25/00503/FULMAJ - Land To The West Side Of Blackburn Road Chorley

Approved Planning 3 papers

AI summaryChorley planning committee approves temporary open storage use on part of the Botany Hill industrial business park for up to two years, with conditions on lighting, access hours and engine idling.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTemporary B8 storage for up to two years
MoneyNot stated
What happens nextBiodiversity Gain Plan required before commencementOff-site units to deliver 10% net gain
Who it affectsLand west of Blackburn Road, ChorleyAbout 2 hectares of the Botany Hill site

What was decided

Planning permission was granted for a temporary Class B8 outdoor storage use on approximately 2 hectares, divided into four compounds with 2.4 metre fencing. Report P7

The committee approved a two year temporary period rather than the three years recommended by officers, requiring condition 3 to be reworded. Report P1, P65

Conditions restrict access and lighting hours, require engines to be switched off while vehicles are stationary, and control the eventual removal of fencing and lighting. Report P67, P69, P71, P65

Why

Officers judged the proposal an acceptable meanwhile use on land allocated for significant employment development, with limited noise, lighting and traffic impact and no harm to neighbour amenity. Report P28, P42, P44, P46

The site already has planning permission for industrial buildings, so the temporary storage would not undermine the longer term development of the allocation. Report P28, P35

The Lead Local Flood Authority, Lancashire Highway Services, Regulatory Services and the Council's ecology officer (MEAS) raised no objections, subject to standard and BNG conditions. Report P11, P12, P13, P14

What happens next

A mandatory pre-commencement Biodiversity Gain Plan must be submitted and approved before development can begin, delivering at least 1.593 habitat units and 0.063 hedgerow units off site. Report P50, P51

The use, fencing and lighting must be removed by the expiry date set in the reworded condition 3. Report P65

Options considered

  • Rejected: Approve temporary B8 storage for up to three years as recommended by officers. Committee approved a shorter two year period and required condition 3 to be reworded Report P1
  • Rejected: Refuse planning permission. Officers found no unacceptable impact and the proposal supported economic development as a meanwhile use Report P42, P53

Implications

  • Legal: The grant is subject to the statutory biodiversity gain condition under Schedule 7A of the Town and Country Planning Act 1990. Report P47, P50
  • Equalities: The site is level and accessible, with visits expected to be rare, so disability access provision is considered acceptable. Report P38
  • Climate: Biodiversity Net Gain of at least 10% must be achieved off site through purchase of units or a habitat bank, as the site cannot deliver it on site. Report P50
  • Risk: Objections raised concerns about increased traffic, noise, antisocial behaviour and visual impact, which officers considered limited given the temporary, low intensity nature of the use. Report P9, P35, P44
  • Other: The decision supports the phased build out of the wider Botany Hill industrial business park by putting phase 2 land to short term use. Report P7, P23, P28

Who and where

  • The applicant and businesses seeking short term storage of vehicles, trucks, parts, plant and machinery Report P7, P23
  • Nearby residents on Blackburn Road, over 30 metres away and at a higher level Report P44, P45
  • Users of the public right of way running east to west along the southern boundary Report P5
  • Future developers of phase 2 of the Botany Hill industrial business park Report P7, P28

Timeline

  • 30 April 2024: Outline planning permission 22/01243/FULMAJ granted for the wider employment development Report P55
  • 30 June 2025: Central Lancashire Local Plan submitted to the Secretary of State Report P16
  • 8 September 2026: Planning Committee resolved to approve the temporary storage use subject to reworded condition 3
  • By the date in reworded condition 3: Use must cease and fencing and lighting removed Report P65

Plain English for the jargon

  • BNG (Biodiversity Net Gain): A requirement for development to deliver at least a 10% increase in biodiversity value compared with the pre-development baseline.
  • Use Class B8: Planning use class covering storage or distribution, including open storage.
  • Meanwhile use: A temporary use of land that is awaiting longer term development.
  • MEAS: Chorley Council's ecology advisor who reviewed the BNG information.
  • LCC Highways: Lancashire County Council Highways, the local highway authority.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22b

Resolved

Planning permission approved for the temporary use of land for up to two years subject to conditions including the appropriate rewording of condition 3.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Planning Committee

Recommendation

1. It is recommended that planning permission for the temporary use of land for up to 3 years is approved subject to conditions.

SITE DESCRIPTION

2. The application site is located within the settlement area of Chorley and forms part of a wider site allocated for either housing or employment use in the Chorley Local Plan 2012 – 2026.

3. The application site comprises approximately 2ha of a 7.05ha industrial business park development that was previously agricultural land and is now an engineered development platform following ground preparation works for the industrial development approved under planning permission 22/01243/FUL.

4. The site lies to the north east of J8 of the M61. It is bounded by Blackburn Road to the east and the developing part of the industrial business park to the west. Agricultural land lies both to the north and south of the site. A public right of way runs east to west adjacent to the southern boundary of the site. The site occupies a lower level relative to Blackburn Road and rises up from Millenium Way.

5. A vehicular access has been constructed from the A674 Millennium Way that provides access into the industrial business park, known as Botany Hill, the development of which is progressing through the engineering of development platforms across the site and erection of several industrial warehouse buildings.

DESCRIPTION OF PROPOSED DEVELOPMENT 6. This application seeks planning permission on part of the Botany Hill industrial business park site for a temporary storage use under Class B8 for a period of up to 3 years. This would comprise outdoor storage areas enclosed by a 2.4m high security fence and gated access with the site divided into four separate storage compounds. The use sought is for the storage of commercial vehicles, trucks, parts, plant and machinery. This would support the phased approach that is being taken in relation to the industrial business park development by seeking to make best use of available land between the development of phases (phase 1 to the west of the site being built out first and the area of the application site being phase 2 to be built out at a later date).

REPRESENTATIONS

7. One representation in objection has been received raising the following concerns: • Increase traffic movements resulting in noise and pollution. • The development would attract antisocial behaviour. • Impact on the appearance of the site and character of the area.

CONSULTATIONS

8. MEAS: the BNG information is accepted.

9. Regulatory Services - Environmental Health: No objections.

10. Lancashire Highway Services: do not object to the proposed temporary use.

11. Lead Local Flood Authority: has no comments to make on the above application, as the proposed development has no surface water implications, given the nature of the development, which is for the installation of security fencing and gate access and this application forms part of the 22/01243/FULMAJ development site.

PLANNING CONSIDERATIONS

12. The Central Lancashire authorities (South Ribble, Chorley and Preston) are preparing a new development plan: the Central Lancashire Local Plan (CLLP) 2023-2041. Preparation of the plan must be undertaken in accordance with a series of stages set through the Town and Country Planning (Local Planning) (England) Regulations 2012. In accordance with those regulations, Chorley Council agreed to the publication of the CLLP prior to its formal submission to the Secretary of State (SoS) for examination. The Plan was submitted to the SoS on 30 June 2025.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/00503/FULMAJ: Land To The West Side Of Blackburn Road ChorleyReport 143 KB DownloadRead as text
PDF
3b: Location PlanPlan 240 KB Download
PDF
3b: PresentationReport 2.6 MB Download

At this meeting

Whole meeting

Who was there

11 of 24 attended
JM
Councillor June MolyneauxChair, present
RG
Councillor Russ GreenVice-Chair, present
SA
Councillor Sarah AinsworthCommittee Member, present
LD
Councillor Lesley DuroseCommittee Member, present
AH
Councillor Alex HiltonCommittee Member, present
AS
Councillor Arjun SinghCommittee Member, present
CS
Councillor Chris SnowCommittee Member, present
CS
Councillor Craige SouthernCommittee Member, present
MT
Councillor Martin ToppCommittee Member, present
AW
Councillor Alan WhittakerCommittee Member, present
KW
Councillor Katie WilkieCommittee Member, present
KF
Kevin FosterOfficer, expected

All 24 on the meeting page

On this subject at Chorley

Search all
  1. 25/00503/FULMAJ - Land To The West Side Of Blackburn Road ChorleyThis decision
  2. 26/00314/FULMAJ - Land Off Wigan Road And Parkhurst Avenue Clayton Le WoodsAgreed
  3. 25/01051/FULMAJ - Land to the West Side of Preston Road, CoppullAgreed
  4. 25/001051/FULMAJ - Land to the West Side of Preston Road, CoppullDeferred
  5. 25/00717/FULMAJ - Land At Barnes Wallis Way Buckshaw VillageDecided
  6. 25/00107/FULMAJ Land To The North West Of Botany Canal BridgeApproved

More from Chorley Planning Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Minutes of meeting Tuesday, 4 August 2026 of Planning Committeethat the minutes of meeting Tuesday, 4 August 2026 of the Planning Committee were approved as a correct record. Approved Open
8 Sep 2026 25/01052/FULMAJ - Moor Road, CrostonPlanning permission was minded to be refused for the following reason: ‘The application is contrary to policy 1 of th... Refused Open
8 Sep 2026 Appeals Reportthat the be noted. Noted Open
4 Aug 2026 Minutes of meeting Tuesday, 7 July 2026 of Planning CommitteeMinutes approved. Approved Open
4 Aug 2026 25/01052/FULMAJ - Moor Road, CrostonDecision deferred for further consideration of and information relating to: · The relationship to, and impact of, the... Deferred Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies