Resolved
Decision deferred to allow members of the Development Control Committee the opportunity to visit the site of the proposals.
Development Control Committee deferred this item on Tuesday 6 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision deferred to allow members of the Development Control Committee the opportunity to visit the site of the proposals.
1. It is recommended that planning permission be granted subject to conditions and a Section 106 Obligation to secure the provision of a commuted sum for the provision of new play equipment at King George V Play Area.
SITE DESCRIPTION
2. The application site is located on land to the south of Rawlinson Lane between a railway line to the east and existing residential development to the west. It is located within the settlement area of Adlington and is currently accessed via a short road currently serving three properties.
3. Whilst bordered by trees, a large majority of the site is covered by hardstanding, with the site previously being used intermittently for storage purposes, and more recently as a base for Network Rail contractors to carry out works to the railway. The site is long and narrow at approximately 20m in width, extending to approximately 285m in length.
4. The character of the surrounding area is residential and consists largely of modern detached dwellings with more traditional terraced and semi-detached dwellings to the west of the site facing Westhoughton Road. The railway line to the east of the site is a notable feature in the context of the application site. It is noted that permission has been previously granted, in 2016, for the erection of two dwellings to the north of the application site (application ref 16/00498/FUL) adjacent to no.3 Mercer Court.
DESCRIPTION OF PROPOSED DEVELOPMENT
5. The application seeks planning permission for the erection of 7no. dwellings and associated works. Access would be taken from Mercer Court and the dwellings would be set out in a linear arrangement along an access drive with a turning head to the far south of the site. The dwellings themselves would be of a traditional design style although their scale would be similar to that of a dormer bungalow. The parking and gardens would be positioned to the sides of the proposed dwellings. REPRESENTATIONS
6. Representations in objection to the proposed development have been received from the occupiers of 8 addresses. These raise the following issues: Impact on drainage and flooding on the proposed properties and existing properties. The gardens to the rear of Westhoughton Road flood due to the presence of a natural underground water supply. Impact on wildlife. Existing issues of noise, dust and air pollution from railway engineering works. The ground is clay, which impedes natural drainage. Water flows from gardens to the west of the site onto the application site. If approved no work should take place during the summer. The area is an area at risk of flooding. If surface water is prevented from draining onto the application site from gardens to the west then the dwellings along Westhoughton Road would be affected. Inadequate local electricity supply to support more dwellings. Impact on highway safety.
CONSULTATIONS
7. Regulatory Services - Environmental Health: Have no objection subject to conditions.
8. Waste & Contaminated Land: Have no objection subject to a condition.
9. Lancashire Highway Services: Have no objection subject to conditions.
10. Lead Local Flood Authority: Have no objection.
11. United Utilities: Have no objection subject to conditions.
12. Network Rail: Objection to the layout of the dwellings in relation to the less than 2m gap from the railway boundary.
13. Greater Manchester Ecology Unit: Have no objection.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
18/00191/FUL: Land Rear of 24/26 Westhoughton Road, AdlingtonReport | 92 KB | DownloadRead as text |
PDF |
Item 3a Location PlanPlan | 260 KB | Download |
Follow Development Control Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2019 | Minutes of meeting Tuesday, 18 June 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 18 June 2019 be approved as a correct record... | Approved | Open |
| 16 Jul 2019 | 19/00417/FULMAJ - Land Adjoining Cuerden Residential Park, Nell Lane, CuerdenFull planning permission granted, subject to conditions and a Section 106 legal agreement. | Agreed | Open |
| 16 Jul 2019 | 19/00325/FUL - Playing Field, Kem Mill Lane, Whittle-le-WoodsFull planning permission granted, subject to conditions. | Decided | Open |
| 18 Jun 2019 | Minutes of meeting Tuesday, 21 May 2019 of Development Control CommitteeDecision – That the minutes of the Development Control Committee held on 21 May 2019 be approved as a correct record ... | Approved | Open |
| 18 Jun 2019 | 18/00108/FULMAJ - Chorley Rugby Union Club, Chancery Road, Astley Village, ChorleyFull planning permission granted, subject to conditions and a supplemental Section 106 Agreement. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.