Revenue and Capital Budget Monitoring 2017/18 Report 3 (end of December 2017)

Noted Executive 5 papers

Executive Cabinet noted this item on Thursday 15 February 2018. Below is the council's own wording, with the papers it was decided on.

Item18.EC.15

Resolved

That the full year forecast position for the 2017/18 revenue budget and capital investment programme be noted. 2. That the forecast position on the Council’s reserves be noted. 3. That Council be requested to approve the contribution of £60,000 from in-year revenue underspends to the Buildings Maintenance Reserve to finance one-off costs relating to the Council’s maintenance of offices and buildings. 4. That the Council be requested to approve the contribution of £100,000 from in-year revenue underspends to the Change Management Reserve to finance one-off redundancy and pension strain costs arising from transformation and shared services strategies. 5. Approval for the contribution of £40,000 from in-year revenue underspends to fund the revenue implications of future planning appeals. 6. Approval for the use of £40,000 from in-year revenue underspends to provide the council with external expertise for the furthering of income generation. 7. That Council be requested to approve the contribution of £130,000 from in-year revenue underspends to enable the modernisation of the Council’s ICT and Streetscene services. 8. That Council be requested to approve the budget changes to the capital programme outlined in paragraph 70 of he report. 1. That the full year forecast position for the 2017/18 revenue budget and capital investment programme be noted. 2. That the forecast position on the Council’s reserves be noted. 3. That Council be requested to approve the contribution of £60,000 from in-year revenue underspends to the Buildings Maintenance Reserve to finance one-off costs relating to the Council’s maintenance of offices and buildings. 4. That the Council be requested to approve the contribution of £100,000 from in-year revenue underspends to the Change Management Reserve to finance one-off redundancy and pension strain costs arising from transformation and shared services strategies. 5. Approval for the contribution of £40,000 from in-year revenue underspends to fund the revenue implications of future planning appeals. 6. Approval for the use of £40,000 from in-year revenue underspends to provide the council with external expertise for the furthering of income generation. 7. That Council be requested to approve the contribution of £130,000 from in-year revenue underspends to enable the modernisation of the Council’s ICT and Streetscene services. 8. That Council be requested to approve the budget changes to the capital programme outlined in paragraph 70 of he report. Reasons for recommendation(s): To ensure the Council’s budgetary targets are achieved. Ensuring cash targets are met maintains the Council’s financial standing. Alternative options considered and rejected: None.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Report of Meeting Date Chief Finance Officer (Introduced by the Executive Executive Cabinet 15 February 2018 Member for Resources)

REVENUE AND CAPITAL BUDGET MONITORING 2017/18 REPORT 3 (END OF DECEMBER 2017)

PURPOSE OF REPORT 1. This report sets out the provisional revenue and capital outturn figures for the Council as compared against the budgets and efficiency savings targets set for the financial year 2017/18.

RECOMMENDATION(S) 2. Note the full year forecast position for the 2017/18 revenue budget and capital investment programme.

3. Note the forecast position on the Council's reserves.

4. Budget virements over £50,000 require the approval of full Council. Request Council approval for the contribution of £60,000 from in-year revenue underspends to the Buildings Maintenance Reserve to finance one-off costs relating to the Council’s maintenance of offices and buildings.

5. Request Council approval for the contribution of £100,000 from in-year revenue underspends to the Change Management Reserve to finance one-off redundancy and pension strain costs arising from transformation and shared service strategies.

6. Request Executive Cabinet approval for the contribution of £40,000 from in-year revenue underspends to fund the revenue implications of future planning appeals.

7. Request Executive Cabinet approval for the use of £40,000 from in-year revenue underspends to provide the council with external expertise for the furthering of income generation.

8. Request Council approval for the contribution of £130,000 from in-year revenue underspends to enable the modernisation of the Council’s ICT and Streetscene services.

9. Request Council approve the budget changes to the capital programme outlined in paragraph 70.

EXECUTIVE SUMMARY OF REPORT

10. The projected revenue outturn currently shows a forecast underspend of £431,000 against budget. No action is required at this stage in the year. 11. The latest forecast excludes any variation to projected expenditure on investment items added to the budget in 2017/18. These projects are forecast to fully expend in 2017/18 and should there be any balances remaining at year end they will be transferred into specific reserves and matched to expenditure in future years.

12. In the 2017/18 budget the expected net income from Market Walk after deducting financing costs is £0.998m. The latest projection shows an overspend of £17k that includes £117k of revenue expenditure relating to the Market Walk Extension project including £70k cost of the temporary parking arrangements at the Flat Iron Car Park. These costs will be mostly met from underspends in the Market Walk revenue expenditure budget.

13. The forecast of capital expenditure in 2017/18 is £18.715m.

14. The Council’s Medium Term Financial Strategy proposed that working balances are to reach £4.0m over the 3 year lifespan of the MTFS to 2018/19 due to the financial risks facing the Council. A budgeted contribution into General Balances of £500k is contained within the budget for 2017/18. The current forecast to the end of December shows that the General Fund balance will be £4.008m by the end of the financial year and be on target to achieve £4m a year early.

Confidential report Yes No Please bold as appropriate

Key Decision? Yes No Please bold as appropriate

Reason 1, a change in service 2, a contract worth £100,000 Please bold as appropriate provision that impacts upon or more the service revenue budget by £100,000 or more 3, a new or unprogrammed 4, Significant impact in capital scheme of £100,000 or environmental, social or more physical terms in two or more wards

REASONS FOR RECOMMENDATION(S) (If the recommendations are accepted) 15. To ensure the Council’s budgetary targets are achieved. Ensuring cash targets are met maintains the Council’s financial standing.

ALTERNATIVE OPTIONS CONSIDERED AND REJECTED 16. None

CORPORATE PRIORITIES

17. This report relates to the following Strategic Objectives:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
General Fund SummaryAppendix 1 53 KB Download
PDF
Investment BudgetsAppendix 2 91 KB Download
PDF
Analysis of Reserves & ProvisionsAppendix 3 57 KB Download
PDF
Capital ProgrammeAppendix 4 49 KB Download
PDF
Revenue and Capital Budget Monitoring 2017/18 Report 3 (end of December 2017)Report 227 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 27 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, present
PW
Councillor Paul WalmsleyCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
GD
Councillor Graham DunnCommittee Member, present
JW
John WalkerObserver, apologies
GH
Gary HallOfficer, in attendance
CS
Chris SinnottOfficer, expected
AK
Asim KhanOfficer, in attendance
ML
Mark LesterOfficer, in attendance
RH
Rebecca HuddlestonOfficer, in attendance

All 27 on the meeting page

On this subject at Chorley

Search all
  1. Revenue and Capital Budget Monitoring 2017/18 Report 3 (end of December 2017)This decision
  2. Revenue Budget 2026/27 Medium Term Financial Strategy and Capital Programme 2026-2029Approved
  3. Revenue Budget 2025/26, Medium Term Financial Strategy and Capital Programme 2025-2028Approved
  4. Revenue Budget 2024/25, Medium Term Financial Strategy and Capital Programme 2024-2027Approved
  5. Revenue Budget 2023/24, Medium Term Financial Strategy and Capital Programme 2023-2026Approved
  6. Revenue Budget 2022/23, Medium Term Financial Strategy and Capital Programme 2022-2025Approved

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies