Chorley Borough Council
Executive Cabinet, Thursday 12 November 2020 at 6.30pm

Update on and contract award for Astley Hall conservation work

Noted Executive 7 papers

Executive Cabinet noted this item on Thursday 12 November 2020. Below is the council's own wording, with the papers it was decided on.

Item20.EC.225

Resolved

To note progress on the project and timescale for completion. 2. To ratify the procurement approach that was approved by executive member decision in Appendix E and F. 3. To delegate powers to award the contract for the main works to the Executive Member for Resources based on the competitive tender process. 1. To note progress on the project and timescale for completion. 2. To ratify the procurement approach that was approved by executive member decision in Appendix E and F. 3. To delegate powers to award the contract for the main works to the Executive Member for Resources based on the competitive tender process. Reasons for recommendation(s) 1. To ensure members are fully informed of progress on this project and ensure a decision is taken on the contract award in line with our formal procedures. 2. The decision on how the tender would be undertaken was taken by Executive Member Decision due to the amended timescales and to get the project back on track. The process needs to be ratified by Executive Cabinet in order to allow delegated powers for the contract award once the tenders have been returned and reviewed. Alternative options considered and rejected: No alternative options have been considered as the contract award requires ratification from Executive Cabinet to delegate the decision to the executive member to keep the project on track. The decision to undertake the work has already been agreed as part of the corporate strategy .
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Background

10. Astley Hall is a Grade I listed building situated in the beautiful grounds of Astley Park. It is a popular visitor destination and significant heritage asset for the borough having been built circa 16th century and has been under the ownership of the council for almost 100 years.

11. Like most historic buildings the Hall requires significant work to conserve it for future generations and we are at that point in time, roughly every 70 years, when major work needs to be done to maintain the building.

12. The most significant area needing attention is the front of the building where the render has been failing for some time and the window frames are in a poor state of repair.

13. The council has been planning this work for a number of years and had submitted two Heritage Lottery Fund (HLF) bids to secure funding for the repairs but was unsuccessful on both occasions.

14. In 2019 the council agreed to fund the work itself given the huge importance to the local area and work has been continuing since then to put plans in place for the improvements.

15. The process has been delayed by the Covid-19 pandemic and having secured Listed Building Consent in October work is planned to start on site by the New Year with a completion date in the summer.

WORKS TO ASTLEY HALL

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Update on and contract award for Astley Hall conservation workAppendix A 169 KB Download
PDF
for Update on and contract award for Astley Hall conservation workAppendix B 127 KB Download
PDF
for Update on and contract award for Astley Hall conservation workAppendix C 270 KB Download
PDF
for Update on and contract award for Astley Hall conservation workAppendix D 615 KB Download
PDF
for Update on and contract award for Astley Hall conservation workAppendix E 251 KB Download
PDF
for Update on and contract award for Astley Hall conservation workAppendix F 111 KB Download
PDF
Update on and contract award for Astley Hall conservation workReport 272 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 27 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, present
GD
Councillor Graham DunnCommittee Member, present
AM
Councillor Alistair MorwoodCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
GH
Gary HallOfficer, in attendance
CS
Chris SinnottOfficer, in attendance
AK
Asim KhanOfficer, in attendance
ML
Mark LesterOfficer, in attendance
CM
Chris MoisterOfficer, in attendance
JT
James ThomsonOfficer, in attendance

All 27 on the meeting page

On this subject at Chorley

Search all
  1. Update on and contract award for Astley Hall conservation workThis decision
  2. Yarrow Valley Play Area Evaluation Criteria and Contract Award Delegation.Approved
  3. Water Supply Contract - Contract AwardNoted
  4. Town Hall Improvement Works - Contract AwardApproved
  5. Approval for the Contract Award Procedure and Evaluation Criteria for Trade Waste Collections from Council Buildings and MarketsApproved
  6. Approval to Procure and Award Contract to undertake Reconfiguration Works to Strawberry Fields Digital OfficeApproved

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies