Approval to award the contract for project management and quantity surveyor service for Primrose Gardens to Pick Everard under the Scape framework to a contract value of £144,000. 2. Approval of the acquisition of the St John Ambulance Hall with vacant possession for the capital sum of £188,500. 3. Authorisation be delegated to the Head of Legal, Democratic and Human Resources to prepare and execute the necessary legal documentation to complete the purchase of the St John ambulance Hall 4. Approval for the payment of £770 stamp duty plus the legal fees for St John on the condition that the sale is completed within eight weeks. 1. Approval to award the contract for project management and quantity surveyor service for Primrose Gardens to Pick Everard under the Scape framework to a contract value of £144,000. 2. Approval of the acquisition of the St John Ambulance Hall with vacant possession for the capital sum of £188,500. 3. Authorisation be delegated to the Head of Legal, Democratic and Human Resources to prepare and execute the necessary legal documentation to complete the purchase of the St John ambulance Hall 4. Approval for the payment of £770 stamp duty plus the legal fees for St John on the condition that the sale is completed within eight weeks. Reasons for recommendation(s) To enable the Primrose Gardens Project to continue and be delivered to timescales ensuring Eric Wright Construction deliver a high quality development with value engineering throughout the process to ensure costs are contained within budget. Alternative options considered and rejected None
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
Report of Meeting Date Chief Executive Officer (Introduced by the Executive Executive Cabinet 8th December Member for Customer and Advice 2016 Services )
APPOINTMENT OF CONSULTANTS FOR PRIMROSE GARDENS AND AUTHORISATION OF THE PURCHASE OF THE ST JOHN AMBULANCE BUILDING
PURPOSE OF REPORT 1. To provide an update on the commission of professional consultancy services for Primrose Gardens retirement living(extra care) scheme on Fleet Street and seek approval to award the contract to Pick Everard.
2. To confirm the outcome of the negotiations regarding the sale of the St John Ambulance Hall building to the Council as part of the land assembly for the development of Primrose Gardens Retirement living scheme.
RECOMMENDATION(S)
3. To approve the award of the contract for project management and quantity surveyor service to Pick Everard under the Scape framework to a contract value of £144,000.
4. To approve the acquisition of the St John Ambulance Hall with vacant possession for the capital sum of £188,500. Authority be delegated to the Head of Legal Democratic and HR Services to prepare and execute the necessary legal documentation to complete the purchase.
5. To approve the payment of £770 stamp duty plus also St John legal fees on the condition that the sale is completed within 8 weeks.
Confidential report Yes No Please bold as appropriate
Key Decision? Yes No Please bold as appropriate
Reason 1, a change in service 2, a contract worth £100,000 Please bold as appropriate provision that impacts upon or more the service revenue budget by £100,000 or more 3, a new or unprogrammed 4, Significant impact in capital scheme of £100,000 or environmental, social or more physical terms in two or more wards
REASONS FOR RECOMMENDATION(S) (If the recommendations are accepted) 6. To enable the Primrose Gardens Project to continue and be delivered to timescales ensuring Eric Wright Construction deliver a high quality development with value engineering throughout the process to ensure costs are contained within budget.
ALTERNATIVE OPTIONS CONSIDERED AND REJECTED 7. None
CORPORATE PRIORITIES
8. This report relates to the following Strategic Objectives:
Involving residents in improving their local A strong local economy area and equality of access for all Clean, safe and healthy communities X An ambitious council that does more X to meet the needs of residents and the local area
9. Primrose Gardens is the Councils retirement living/extra care scheme which has been awarded HCA Care and Specialised Housing Grant and secured planning permission in July 2016.
10. The council gave the scheme the go-ahead in September 2016 and this included allocating a budget for professional fees to support the delivery of the project, to ensure that we have the expertise necessary.
11. The design team have been refining the designs, undertaking further specialist survey work and the acquisition of the St John Ambulance building is now in process and will be complete by early January 2017.
12. The council have instructed Hill Dickinson Solicitors to produce the Pre Construction Agreement t and this draft document is now with all parties for comment and amend and once approved by Executive Member, it will be signed.
13. Therefore it is necessary to engage the service of professional consultants who have the expertise to support the project delivery by providing capacity and skills in areas which are not available in-house.
SCAPE FRAMEWORK
14. It is proposed that the professional consultants will be procured using the Scape Procure framework. Scape is a public-sector owned, private company that is wholly owned by six Local Authority shareholders. This means they can act as a Contracting Authority with the ability to procure Framework Contracts for Public Sector bodies.
15. Scape are a non-profit-making and have a strong commitment to investing in social and community projects and have a proven track record of delivery.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.