Resolved
The report was noted
Overview and Scrutiny Committee noted this item on Thursday 18 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
The report was noted
1. To update members on progress made on the recommendations of the Task Group on Developing the Council’s Green Agenda
Recommendation(s) 2. To note the contents of the report.
Executive summary of report
3. The final report of the Task Group for the Green Agenda was presented to Executive Cabinet in March 2020 and it was agreed that an action plan be developed to expedite the green agenda as a corporate priority.
4. Funding was allocated to the project and following transfer of the project to Spatial Planning in September 2020, a plan was devised to develop a programme which pulled together of all the Councils strands of activity relating to the green agenda, the recruitment of a dedicated officer was undertaken and, the member-led, Climate Change Working Group was established.
Confidential report Yes No Please bold as appropriate
Corporate priorities
5. This report relates to the following Strategic Objectives:
Involving residents in improving their local A strong local economy area and equality of access for all Clean, safe and healthy homes and X An ambitious council that does more X communities to meet the needs of residents and the local area
6. The general update is that the inaugural meeting of the member-led Climate Change Working Group met on the 22nd February 2021 and along with terms of reference, the meeting agenda included an update from officers as to the overall programme for Climate Change and the start of a discussion about key areas of focus for this agenda for the Council. The Climate Change Programme Officer started in role on 8th March 2021 and is part of the Spatial Planning Team where overall responsibility for this work sits.
7. The table below lists all the 24 recommendations made by the Task Group. For clarity, these have been extracted from the overall programme of activity for Climate Change, to ensure that this committee can clearly see where these recommendations have been progressed. The programme as whole includes additional strands of work.
8. Progress to-date is detailed in the update column and it is worth noting that as many of these will be delivered or led by the new Climate Change Programme Officer, a number of these actions are to commence, however momentum will now accelerate with much more progress to be expected by the next monitoring report.
9. The Climate Officer will engage with leads for actions where responsibility is in other directorates and ensure these are incorporated into business plans for the coming year.
Summary Table of Recommendations and Progress
Recommendation/Action Lead Update Undertake work to map and calculate Climate Change Initial assessment complete- there is a the council’s current carbon footprint Programme need to review the findings and Officer (working undertake quality assurance with LCC and internal depts) Lancashire County Council are leading on a Lancashire Wide Project to a) Calculate the baseline carbon footprint of each of the councils’ assets b) Commission external consultants to calculate the baseline carbon footprint of all borough Commission work to develop a roadmap Climate Change Gap analysis complete but still further and action plan towards achieving Programme work to develop SMART action plan to carbon neutrality by 2030 including Officer/Local achieve 2030 net zero targets, actions, and measures Plan Coordinator Set up a council-led climate change Service Lead Completed. steering group to oversee activity and Spatial Planning provide direction /Climate Change Programme Officer Embed green considerations in all Democratic To be implemented in 2021 decision making by including a space for Services Team an environmental impact comment on all Lead Climate committee reports. Also review the Change sustainability element of the existing Programme Integrated Impact Assessment Officer /
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Overview and Scrutiny Task Group: Developing the Council's Green Agenda: Monitoring of RecommendationsAgenda | 200 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of meeting Thursday, 26 March 2026 of Overview and Scrutiny CommitteeResolved (unanimously): That the minutes of the meeting held on Thursday, 26 March 2026 be approved a correct record ... | Approved | Open |
| 2 Jul 2026 | Minutes of the Overview and Scrutiny Performance Panel held on Thursday, 25 June 2026Resolved (unanimously) – That the minutes of the Overview and Scrutiny Performance Panel, held on Thursday, 25 June 2... | Noted | Open |
| 2 Jul 2026 | Notice of Executive DecisionsResolved (unanimously) – That the latest Notice of Executive Decisions July 2026 be noted. | Noted | Open |
| 2 Jul 2026 | Chorley Leisure Scrutiny UpdateResolved (unanimously – 1. That the Executive Member for Early Intervention and the officers be thanked for their att... | Decided | Open |
| 2 Jul 2026 | Update from the Representative on the LCC Health and Adult Social Care Scrutiny CommitteeResolved (unanimously) – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.