Resolved
RESOLVED – That the Internal Audit Annual Report for 2017/18 be noted.
Governance Committee noted this item on Wednesday 30 May 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Internal Audit Annual Report for 2017/18 be noted.
5. That the Internal Audit Annual Report for 2017/18 be noted.
EXECUTIVE SUMMARY OF REPORT 6. The Public Sector Internal Audit Standards require the Head of Shared Assurance to provide an opinion on the overall adequacy and effectiveness of the organisation’s framework of control, risk management and governance.
7. Control – The Internal Audit Service provides an independent opinion on the adequacy of the internal control system. All recommendations for improvement are agreed with Senior Management and a summary is reported to the Governance Committee. Only one Internal Audit report with a limited controls assurance rating was issued during 2017/18.
8. Risk Management – the Council’s arrangements were further strengthened during 2017/18 by the continued development of the GRACE risk management system. Extensive training was delivered to Officers and the revised Risk Management Framework was approved by the Governance Committee in March.
9. Governance – actions have been taken during 2017/18 to strengthen the Council’s governance arrangements. The Annual Governance Statement Action Plan for 2018/19 includes details of actions to further strengthen Council’s governance arrangements. The 2018 AGS has been produced following a rigorous assessment process, both internal and external.
Confidential report Yes No Please bold as appropriate CORPORATE PRIORITIES
10. This report relates to the following Strategic Objectives:
Involving residents in improving their local A strong local economy area and equality of access for all Clean, safe and healthy homes and An ambitious council that does more x communities to meet the needs of residents and the local area
INTERNAL AUDIT PLANS
11. Appendix 1 to this report provides a detailed account of the individual audits undertaken in respect of Chorley Council and Shared Services during the 2017/18 financial year. A summary of any actions that have been agreed with management to further improve controls within all the areas audited is also included within the appendix.
12. The following tables also provide an analysis of the planned and actual auditor days used during the year together with an explanation of any variations that have occurred.
Chorley Council
Planned Actual Variance (Days) (Days) (Days) Audits undertaken 255 231 (24) Audits not undertaken Commercial Properties 15 1 (14)
Contingency 90 111 21 TOTALS 360 343 (17)
13. With regard to audits not undertaken, the review of Commercial Properties has been carried forward to 2018-19 to allow time for the new officer structure to embed.
Shared Services
Planned Actual Variance (Days) (Days) (Days) Audits undertaken 75 76 (1) Contingency 45 43 2 TOTALS 120 119 (1)
CONTROLS ASSURANCE
14. Public Sector Internal Audit Standards (PSIAS) require the “Head of Internal Audit” to give an opinion on the overall adequacy and effectiveness of the Council’s framework of governance, risk management and control. This responsibility falls on the Head of Shared Assurance Services on behalf of Chorley Council.
15. Members will recall that individual audits are awarded a separate controls assurance rating from the following matrix: Critical 4 8 12 16
Risk Rating Major 3 6 9 12
Standard 2 4 6 8
Minor 1 2 3 4
Full Substantial Adequate Limited Control Rating
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Peer Review of Internal Audit against the UK Public Sector Internal Audit StandardsAppendix 1 | 126 KB | Download |
PDF |
Internal Audit Annual Report 2017/18Report | 213 KB | DownloadRead as text |
Follow Governance Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2025 | Minutes of meeting Wednesday, 22 January 2025 of Governance Committee(Unanimously) That the minutes of the last meeting, held on Wednesday 22 January 2025, be signed as an accurate recor... | Decided | Open |
| 19 Mar 2025 | Minutes of meeting Monday, 24 February 2025 of Governance Committee - Constitution Working Group(Unanimously) That the minutes of the Governance Committee – Constitution Working Group, held on Monday 24 February 2... | Noted | Open |
| 19 Mar 2025 | Internal Audit Plan April - September 2025(Unanimously) That the Committee approve the internal audit plan for April – September 2025. | Approved | Open |
| 19 Mar 2025 | Global Internal Audit Standards in the UK Public Sectorthat the report be noted. | Noted | Open |
| 19 Mar 2025 | Annual Review of Risk Management Strategy(Unanimously) That the Committee approves the revised Risk Management Strategy and requests that regular updates and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.