Budget Monitoring 2015/16 Report 1 (End of June 2015)This decision
  2. Revenue Budget 2026/27 Medium Term Financial Strategy and Capital Programme 2026-2029Approved
  3. Revenue Budget 2025/26, Medium Term Financial Strategy and Capital Programme 2025-2028Approved
  4. Revenue Budget 2024/25, Medium Term Financial Strategy and Capital Programme 2024-2027Approved
  5. Revenue Budget 2023/24, Medium Term Financial Strategy and Capital Programme 2023-2026Approved
  6. Revenue Budget 2022/23, Medium Term Financial Strategy and Capital Programme 2022-2025Approved

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies