Governance Committee, Wednesday 20 September 2017 at 2.30pm

Internal Audit Progress Report as at 28 July 2017

Agreed Committee 1 paper

Governance Committee agreed this item on Wednesday 20 September 2017. Below is the council's own wording, with the papers it was decided on.

Item17.G.102

Resolved

It was agreed with SMT that Internal Audit would provide support with the development/enhancement of key risk registers including; the Corporate Risk Register, Corporate Plan Projects and Key Partnerships. Whilst these risk registers were at various stages of development, there were currently over 190 individual risks being continuously reviewed and monitored by the risk owners. The committee was assured that good progress was being made. The Chief Finance Officer reminded the Committee of a previous issue regarding the CIL system. Members were reassured that controls put in place to mitigate this had improved the issue significantly in the past year. RESOLVED – That the report be noted.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Governance Committee

Background

6. This is the first progress report for 2017/18 and covers the period between 1st April 2017 and 28th July 2017. INTERNAL AUDIT PLANS

7. Appendix 1 provides a ‘’snapshot’’ of the overall progress made in relation to the 2017/18 Internal Audit Plans, indicating which audits have been completed and their assurance rating, those that are in progress and those that have yet to start. Appendix 1 also shows the time planned and actually spent on individual audits.

8. The table below highlights the main pieces of work undertaken during the period together with any control issues identified, where applicable;

Audit Assurance Comments Area Rating Chorley Council

Annual Not Proactive input was provided in collating Governance applicable information to inform the Annual Governance Statement Statement.

Waste Contract Not Project team support is being provided to ensure Procurement applicable that proportionate governance, risk management and control processes are in place for the procurement exercise.

Review of Pending Audit in progress. Results to be presented to Transport January Governance Committee.

General Data Not We are supporting the ICT & Programme Protection applicable Manager in preparation for the introduction of Regulations GDPR in 2018. (GDPR)

Homelessness Pending Audit in progress. Results to be presented to January Governance Committee.

Primrose Garden & Not Project team support to ensure that the risks are Retirement Village applicable being appropriately identified, recorded and monitored.

Market Walk Pending Audit in progress. Results to be presented to January Governance Committee.

Community Amber (14) No key control issues identified Infrastructure Levy Shared Services

Internal Audit of the Not We undertook a “light touch” internal inspection to Financial & applicable provide the Joint Committee with assurance in Assurance Shared respect of the integrity of the partnership’s year- Services Annual end financial statements Accounts 2016/17 CONTROLS ASSURANCE KEY

Control Rating Limited 4 8 12 16

Control Rating Limited - the Authority cannot place sufficient reliance on the controls. Adequate 3 7 11 15 Substantive control weaknesses exist. Adequate - the Authority can Substantial 2 6 10 14 place only partial reliance on the controls. Some control issues need Full 1 5 9 13 to be resolved. Substantial - the Authority can place Minor Standard Major Critical sufficient reliance on the controls. Only minor control weaknesses Risk Rating exist. Full – the Authority can place Risk Rating complete reliance on the controls. No control weaknesses exist. Minor, Standard, Major or Critical reflects the relative risk of each system and the impact on the Council if it was to fail. The risk rating for each audit has been agreed following a detailed risk assessment by Internal Audit and approval by Senior Management.

INTERNAL AUDIT PERFORMANCE

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Progress Report as at 28 July 2017Report 509 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
PL
Councillor Paul LeadbetterChair, present
AG
Councillor Anthony GeeVice-Chair, present
JC
Councillor Jean CronshawCommittee Member, present
AC
Councillor Alan CullensCommittee Member, present
GF
Councillor Gordon FranceCommittee Member, apologies
DG
Councillor Danny GeeCommittee Member, present
DP
Councillor Debra PlattCommittee Member, present
KS
Councillor Kim SnapeCommittee Member, present
GH
Gary HallOfficer, in attendance
SG
Susan GuinnessOfficer, expected
CM
Chris MoisterOfficer, in attendance
GB
Garry BarclayOfficer, expected

All 17 on the meeting page

On this subject at Chorley

Search all
  1. Internal Audit Progress Report as at 28 July 2017This decision
  2. Internal Audit Annual Report and Opinion 2025-2026 ~ Chorley LeisureNoted
  3. Internal Audit Charter and Strategy UpdateApproved
  4. Internal Audit Annual Report and Opinion 2025/2026Noted
  5. Internal Audit - Compliance with the Global Internal Audit StandardsNoted
  6. Internal Audit Plan April - September 2026Approved

More from Chorley Governance Committee

All decisions
MeetingDecisionOutcome
19 Mar 2025 Minutes of meeting Wednesday, 22 January 2025 of Governance Committee(Unanimously) That the minutes of the last meeting, held on Wednesday 22 January 2025, be signed as an accurate recor... Decided Open
19 Mar 2025 Minutes of meeting Monday, 24 February 2025 of Governance Committee - Constitution Working Group(Unanimously) That the minutes of the Governance Committee – Constitution Working Group, held on Monday 24 February 2... Noted Open
19 Mar 2025 Internal Audit Plan April - September 2025(Unanimously) That the Committee approve the internal audit plan for April – September 2025. Approved Open
19 Mar 2025 Global Internal Audit Standards in the UK Public Sectorthat the report be noted. Noted Open
19 Mar 2025 Annual Review of Risk Management Strategy(Unanimously) That the Committee approves the revised Risk Management Strategy and requests that regular updates and ... Approved Open