Executive Cabinet, Thursday 19 November 2015 at 6.00pm

Approval for the procurement approach including the award procedure, evaluation methodology and criteria to purchase fifteen 3.5 tonne tipper vans, one refuse collection vehicle, one skip wagon and three ride on mowers

Approved Executive 1 paper

Executive Cabinet approved this item on Thursday 19 November 2015. Below is the council's own wording, with the papers it was decided on.

Item15.EC.166

Resolved

Approval granted to the procurement approach for the Vans via a further competition through the Chest under Crown Commercial Services (CCS) Public Sector Vehicle Purchase Framework agreement RM1070. Lot 2 on this framework covers purchase of these Vans and was undertaken by CCS using the Open Procedure in compliance with the public Procurement Regulations. 2. Approval granted that the procurement approach for the RCV and Skip Wagon via two further competition exercises under separate lots of the EU compliant ESPO (Eastern Shires Purchasing Organisation) Specialist Vehicle Framework Ref 215R-324 via further competition through the Chest. 3. Approval granted to the procurement approach for the Mowers via a further competition through the Chest under ESPO Grounds Maintenance Machinery framework agreement No.274- 14. 4. Approval granted to the evaluation criteria for the Vans, RCV, Skip Wagon and Mowers as follows Vans, RCV and Skip Wagon: Cost = 65% covering purchase price. Quality = 35% including warranty, technical support, delivery and environmental impact. Training will be an unscored specified requirement. Mowers: Cost = 70% covering purchase price. Quality = 30% including warranty, technical support, delivery and environmental impact. Training and a requirement that the Mowers will be delivered during the week commencing 22nd February 2016, will be an unscored specified requirement. The evaluation criteria for all the vehicles may be subject to a minor amendment following clarification from the Framework Managers. 1. Approval granted to the procurement approach for the Vans via a further competition through the Chest under Crown Commercial Services (CCS) Public Sector Vehicle Purchase Framework agreement RM1070. Lot 2 on this framework covers purchase of these Vans and was undertaken by CCS using the Open Procedure in compliance with the public Procurement Regulations. 2. Approval granted that the procurement approach for the RCV and Skip Wagon via two further competition exercises under separate lots of the EU compliant ESPO (Eastern Shires Purchasing Organisation) Specialist Vehicle Framework Ref 215R-324 via further competition through the Chest. 3. Approval granted to the procurement approach for the Mowers via a further competition through the Chest under ESPO Grounds Maintenance Machinery framework agreement No.274- 14. 4. Approval granted to the evaluation criteria for the Vans, RCV, Skip Wagon and Mowers as follows Vans, RCV and Skip Wagon: Cost = 65% covering purchase price. Quality = 35% including warranty, technical support, delivery and environmental impact. Training will be an unscored specified requirement. Mowers: Cost = 70% covering purchase price. Quality = 30% including warranty, technical support, delivery and environmental impact. Training and a requirement that the Mowers will be delivered during the week commencing 22nd February 2016, will be an unscored specified requirement. The evaluation criteria for all the vehicles may be subject to a minor amendment following clarification from the Framework Managers. Reasons for recommendation(s) Under the Council’s contract procedure rules approval by the Executive Cabinet of contract award procedure and evaluation criteria for tenders greater than £75,000 in value is required. Alternative ... view the full minutes text for item 15.EC.166
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Report of Meeting Date Director of Public Protection, Streetscene and Community. Executive Cabinet 19 November 2015 (Introduced by the Executive Member for Resources)

APPROVAL FOR THE PROCUREMENT APPROACH INCLUDING THE AWARD PROCEDURE, EVALUATION METHODOLOGY AND CRITERIA TO PURCHASE FIFTEEN 3.5 TONNE TIPPER VANS, ONE REFUSE COLLECTION VEHICLE, ONE SKIP WAGON AND THREE RIDE ON MOWERS

PURPOSE OF REPORT 1. To seek approval for the procurement approach including the award procedure, evaluation methodology and criteria to purchase: Fifteen 3.5 Tonne Tipper Vans (Vans), estimated total value of £500K One Refuse Collection Vehicle (RCV), estimated value of £135K One Skip Wagon, estimated value of £90K Three Ride On Mowers (Mowers), estimated total value of £96K

RECOMMENDATION(S)

2. To approve the procurement approach for the Vans via a further competition through the Chest under Crown Commercial Services (CCS) Public Sector Vehicle Purchase Framework agreement RM1070. Lot 2 on this framework covers purchase of these Vans and was undertaken by CCS using the Open Procedure in compliance with the public Procurement Regulations.

3. To approve the procurement approach for the RCV and Skip Wagon via two further competition exercises under separate lots of the EU compliant ESPO (Eastern Shires Purchasing Organisation) Specialist Vehicle Framework Ref 215R-324 via further competition through the Chest.

4. To approve the procurement approach for the Mowers via a further competition through the Chest under ESPO Grounds Maintenance Machinery framework agreement No.274- 14.

5. To approve the evaluation criteria for the Vans, RCV, Skip Wagon and Mowers as follows Vans, RCV and Skip Wagon: Cost = 65% covering purchase price.

Quality = 35% including warranty, technical support, delivery and environmental impact.

Training will be an unscored specified requirement. Mowers:

Cost = 70% covering purchase price.

Quality = 30% including warranty, technical support, delivery and environmental impact.

Training and a requirement that the Mowers will be delivered during the week commencing 22nd February 2016, will be an unscored specified requirement.

The evaluation criteria for all the vehicles may be subject to a minor amendment following clarification from the Framework Managers.

EXECUTIVE SUMMARY OF REPORT 6. The report outlines the procurement approach including the award procedure, evaluation methodology and criteria to purchase a number of vehicles as detailed in the report.

Confidential report Yes No Please bold as appropriate

Key Decision? Yes No Please bold as appropriate

Reason 1, a change in service 2, a contract worth £100,000 Please bold as appropriate provision that impacts upon or more the service revenue budget by £100,000 or more 3, a new or unprogrammed 4, Significant impact in capital scheme of £100,000 or environmental, social or more physical terms in two or more wards

REASONS FOR RECOMMENDATION(S) (If the recommendations are accepted)

7. Under the Council’s contract procedure rules approval by the Executive Cabinet of contract award procedure and evaluation criteria for tenders greater than £75,000 in value is required.

ALTERNATIVE OPTIONS CONSIDERED AND REJECTED

8. To not agree contract award procedure and evaluation criteria and fail to comply with the Council procurement rules.

CORPORATE PRIORITIES

9. This report relates to the following Strategic Objectives:

Involving residents in improving their local A strong local economy area and equality of access for all An ambitious council that does more Clean, safe and healthy communities  to meet the needs of residents and the local area BACKGROUND

10. There are a number of vehicles within the Streetscene vehicle fleet that are due for replacement as detailed below:

9 x Tipper Vans (below 3.5 tonnes) – hired 2 x Tipper Vans (below 3.5 tonnes) – owned 4 x ‘Beavertail’ / Tipper vehicles (above 3.5 tonne) – leased 3 x Ride On Mowers - owned 1 x RCV - owned 1 x Skip Wagon - owned

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval for the procurement approach including the award procedure, evaluation methodology and criteria to purchase fifteen 3.5 tonne tipper vans, one refuse collection vehicle, one skip wagon and three ride on mowersReport 150 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 26 attended
HH
Hayley HughesOfficer, expected
AB
Councillor Alistair BradleyDeputy Leader, present
PW
Councillor Peter WilsonExecutive Leader, present
BM
Councillor Beverley MurrayCommittee Member, present
GD
Councillor Graham DunnCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
PW
Councillor Paul WalmsleyCommittee Member, present
GH
Gary HallOfficer, in attendance
JC
Jamie CarsonOfficer, in attendance
CM
Chris MoisterOfficer, in attendance
AJ
Alex JacksonOfficer, expected
EB
Councillor Eric BellObserver, in attendance

All 26 on the meeting page

On this subject at Chorley

Search all
  1. Approval for the procurement approach including the award procedure, evaluation methodology and criteria to purchase fifteen 3.5 tonne tipper vans, one refuse collection vehicle, one skip wagon and three ride on mowersThis decision
  2. Approval for the Procurement of Liquid FuelsApproved
  3. Leisure Contract - Approval to use UK Leisure Procurement FrameworkApproved
  4. Approval for the Contract Award Procedure and Evaluation Criteria for the procurement and Distribution of Waste ReceptaclesApproved
  5. Approval for Procurement of Neighbourhood VansApproved
  6. Approval for the procurement approach including the award procedure, evaluation methodology and criteria to purchase one large (15t) and two compact mechanical sweepers by working in partnership with South Ribble Borough CouncilApproved

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open